N6339418R0009_PPS_MCP_9.12.18.pdf

PDF 621 KB Posted

Attached to
Programmable Power Supply Federal contract opportunity
Solicitation number
N6339418R0009
Issued by
Department of the Navy Naval Sea Systems Command

View the file

Other files for this federal contract opportunity

Other files attached to Programmable Power Supply, newest first.
File Type Posted
N6339418R0009-0006.pdf PDF
N6339418R0009-0005.pdf PDF
N6339418R0009-0004.pdf PDF
J-3-GFP_Attachment_N63394-18-R-0009.pdf PDF
N6339418R0009-0002.pdf PDF
0021.SRB_18R0009_PPS_CDRL_A003R.pdf PDF
0021.SRB__18R0009_PPS_CDRL_A009R.pdf PDF
0021.SRB_18R0009_PPS_CDRL_A001R.pdf PDF
Attachment_Past_Performance_LPTA.doc DOC document
0021.SRB__18R0009_PPS_CDRL_A002.R.pdf PDF
0021.SRB__18R0009_PPS_CDRL_A005R.pdf PDF
0021.SRB_18R0009_PPS_CDRL_A006R.pdf PDF
0021.SRB__18R0009_PPS_CDRL_A004R.pdf PDF
0021.SRB_18R0009_PPS_CDRL_A008R.pdf PDF
0021.SRB__18R0009_PPS_CDRL_A007R.pdf PDF
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CODE

(Hour)

PAGE(S)

until 02:00 PM local t ime 10 Oct 2018

X

A X B X C X D

EX

X

G F 57 - 66

67 - 80 X H 81 - 85 susana.dryer@navy .mil

RATING PAGE OF PAGES

7. ISSUED BY

(Date)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)

Prescribed by GSA FAR (48 CFR) 53.214(c)

DO-A3 1 85

(If other than Item 7)

15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO

AND

ADDRESS SIGN OFFER (Type or print)

OF

OFFEROR

AMENDMENT NO. DATE

15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS

IS DIFFERENT FROM ABOVE - ENTER

SUCH ADDRESS IN SCHEDULE.

18. OFFER DATE

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 700)

2. CONTRACT NO.

N63394 8. ADDRESS OFFER TO

See Item 7

9. Sealed offers in original and 0 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in

CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.

10. FOR INFORMATION

CALL:

A. NAME (NO COLLECT CALLS)

SUSANA DRYER (805)228-0626

11. TABLE OF CONTENTS

SOLICITATION/ CONTRACT FORM

SUPPLIES OR SERVICES AND PRICES/ COSTS

2 - 10

X I CONTRACT CLAUSES

DESCRIPTION/ SPECS./ WORK STATEMENT X

PACKAGING AND MARKING

11 - 19 20 - 22

J LIST OF ATTACHMENTS

INSPECTION AND ACCEPTANCE

DELIVERIES OR PERFORMANCE

23 - 26

27 - 30 X K REPRESENTATIONS, CERTIFICATIONS AND

OTHER STATEMENTS OF OFFERORS

CONTRACT ADMINISTRATION DATA 31 - 36 X

SPECIAL CONTRACT REQUIREMENTS

OFFER (Must be fully completed by offeror) 37 X M

L INSTRS., CONDS., AND NOTICES TO OFFERORS

EVALUATION FACTORS FOR AWARD

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. DISCOUNT FOR PROMPT PAYMENT

(See Section I, Clause No. 52.232-8)

14. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments

AMENDMENT NO. DATE

to the SOLICITATION for offerors and related documents numbered and dated):

FACILITY

12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period

SOLICITATION, OFFER AND AWARD

X

(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)

PART I - THE SCHEDULE

26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE

EMAIL:TEL: (Signature of Contracting Officer)

CODE CODE

B. TELEPHONE (Include area code) C. E-MAIL ADDRESS

AWARD (To be completed by Government)

19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)

23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE

PART IV - REPRESENTATIO NS AND INSTRUCTIO NS

PART III - LIST O F DO CUMENTS, EXHIBITS AND O THER ATTACHMENTS

38 - 55

PART II - CO NTRACT CLAUSES

NSWC, PORT HUENEME DIVISION

4363 MISSILE WAY,

PORT HUENEME CA 93043-4307

FAX:

TEL:

FAX:

TEL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SOLICITATION

6. REQUISITION/PURCHASE NO.5. DATE ISSUED

12 Sep 2018

4. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

[ X ]

3. SOLICITATION NO.

N6339418R0009

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Each Programmable Power Supply (PPS) FAT

FFP

Procure, fabricate, assemble and conduct First Article Testing (FAT) resulting in the delivery of one (1) PPS. The PPS shall be built in accordance with (IAW) the Statement of Work (SOW) and Technical Data Package (TDP). Refer to Contract Delivery Requirement List (CDRLs) for item and data requirements. Payment will be made as a result of successful acceptance of FAT inspection.

NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

FOB: Destination

DWG NR: 7104312-29

PSC CD: 6130

NET AMT

0002 1 Each Motor Control Panel (MCP) FAT

FFP

Procure, fabricate, assemble and conduct FAT resulting in the delivery of one (1) MCP. The MCP shall be built IAW the SOW and TDP. Refer to CDRLs for item and data requirements. Payment will be made as a result of successful acceptance of FAT inspection.

NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

FOB: Destination

DWG NR: 7103707-29

0003 1 Lot CDRLs

FFP

Prepare and maintain data IAW CDRLs A001 through A009 and Data Item Delivery (DID) schedule requirements. The Government shall have unlimited rights to all data generated under this effort IAW DFARS 252.227-7013 unless an assertion is provided and accepted by the Government with the offer IAW DFARS 252.227-7017. The price for all data generated by the contractor directly or indirectly in its performance of this procurement effort is included in the price paid by the Government under CLINs 0001 through 4002.

FOB: Destination

0004 7 Each OPTION Programmable Power Supply Production

FFP

Production Phase: Fabricate, assemble and deliver PPS, spare parts and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.

NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

FOB: Destination

0005 3 Each OPTION Motor Control Panel Production

FFP

Production Phase: Fabricate, assemble and deliver MCP, spare parts and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

FOB: Destination

1001 8 Each OPTION Programmable Power Supply Production

FFP

Production Phase: Fabricate, assemble and deliver PPS, spare parts and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.

NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

FOB: Destination

1002 4 Each OPTION Motor Control Panel Production

FFP

Production Phase: Fabricate, assemble and deliver MCP, spare parts and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.

NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

FOB: Destination

2001 8 Each OPTION Programmable Power Supply Production

FFP

Production Phase: Fabricate, assemble and deliver PPS, spare parts and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.

NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

FOB: Destination

2002 4 Each OPTION Motor Control Panel Production

FFP

Production Phase: Fabricate, assemble and deliver MCP, spare parts and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.

NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

FOB: Destination

3001 8 Each OPTION Programmable Power Supply Production

FFP

Production Phase: Fabricate, assemble and deliver PPS, spare parts and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.

NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

FOB: Destination

3002 4 Each OPTION Motor Control Panel Production

FFP

Production Phase: Fabricate, assemble and deliver MCP, spare parts and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.

NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

FOB: Destination

4001 8 Each OPTION Programmable Power Supply Production

FFP

Production Phase: Fabricate, assemble and deliver PPS, spare parts and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.

NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

FOB: Destination

4002 4 Each OPTION Motor Control Panel Production

FFP

Production Phase: Fabricate, assemble and deliver MCP, spare parts and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.

NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

FOB: Destination

CLAUSES INCORPORATED BY FULL TEXT

HQ B-2-0004 EXPEDITING CONTRACT CLOSEOUT (NAVSEA) (DEC 1995)

(a) As part of the negotiated fixed price or total estimated amount of this contract, both the Government and the Contractor have agreed to waive any entitlement that otherwise might accrue to either party in any residual dollar amount of $500 or less at the time of final contract closeout. The term "residual dollar amount" shall include all money that would otherwise be owed to either party at the end of the contract, except that, amounts connected in any way with taxation, allegations of fraud and/or antitrust violations shall be excluded. For purposes of determining residual dollar amounts, offsets of money owed by one party against money that would otherwise be paid by that party may be considered to the extent permitted by law.

(b) This agreement to waive entitlement to residual dollar amounts has been considered by both parties. It is agreed that the administrative costs for either party associated with collecting such small dollar amounts could exceed the amount to be recovered.

(End of Text)

HQ B-2-0009 NOTE (CDRL)

NOTE A - Offeror shall complete the "Price Group" and "Estimated Total Price" blocks of each data item on the Contract Data Requirements List(s), attached hereto.

HQ B-2-0010 NOTE (OPTION)

NOTE CLINs 0004, 0005, and 1001-4002 - Option item to which the option clause in SECTION I-2 applies and which is to be supplied only if and to the extent said option is exercised.

HQ B-2-0017 REFUNDS (SPARES AND SUPPORT EQUIPMENT) (NAVSEA)

(SEP 1990)

(a) In the event that the price of a spare part or item of support equipment delivered under this contract significantly exceeds its intrinsic value, the Contractor agrees to refund the difference. Refunds will only be made for the difference between the intrinsic value of the item at the time an agreement on price was reached and the contract price. Refunds will not be made to recoup the amount of cost decreases that occur over time due to productivity gains (beyond economic purchase quantity considerations) or changes in market conditions.

(b) For purposes of this requirement, the intrinsic value of an item is defined as follows:

(1) If the item is one which is sold or is substantially similar or functionally equivalent to one that is sold in substantial quantities to the general public, intrinsic value is the established catalog or market price, plus the value of any unique requirements, including delivery terms, inspection, packaging, or labeling.

(2) If there is no comparable item sold in substantial quantities to the general public, intrinsic value is defined as the price an individual would expect to pay for the item based upon an economic purchase quantity as defined in FAR 52.207-4, plus the value of any unique requirements, including delivery terms, inspection, packaging or labeling.

(c) At any time up to two years after delivery of a spare part or item of support equipment, the Contracting Officer may notify the Contractor that based on all information available at the time of the notice, the price of the part or item apparently exceeds its intrinsic value.

(d) If notified in accordance with paragraph (c) above, the Contractor agrees to enter into good faith negotiations with the Government to determine if, and in what amount, the Government is entitled to a refund.

(e) If agreement pursuant to paragraph (d) above cannot be reached, and the Navy's return of the new or unused item to the Contractor is practical, the Navy, subject to the Contractor's agreement, may elect to return the item to the Contractor.

Upon return of the item to its original point of Government acceptance, the Contractor shall refund in full the price paid.

