Solicitation Amendment N6278926Q10080001 SF 30.pdf

PDF 615 KB Posted

Attached to
REPLACE GENSETS ON YDT-2
Solicitation number
N62789-26-Q-1008
Issued by

About this file

This is a Standard Form 30 Amendment of Solicitation/Modification of Contract, Amendment 0001, issued September 9, 2026, by the Supervisor of Shipbuilding Groton Conversion and Repair (SUPSHIP Groton) for the Naval Submarine Support Facility. The solicitation number is N6278926Q1008, originally dated August 27, 2026. The purpose of this amendment is to incorporate Revision 1 of the specification. The hour and date for receipt of offers is not extended, and offerors must acknowledge receipt of this amendment prior to the deadline through one of three methods: completing items 8 and 15 and returning copies, acknowledging receipt on each copy of the offer submitted, or sending separate written communication referencing the solicitation and amendment numbers.

The amendment modifies Section C – Description/Specifications/Statement of Work to procure two (2) Kohler 40EKOZD Marine diesel generator sets for YDT-2. The generator sets must feature three-phase 480VAC Delta configuration, 60Hz operation, 24V DC starting, installed siphon break, generator heater, isolated ground system, 600W 120V block heater, 3-pole 70-amp circuit breaker, motor operator, dry contact kit, open unit guard kit, sound shield with front connection, and Decision Maker 3500 controller. Units must be export packed and delivered FOB destination to Naval Submarine Support Facility, Sub Base New London, Connecticut (Building 17, 2nd Deck, Amberjeck Road, Lower Submarine Base, Groton, CT 06340) between Monday-Friday, 0700-1330 EST. The contractor must accept liability for any costs or schedule delays resulting from failed background checks or base access denial for contractor personnel. No government-furnished materials are required.

View the file

Other files

File Type Posted
YDT-2 Generator Replacement specification Rev 1.docx DOCX document
Solicitation - N6278926Q1008.pdf PDF
C8_ATT_3_BRAND_NAME_Redacted.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Section C - Description/Specifications/Statement of Work

Miscellaneous text in this section has been modified to:

SHIP: NAVAL SUBMARINE SUPPORT FACILITY

ORIGINATOR: James Crudden (860)694-2424 DATE: 03 August 2026

NAICS - 33161

REV 1

1. SCOPE:

TITLE: PROCURE REPLACMENT DIESEL GENSET(s) FOR YDT-2

2. REFERENCE/PLANS:

2.1 NAVSEA dwg 311-5113813

3. REQUIREMENTS:

3.1 The Contractor shall provide (QTY 2) Kohler 40EKOZD Marine GENSET as identified in reference 2.1.

3.1.1 Three Phase 480VAC Delta

3.1.2 60hz

3.1.3 24V DC starting

3.1.4 Installed siphon break

3.1.5 Installed generator heater

3.1.6 Installed isolated ground system

3.1.7 Installed block heater (600w 120v)

3.1.8 Installed circuit breaker - 3 pole, 70 amp

3.1.9 Installed motor operator

3.1.10 GM102189-KP1 - LCB Motor Operator Cover (Loose)

3.1.11 Installed Dry Contact Kit

3.2.12 Installed open unit guard kit

3.1.13 Sound Shield (front connection)

3.1.14 Decision Maker 3500 controller

3.1.15 Units will be Export Packed.

3.2 Contractor shall Deliver/Ship (FOB Destination). Delivery must be accomplished between Monday - Friday between 0700 and 1330 EST.

Delivery location is as follows:

SUB BASE NEW LONDON CT

NSSF NLON, R6-25D

BLDG 17 2ND DECK, AMBERJECK ROAD

LOWER SUBMARINE BASE

Groton, CT 06340 M/F: Jim Crudden Phone: 860-694-2424

4. NOTES:

4.1 For Contractor personnel that do not have a CAC card or a NCACS card, the following is required to obtain DBIDS credentials to gain access the base:

a. Ensure you provide the names of personnel requiring access to the SUBASE to the NSSF POC. NSSF will pass the information to the SUBASE Pass and ID office as your government sponsor.

b. Upon arrival at SUBASE, Present valid identification, Real ID Act-compliant state drivers license. If you dont have a Real ID compliant drivers license, you can use a passport. If you dont have a passport you will be required to have an original birth certificate and your social security card (not just your number).

c. Present a completed copy of the SECNAV 5512/1 form to obtain your background check. A copy of SECNAV 5512/1 can be obtained by contacting the NSSF POC.

d. Upon completion of the background check, the Visitor Control Center representative will complete the DBIDS enrollment process, which includes your photo, fingerprints, base restrictions, and several other assessments; after all this is done, you will be provided with your new DBIDS credential.

You may now proceed to enter the base.

e. The Contractor hereby accepts full liability for any and all additional costs or schedule delay, resulting from a failed background check or refusal of

N6278926Q10080001 gate access, for any of the contractors employees, subcontractors, or agents.

5. GFM:

5.1 None

The Requirements text has been modified to:

The Contractor shall provide (QTY 2) Kohler 40EKOZD Marine GENSET as identified in reference 2.1 of the statement of work.

N6278926Q10080001

IDCode: J
Page: 1
Pages: 3
AmendNo: 0001
EffDate: 09 Sep 2026
ReqNo: See Continuation Sheet
ProjNo:
IssCode: N62789
AdmCode:
IssuedBy: SUP OF SHIPBUILDING GROTON

CONVERSION AND REPAIR USN, 73 EASTERN POINT RD

GROTON, CT 06340-4990

UNITED STATES

Kyle Berg, Email: kyle.r.berg3.civ@us.navy.mil Telephone: 860-433-1111 AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: N6278926Q1008
SolDate: 27 Aug 2026
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: Off
OffrNoEx: 1
NoCopies: 1
ApprData: See Section G - Contract Administration Data
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: The purpose of this amendment is to incorporate Revision 1 of the specification.
ContNameTitle:
CoNameTitle: Stephanie L. Neale
ContDate:
CODate: 09 Sep 2026

File details come from the government source that posted it. Updated .