If no agreement pursuant to paragraph (d) above is reached, and return of the item by the Navy is impractical, the Contracting Officer may, with the approval of the Head of the Contracting Activity, issue a Contracting Officer's final decision on the matter, subject to Contractor appeal as provided in the "DISPUTES" clause (FAR 52.233-1).

(f) The Contractor will make refunds, as required under this requirement, in accordance with instructions from the Contracting Officer.

(g) The Contractor shall not be liable for a refund if the Contractor advised the Contracting Officer in a timely manner that the price it would propose for a spare part or item of support equipment exceeded its intrinsic value, and with such advice, specified the estimated proposed price, the estimated intrinsic value and known alternative sources or item, if any, that can meet the requirement.

(h) This requirement does not apply to any spare parts or items of support equipment whose price is determined through adequate price competition. This requirement also does not apply to any spare part or item of support equipment with a unit price in excess of $100,000; or in excess of $25,000 if the Contractor submitted, and certified the currency, accuracy and completeness of, cost or pricing data applicable to the item.

HQ B-2-0022 CONTRACT SUMMARY FOR PAYMENT OFFICE (FIXED PRICE) (FEB 1997)

This entire contract is fixed price.

Section C - Descriptions and Specifications

STATEMENT OF WORK

STATEMENT OF WORK (SOW)

VERTICAL LAUNCHING SYSTEM (VLS)

PROGRAMMABLE POWER SUPPLY (PPS) MK 179 MOD 0

MOTOR CONTROL PANEL (MCP)

1 SCOPE

1.1 This SOW describes the requirement for the procurement, fabrication, assembly, test, final acceptance and delivery of Vertical Launching System (VLS) Programmable Power Supply (PPS) MK 179 Mod 0 Part Number (P/N) 7104312-29 and Motor Control Panel (MCP) P/N 7103707-29. The PPS provides Direct Current (DC) and routes Alternating Current (AC) power for missile relaunch and launch functions. The MCP supplies voltage output to the hatch motor drives and provides monitoring and power control for the module.

2 APPLICABLE DOCUMENTS AND STATEMENTS

2.1 The Government documents are provided in the Technical Data Packages (TDP), which will be provided as

Government Furnished Information (GFI).

2.2 Government Documents

Drawing Number Nomenclature

7104312-29 PPS

7103707-29 MCP

3 REQUIREMENTS

3.1 General Requirements

3.1.1 The Contractor shall procure, fabricate, assemble, inspect, test, and deliver the PPS, MCP and associated parts in accordance with technical drawings and specifications identified in Section C and other contents within the SOW.

3.1.2 All technical drawings and specifications used for the procurement, fabrication, assembly, test, final acceptance and delivery of PPS shall be in accordance with the latest revision, Notice of Revision (NOR) and Specification Change Notice (SCN) level identified with the TDP.

3.1.3 The Contractor shall fabricate, assemble and procure all necessary tooling and test equipment to manufacture, test and dimensionally inspect parts, components, subassemblies and assemblies.

3.2 Technical Data Reviews, Quality Audits

3.2.1 During the performance of the Contract, the Government shall have the right to perform technical data reviews and quality audits consisting of evaluation of records, processes and products to verify the Contractor's compliance with the respective quality programs. The Government audits will include evaluation of effectiveness in implementing the Contractor's and subcontractors' or suppliers' audit programs to promote prevention of defects, which includes schedule of audits, evaluation of operations, notification of required corrective action with follow up and means of notification to top management concerning audit results.

3.3 Government Inspection

3.3.1 The Contractor shall ensure technical, administrative, and management support for Government Source

Inspection (GSI) for purposes of inspection and acceptance of supplies and services. GSI will be conducted at the convenience of the Government.

3.4 Manufacturing Processes

3.4.1 The Contractor shall procure, maintain and control manufacturing processes to fabricate, assemble, inspect, test, and deliver PPS and MCP as described in the SOW. The processes shall cover all phases from the ordering of raw materials to Government acceptance of the finished product. All components shall be manufactured in accordance with the drawings and specifications referenced in the TDP and SOW.

3.5 Testing, Inspection and Acceptance

3.5.1 The Contractor shall perform testing and inspection of the PPS and MCP at the Contractor’s facility in accordance with the applicable drawings, standards and specifications and factory test and inspection plans.

The Contractor shall assure that all testing and inspections required for acceptance are satisfactorily performed.

3.6 Counterfeit Parts and Materials

3.6.1 The Contractor shall establish processes to minimize the risk of procuring and using counterfeit parts and materials. The Contractor shall describe the proposed Diminished Manufacturing Sources and Material Shortages (DMSMS). The Contractor shall document these processes and make available those documented processes to Government representatives upon request. (CDRL A001)

3.7 Shipping and Packaging

3.7.1 The Contractor shall clean, preserve, package, pack and mark all equipment procured hereunder in accordance with "Level B Packaging and Packing" of Military Specification MIL-STD-2073-1E or the latest revision as of the date of the Contract.

3.8 Environmental Compliance and Regulations

3.8.1 The Contractor shall comply with all applicable environmental federal, state, and local laws and regulations and Navy policies, instructions and ISO 14000 Environmental Management Systems Standards.

3.9 Hazardous Waste and Material Control/Handling

3.9.1 The Contractor shall comply with all applicable Navy instructions for handling and control of hazardous waste. Any hazardous waste and material generated by Contractor personnel must be disposed by the Contractor personnel in accordance with 40 CFR 265.170-265.177. The Contractor must use an approved hauler/treatment, storage, and disposal facility.

3.10 Specific Requirements

3.10.1 First Article Inspection

3.10.1.1 The Contractor shall perform First Article Inspection (FAI) on one PPS and one MCP unit. The FAI objective is to prepare evidence that all the technical data package and specification requirements are correctly understood, accounted for, verified, and recorded. The Government reserves the right to witness all FAI activities.

3.10.1.2 The Contractor shall prepare a comprehensive schedule of FAI events that includes date, time, expected duration and location and shall notify the Government at least five working days prior to the first event.

(CDRL A002)

3.10.1.3 The Contractor shall prepare FAI Validation reports. The Government retains the right to examine all FAI reports at any time in the future. All deficiencies discovered during the FAIs that affect form, fit, function or performance shall be corrected at Contractor’s expense prior to unit delivery. (CDRL A003)

3.10.2 Physical Configuration Audit (PCA)

3.10.2.1 The purpose for PCA is to verify the “as-built” configuration matches its technical documentation and to validate supporting processes. The Government will perform a PCA of the first assembly built of the PPS, MCP and associated parts.

3.10.2.2 The Contractor shall ensure qualified engineering, technical, manufacturing, management, administrative and other support are available as necessary for these Government audits. Technical personnel shall be required to have necessary tools, measuring devices and other equipment available for equipment disassembly, dimensional and tolerance verification and performance verification. The Contractor shall ensure an area for audit conduct is well illuminated, temperate and low noise level. The audit work area shall contain worktables, print copies of all pertinent drawings, telephone and easy access to a copy machine.

3.10.2.3 The Contractor shall allow the Government to witness the PCA, at a minimum, to the individual parts that make up the configuration item and/or completed assembly(s):

• An as-built list delineating all Engineering Change Proposal (ECPs) (either requested or approved)

• The hardcopies of production specifications and technical drawings

• Complete shortage list

• To manufacturing instructions

• To acceptance test procedures and data

• To purchase order documents

• Associated certificates of conformance from suppliers or appropriate documents indicating compliance with material or drawing requirements.

3.10.2.4 The Contractor shall prepare a PCA technical report. (CDRL A004)

3.10.2.5 The audits shall be conducted at the Contractor’s or subcontractor’s facility by NSWC Dahlgren and Port

Hueneme Division personnel and/or by other Government designated representatives.

3.10.2.6 Each audit shall be performed after assembly completion (including acceptance testing) and prior to DD

250 Acceptance. For planning purposes, each complete PCA will require approximately five days for audit conduct, and two days for post audit close-out efforts.

3.10.2.7 Following the conduct of the PCA, the Contractor shall resolve all audit findings and document such resolution in a report (CDRL A004).

3.10.3 Production Readiness Review (PRR)

3.10.3.1 The Contractor shall perform PRR with the Government to assure the Contractor has accomplished the adequate production planning in preparation for production of the PPS, MCP and associated parts to meet performance requirements in accordance with the contract schedule and without unacceptable risks.

3.10.3.2 The Contractor shall prepare a PRR report. (CDRL A005)

3.10.3.3 The Contractor shall develop various plans to include Manufacturing, Testing, Quality Assurance, Failure Analysis and Corrective Action Reporting (FACAR), Configuration Management, Calibration, and Supplier Management Plans and then demonstrate that it shall manufacture and test the PPS, MCP and associated parts in accordance with those plans.

3.10.3.4 On-site examination of the above objective evidence as listed on 3.10.3.3, as well as examination of the manufacturing equipment and facility, review of support functions/groups, and interviews with project personnel, are all integral parts of the PRR. Processes must be able to produce repeatable conforming hardware within the time constraints of the contract. During the PRR, the Contractor shall be prepared to discuss manufacturing and procurement planning status, issues, risks and schedules associated with the production program, and make available requested supporting objective evidence.

3.10.4 First Article Test

3.10.4.1 The Contractor shall perform a First Article Test (FAT) on one PPS and one MCP to demonstrate the built to print unit will pass testing. The test, test item and test objective are identified in the TDPs.

3.10.4.2 The Contractor shall prepare for all aspects of test planning, conduct and reporting, including, as a minimum, a test plan a test report, fixtures, support equipment and apparatus, instrumentation, test site, test equipment, personnel, safety and post-test asset disposition.

3.10.4.3 The Contractor shall convene a Test Readiness Review (TRR) at least five working days prior to each FAT event. Multiple FAT events may be reviewed during a single TRR. The TRR shall be chaired by the Contractor and co-chaired by the Government. Additional Government subject matter experts will attend each TRR.

3.10.4.4 The Government reserves the right to witness all FAT activities. The Contractor shall maintain a comprehensive schedule of FAT events that includes date, time, expected duration and location, and shall notify the Government at least five days prior to the first event.

3.10.4.5 The Contractor shall prepare a comprehensive test plan for the FAT unit. (CDRL A006)

3.10.4.6 The Contractor shall prepare a Quick Look Report after completion of a FAT event. The quick look report shall offer an initial assessment of the unit under test performance and shall describe all apparent anomalies. (CDRL A007)

3.10.4.7 The Contractor shall prepare a final report after the completion of the FAT event. (CDRL A008)

3.10.4.8 The Contractor shall coordinate testing of the Lowest Replaceable Unit (LRU) of the PPS and MCP with the Government. The Government has the Automated Test Equipment (ATE) to test the below LRUs:

PPS FAT Requirements LRU Test Requirement

PPS MK 179 Mod 0 7104312 Relay Assy. 7104330 7104532 Housekeeping Power Assy 7104325 7104531 Fuse Block/EMI Assy 7104335 7104529 29V Assy 7104205 7104533 SBR Assy 7104320 7104570

PSCM 8591698 8591703

MCP FAT Requirements LRU Test Requirement

MCP MK 448 Mod 1 7104974

MCP BITE Display 5498353 5498067 A1 Anti-Icing Module 7103930-9 7103937 A2 & A3 Motor Drive Assy 7104048-9 7103969 A4 Lamp Driver Contactor Assy 7103940-9 7103974 A5 Relay Assy 7103868-9 (7103868-19 with SCIP 77188) 7103868 A6A1 Receiver Card 7104187-9 7104187

A6A2 & A6A3 MCC CCA 6388340-9 7103887

A6A4 BITE Monitor CCA 7103779-9 7103782 A6A5 Plenum Drain Valve/Anti-Icing CCA 7103876-9 7103876 A7 & A9 Power Supply Assy 7104008-9 5498074 A8 Power Assy 5598132-19 5598132 A13 MCP Control Module Assy 7105544-9 7105544

4 TECHNICAL DATA RIGHTS

4.1 The Government shall maintain the Government owned Technical Data Package(s) (TDP). Proposed changes to the TDP shall be submitted by the Contractor to the Government. The Government shall retain unlimited rights to all versions of and changes to all drawings, specifications and other documents for the PPS and associated parts produced under this contract.

4.2 The Contractor shall prepare the updated drawings, specifications and any other documents, including the

Request for Variance. (CDRL A009)

HQ C-1-0001 ITEMS(S) CLIN 0003- DATA REQUIREMENTS (NAVSEA) (SEP 1992)

The data to be furnished hereunder shall be prepared in accordance with the Contract Data Requirements List, DD Form 1423, Exhibit(s) _A_, attached hereto.

HQ C-2-0008 ASSIGNMENT AND USE OF NATIONAL STOCK NUMBERS (NAVSEA) (MAY 1993)

To the extent that National Stock Numbers (NSNs) or preliminary NSNs are assigned by the Government for the identification of parts, pieces, items, subassemblies or assemblies to be furnished under this contract, the Contractor shall use such NSNs or preliminary NSNs in the preparation of provisioning lists, package labels, packing lists, shipping containers and shipping documents as required by applicable specifications, standards or Data item Descriptions of the contract or as required by orders for spare and repair parts. The cognizant Government Contract Administration Office shall be responsible for providing the Contractor such NSNs or preliminary NSNs which may be assigned and which are not already in possession of the Contractor.

HQ C-2-0009 ASSIGNMENT OF SERIAL NUMBER(S) (NAVSEA) (SEP 1990)

The Contractor shall request serial number assignment, in writing, from the Cognizant Technical Program Office, with a copy to the cognizant Contract Administration Office. The request for serial number assignment shall contain the following minimum information:

(a) Contract number;

(b) Assigned line item number and description;

(c) Assigned type designation;

(d) Assigned model number;

(e) Top drawing number and ID (List of Drawings) number;

(f) Exact quantity for which serial numbers are being requested, including preproduction samples required by the contract; and

(g) National Stock Number

HQ C-2-0014 CONTRACTOR'S PROPOSAL (NAVSE) (MAR 2001)

(a) Performance of this contract by the Contractor shall be conducted and performed in accordance with detailed obligations to which the Contractor committed itself in Proposal TBD dated in response to NAVSEA PHD NSWC Solicitation No. N63394-18-R- 0009.

(b) The technical volume(s) of the Contractor's proposal is incorporated by reference and hereby made subject to the provisions of the "ORDER OF PRECEDENCE" (FAR 52.215-8) clause of this contract. Under the "ORDER OF PRECEDENCE" clause, the technical volume of the Contractor's proposal referenced herein is hereby designated as item

(f) of the clause, following "the specification" in the order of precedence.

HQ C-2-0023 EXCLUSION OF MERCURY (NAVSEA) (MAY 1998)

Mercury or mercury containing compounds shall not be intentionally added or come in direct contact with hardware or supplies furnished under this contract.

HQ C-2-0026 FIRST ARTICLE (CONTRACTOR TESTING) (NAVSEA) (APR 2015)

(a) For the purpose of this contract, the "First Article" is synonymous with the terms "preproduction model(s) and "preproduction equipment".

(b) The First Article shall conform in every respect to the requirements of this contract and shall be fully tested by the Contractor to determine compliance with said requirements. The production equipment shall be manufactured with tools, material and methods that are the same as or representative of the tools, material and methods that were used to manufacture the First Article.

HQ C-2-0032 INFORMATION AND DATA FURNISHED BY THE GOVERNMENT - ALTERNATE II

(NAVSEA) (SEP 2009)

(a) NAVSEA Form 4340/2 or Schedule C, as applicable, Government Furnished Information, attached hereto, incorporates by listing or specific reference, all the data or information which the Government has provided or will provide to the Contractor except for

(1) The specifications set forth in Section C, and

(2) Government specifications, including drawings and other Government technical documentation which are referenced directly or indirectly in the specifications set forth in Section C and which are applicable to this contract as specifications, and which are generally available and provided to Contractors or prospective Contractors upon proper request, such as Federal or Military Specifications, and Standard Drawings, etc.

(b) Except for the specifications referred to in subparagraphs (a)(1) and (2) above, the Government will not be obligated to provide to the Contractor any specification, drawing, technical documentation or other publication which is not listed or specifically referenced in NAVSEA Form 4340/2 or Schedule C, as applicable, notwithstanding anything to the contrary in the specifications, the publications listed or specifically referenced in NAVSEA Form 4340/2 or Schedule C, as applicable, the clause entitled "GOVERNMENT PROPERTY" (FAR 52.245-1) or "GOVERNMENT PROPERTY INSTALLATION OPERATION SERVICES " (FAR 52.245-2), as applicable, or any other term or condition of this contract.

(c)(1) The Contracting Officer may at any time by written order:

(i) delete, supersede, or revise, in whole or in part, data listed or specifically referenced in NAVSEA Form 4340/2 or Schedule C, as applicable; or

(ii) add items of data or information to NAVSEA Form 4340/2 or Schedule C, as applicable; or

(iii) establish or revise due dates for items of data or information in NAVSEA Form 4340/2 or Schedule C, as applicable.

(2) If any action taken by the Contracting Officer pursuant to subparagraph (c)(1) immediately above causes an increase or decrease in the costs of, or the time required for, performance of any part of the work under this contract, the contractor may be entitled to an equitable adjustment in the contract amount and delivery schedule in accordance with the procedures provided for in the "CHANGES" clause of this contract.

HQ C-2-0051 SPECIFICATIONS AND STANDARDS (NAVSEA) (AUG 1994)

(a) Definitions.

(i) A "zero-tier reference" is a specification, standard, or drawing that is cited in the contract (including its attachments).

(ii) A "first-tier reference" is either: (1) a specification, standard, or drawing cited in a zero-tier reference, or (2) a specification cited in a first-tier drawing.

(b) Requirements.

All zero-tier and first-tier references, as defined above, are mandatory for use. All lower tier references shall be used for guidance only.

HQ C-2-0059 UPDATING SPECIFICATIONS AND STANDARDS (NAVSEA)

(AUG 1994)

If, during the performance of this or any other contract, the contractor believes that any contract contains outdated or different versions of any specifications or standards, the contractor may request that all of its contracts be updated to include the current version of the applicable specification or standard. Updating shall not affect the form, fit or function of any deliverable item or increase the cost/price of the item to the Government. The contractor should submit update requests to the Procuring Contracting Officer with copies to the Administrative Contracting Officer and cognizant program office representative for approval. The contractor shall perform the contract in accordance with the existing specifications and standards until notified of approval/disapproval by the Procuring Contracting Officer. Any approved alternate specifications or standards will be incorporated into the contract.

HQ C-2-0062 WAIVER OF FIRST ARTICLE REQUIREMENTS (NAVSEA) (SEP 1990)

If the First Article is waived by the Government, the Contractor shall deliver supplies that are identical or substantially identical to those previously accepted by the Government under the following contract(s):

(Offeror to fill in Contract Number(s), as applicable. See Section M)

HQ C-2-0063 USE OF NAVY SUPPORT CONTRACTORS FOR OFFICIAL

CONTRACT FILES (NAVSEA) (APR 2004)

(a) NAVSEA may use a file room management support contractor, hereinafter referred to as "the support contractor", to manage its file room, in which all official contract files, including the official file supporting this procurement, are retained. These official files may contain information that is considered a trade secret, proprietary, business sensitive or otherwise protected pursuant to law or regulation, hereinafter referred to as “protected information”. File room management services consist of any of the following: secretarial or clerical support; data entry; document reproduction, scanning, imaging, or destruction; operation, management, or maintenance of paper-based or electronic mail rooms, file rooms, or libraries; and supervision in connection with functions listed herein.

(b) The cognizant Contracting Officer will ensure that any NAVSEA contract under which these file room management services are acquired will contain a requirement that:

The support contractor not disclose any information;

(2) Individual employees are to be instructed by the support contractor regarding the sensitivity of the official contract files;

(3) The support contractor performing these services be barred from providing any other supplies and/or services, or competing to do so, to NAVSEA for the period of performance of its contract and for an additional three years thereafter unless otherwise provided by law or regulation; and,

(4) In addition to any other rights the contractor may have, it is a third party beneficiary who has the right of direct action against the support contractor, or any person to whom the support contractor has released or disclosed protected information, for the unauthorized duplication, release, or disclosure of such protected information.

(c) Execution of this contract by the contractor is considered consent to NAVSEA's permitting access to any information, irrespective of restrictive markings or the nature of the information submitted, by its file room management support contractor for the limited purpose of executing its file room support contract responsibilities.

(d) NAVSEA may, without further notice, enter into contracts with other contractors for these services. Contractors are free to enter into separate non-disclosure agreements with the file room contractor. (Please contact Director, E Business Division for contractor specifics.) However, any such agreement will not be considered a prerequisite before information submitted is stored in the file room or otherwise encumber the government.

Section D - Packaging and Marking

SECTION D

PROHIBITED PACKING MATERIALS

The use of asbestos, excelsior, newspaper or shredded paper (all types including waxed paper, computer paper and similar hygroscopic or non-neutral material) is prohibited. In addition, the use of yellow wrapping or packaging material is prohibited except where used for the containment of radioactive material. Loose fill polystyrene is prohibited for shipboard use.

HQ D-1-0001 PACKAGING OF DATA

Data to be delivered by Integrated Digital Environment (IDE) or other electronic media shall be as specified in the contract.

All unclassified data to be shipped shall be prepared for shipment in accordance with best commercial practice.

Classified reports, data, and documentation shall be prepared for shipment in accordance with National Industrial Security Program Operating Manual (NISPOM), DOD 5220.22-M dated 28 February 2006 with Change 1 dated 28 March 2013.

HQ D-1-0007 WARRANTY NOTIFICATION FOR ITEM(S) CLIN 0001, 0002, 0004, 0005, 1001-4002

ALTERNATE I (NAVSEA) (APR 2015)

The Contractor shall apply a permanent warranty notification stamping or marking on each warranted deliverable end item and its container in accordance with MIL-STD-129R dated 18 February 2014 and MIL-STD-130N(1) dated 16 November 2012. The notification shall be placed in close proximity to other required stamping or markings so as to be easily readable by personnel. The warranty notification shall read:

THIS ITEM WARRANTED UNDER CONTRACT TBD TO

CONFORM TO DESIGN, MANUFACTURING, AND PERFORMANCE

REQUIREMENTS AND BE FREE FROM DEFECTS IN MATERIAL AND

WORKMANSHIP FOR 180 Calendar Days FROM DATE OF ACCEPTANCE. IF ITEM IS DEFECTIVE NOTIFY the Contract Specialist Susana Dryer, susana.dryer@navymil AND PCO Michael Thompson, michael.d.thompson4@navy.mil

HQ D-2-0005 IDENTIFICATION MARKING OF PARTS – ALTERNATE I (NAVSEA) (APR 2015)

(a) Identification marking of individual parts within the systems, equipments, assemblies, subassemblies, components, groups, sets or kits, and of spare and repair parts shall be done in accordance with applicable specifications and drawings. To the extent identification marking of such parts is not specified in applicable specifications or drawings, such marking shall be accomplished in accordance with the following:

(1) Parts not manufactured to Government specifications shall be marked in accordance with generally accepted commercial practice.

(2) Parts manufactured to Government specifications shall be marked as follows:

(i) Electrical Parts - that is, all parts in electrical equipments and electrical parts when used in equipments which are not electrical in nature (e.g., electric controls and motors in a hydraulic system) - shall be identified and marked in accordance with MIL-STD-1285D(1) dated 10 November 2010, or, where MIL-STD-1285D(1) does not cover such a part, in accordance with MIL-STD-130N(1) dated 16 November 2012. Requirements of MIL-STD-1686C dated 25 October 1995 for Electrostatic Discharge Control shall be addressed.

(ii) Electronic Parts - that is, all parts in electronic equipments and electronic parts when used in equipments which are not electronic in nature (e.g., electronic fuel controls in some engines) - shall be identified and marked in accordance with Requirement 67 of MIL-HDBK-454B dated 15 April 2007. Requirements of MIL-STD-1686C for Electrostatic Discharge Control shall be addressed.

(iii) Parts other than electrical or electronic parts (as described above) shall be identified and marked in accordance with MIL-STD-130N(1).

(b) In cases where parts are so small as not to permit identification marking as provided above, such parts shall be appropriately coded so as to permit ready identification.

HQ D-2-0007 MARKING AND PACKING LIST(S) - ALTERNATE I (NAVSEA) (APR 2015)

(a) Marking. Shipments, shipping containers and palletized unit loads shall be marked in accordance with MIL- STD-129R dated 18 February 2014.

(b) Packing List(s). A packing list (DD Form 250 Material Inspection and Receiving Report may be used) identifying the contents of each shipment, shipping container or palletized unit load shall be provided by the Contractor with each shipment in accordance with the above cited MIL-STD. When a contract line item identified under a single stock number includes an assortment of related items such as kit or set components, detached parts or accessories, installation hardware or material, the packing list(s) shall identify the assorted items.

Where DD Form 1348-1 or DD Form 1348-1A is applicable and an assortment of related items is included in the shipping container, a packing list identifying the contents shall be furnished.

(c) Master Packing List. In addition to the requirements in paragraph (b) above, a master packing list shall be prepared where more than one shipment, shipping container or palletized unit load comprise the contract line item being shipped. The master packing list shall be attached to the number one container and so identified.

(d) Part Identification. All items within the kit, set, installation hardware or material shall be suitably segregated and identified within the unit pack(s) or shipping container by part number and/or national stock number. Refer to the above cited MIL-STD for marking of assorted (related-unrelated) items.

HQ D-2-0008 MARKING OF REPORTS (NAVSEA) (SEP 1990)

All reports delivered by the Contractor to the Government under this contract shall prominently show on the cover of the report:

(1) Name and business address of the Contractor

(2) Contract number

(3) Contract dollar amount

(4) Whether the contract was competitively or non-competitively awarded

(5) Sponsor:

(Name of Individual Sponsor)

(Name of Requiring Activity)

(City and State)

Section E - Inspection and Acceptance

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 Origin Contractor Destination Government 0002 Origin Contractor Destination Government 0003 Destination Government Destination Government 0004 Origin Contractor Destination Government 0005 Origin Contractor Destination Government 1001 Origin Contractor Destination Government 1002 Origin Contractor Destination Government 2001 Origin Contractor Destination Government 2002 Origin Contractor Destination Government 3001 Origin Contractor Destination Government 3002 Origin Contractor Destination Government 4001 Origin Contractor Destination Government 4002 Origin Contractor Destination Government

CLAUSES INCORPORATED BY REFERENCE

52.246-2 Inspection Of Supplies--Fixed Price AUG 1996 52.246-16 Responsibility For Supplies APR 1984 252.246-7000 Material Inspection And Receiving Report MAR 2008

52.209-3 FIRST ARTICLE APPROVAL--CONTRACTOR TESTING (SEP 1989)

(a) The Contractor shall test 1 unit(s) of Lot/Item CLIN 0001and 0002 as specified in this contract. At least 5 calendar days before the beginning of first article tests, the Contractor shall notify the Contracting Officer, in writing, of the time and location of the testing so that the Government may witness the tests.

(b) The Contractor shall submit the first article test report within _5_ calendar days from the date of this contract to 4363 Missile Way, Port Hueneme CA marked "FIRST ARTICLE TEST REPORT: Contract No. TBD, Lot/Item No.

CLIN 0001" Within 5 calendar days after the Government receives the test report, the Contracting Officer shall notify the Contractor, in writing, of the conditional approval, approval, or disapproval of the first article. The notice of conditional approval or approval shall not relieve the Contractor from complying with all requirements of the specifications and all other terms and conditions of this contract. A notice of conditional approval shall state any further action required of the Contractor. A notice of disapproval shall cite reasons for the disapproval.

(c) If the first article is disapproved, the Contractor, upon Government request, shall repeat any or all first article tests. After each request for additional tests, the Contractor shall make any necessary changes, modifications, or repairs to the first article or select another first article for testing. All costs related to these tests are to be borne by the Contractor, including any and all costs for additional tests following a disapproval. The Contractor shall then conduct the tests and deliver another report to the Government under the terms and conditions and within the time specified by the Government. The Government shall take action on this report within the time specified in paragraph

(b) above. The Government reserves the right to require an equitable adjustment of the contract price for any extension of the delivery schedule, or for any additional costs to the Government related to these tests.

(d) If the Contractor fails to deliver any first article report on time, or the Contracting Officer disapproves any first article, the Contractor shall be deemed to have failed to make delivery within the meaning of the Default clause of this contract.

(e) Unless otherwise provided in the contract, and if the approved first article is not consumed or destroyed in testing, the Contractor may deliver the approved first article as part of the contract quantity if it meets all contract requirements for acceptance.

(f) If the Government does not act within the time specified in paragraph (b) or (c) above, the Contracting Officer shall, upon timely written request from the Contractor, equitably adjust under the changes clause of this contract the delivery or performance dates and/or the contract price, and any other contractual term affected by the delay.

(g) Before first article approval, the acquisition of materials or components for, or the commencement of production of, the balance of the contract quantity is at the sole risk of the Contractor. Before first article approval, the costs thereof shall not be allocable to this contract for (1) progress payments, or (2) termination settlements if the contract is terminated for the convenience of the Government.

(h) The Government may waive the requirement for first article approval test where supplies identical or similar to those called for in the schedule have been previously furnished by the offeror/contractor and have been accepted by the Government. The offeror/contractor may request a waiver.

(End of clause)

52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT (DEC 2014)

(a) The Contractor shall comply with the higher-level quality standard(s) listed below.

ISO 9001:2015

(b) The Contractor shall include applicable requirements of the higher-level quality standard(s) listed in paragraph

(a) of this clause and the requirement to flow down such standards, as applicable, to lower-tier subcontracts, in--

(1) Any subcontract for critical and complex items (see 46.203(b) and (c)); or

(2) When the technical requirements of a subcontract require--

(i) Control of such things as design, work operations, in-process control, testing, and inspection; or

(ii) Attention to such factors as organization, planning, work instructions, documentation control, and advanced metrology.

HQ E-1-0001 INSPECTION AND ACCEPTANCE LANGUAGE FOR DATA

Inspection and acceptance of all data shall be as specified on the attached Contract Data Requirements List(s), DD Form 1423.

HQ E-1-0003 INSPECTION AND ACCEPTANCE LANGUAGE FOR F.O.B. DESTINATION

DELIVERIES

Item(s) CLINs 0001, 0002, 0004, 0005 and 1001-4002 - Inspection and acceptance shall be made at destination by a representative of the Government.

HQ E-2-0003 CALIBRATION SYSTEM REQUIREMENTS (NAVSEA) (APR 2015)

Calibration System Requirements. The calibration of measuring and testing equipment shall, as a minimum, adhere to the requirements of ANSI/NCSL Z540.3-2006.

HQ E-2-0004 COST OF QUALITY DATA (NAVSEA) (MAY 1995)

Cost of Quality Data: The contractor shall maintain and use quality cost data as a management element of the quality program. The specific quality cost data to be maintained and used will be determined by the contractor. These data shall, on request, be identified and made available for "on site" review by the Government representative.

HQ E-2-0008 INSPECTION AND TEST RECORDS (NAVSEA) (MAY 1995)

Inspection and Test Records:…