This document is a Bill of Quantity (BOQ) that provides a detailed cost estimate for the renovation of several facilities as part of a larger construction contract (Contract No. N6274224R6722) for the Department of the Navy Naval Facilities Engineering Command (NAVFAC).
The BOQ covers four separate CLINs (contract line items) for renovating the following facilities: Barracks, Dining Facility (DFAC), Training Facility, and Shore Maintenance Facility. Each CLIN includes line item details on the required work, materials, labor, and estimated costs for categories such as exterior closure, interior finishes, plumbing, HVAC, electrical, and furnishings. The BOQ also includes estimated costs for site preparation, utilities, overhead, and profit. A related federal contract opportunity solicitation (Solicitation No. N6274224R6722) is provided, which requires a pre-proposal site visit on August 1, 2024 and has a deadline of August 6, 2024 for submitting pre-proposal inquiries.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Released AMD0002_24R6722.pdf | ||
| Released_amd1_N6274224R6722.pdf | ||
| Exhibit D_24R6722_Fillable BOQ.xlsx | XLSX spreadsheet | |
| Exhibit A_24R6722_PPI_Fillable.docx | DOCX document | |
| RELEASED RFP_N6274224R6722.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
BILL OF QUANTITY, AMENDMENT 0002 DATE PREPARED
| ACTIVITY AND LOCATION: | CONSTRUCTION CONTRACT NO. | ID NO. | |||||||
| Kuching, Sarawak, Malaysia | N6274224R6722 | ||||||||
| ESTIMATED BY | CATEGORY CODE | ||||||||
| PROJECT TITLE: | NO | ||||||||
| D/B Construct Maritime Training Facilities | STATUS OF DESIGN | JOB ORDER NO. | |||||||
| CLIN 001 Renovation of Barracks | QUANTITY | MATERIAL COST | LABOR COST | ENGINEERING ESTIMATE | |||||
| NUMBER | UNIT | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | ||
| B20 | EXTERIOR CLOSURE | ||||||||
| Repaint the wall ( include removal of existing paint and finishes) | sq.m | ||||||||
| B2020 | Windows | units | |||||||
| B2030 | Exterior single doors | units | |||||||
| C10 | INTERIOR CONSTRUCTION | ||||||||
| Toilet doors | units | ||||||||
| Skirt tile | l.m | ||||||||
| C30 | INTERIOR FINISHES | ||||||||
| C3010 | Repaint the wall ( include removal of existing paint and finishes) | sq.m | |||||||
| Wall finishes toilet inclding the removal of existing toilet wall | sq.m | ||||||||
| C3020 | Floor Finishes (floor tile) including the removal of existing floor finish | sq.m | |||||||
| C3030 | Ceiling | sq.m | |||||||
| D20 | PLUMBING | ||||||||
| D2010 | Water Closet with the accessories | units | |||||||
| Lavatory with the structures, accessories, and finish | units | ||||||||
| D2020 | Clean water distribution lines | ls | |||||||
| D2030 | Waste water distribution lines | ls | |||||||
| D30 | HVAC | ||||||||
| Air Conditioning | BTU | ||||||||
| D40 | FIRE PROTECTION | ||||||||
| Fire extingusher | pcs | ||||||||
| E20 | FURNITURE | ||||||||
| Single bed mattress and its accessories | units | ||||||||
| Wardrobe | units | ||||||||
| Office desk | units | ||||||||
| Ergonomic chair | units | ||||||||
| D50 | ELECTRICAL | ||||||||
| D5010 | Electrical Service and Distribution | ls | |||||||
| Exhaust fan | units | ||||||||
| D5020 | Lighting & Branch Wiring | ls | |||||||
| F10 | SPECIAL CONSTRUCTION | ||||||||
| Name sign and project plaque | ls | ||||||||
| X | FIELD REQUIREMENTS, OFFICE OVERHEAD & PROFIT | ||||||||
| X10 | Field Requirements | ||||||||
| X20 | Office Overhead | ||||||||
| X30 | Profit | ||||||||
| Total |
| Table 2: SITEWORK | |||||||||
| CLIN 001 Renovation of Barracks | QUANTITY | MATERIAL COST | LABOR COST | ENGINEERING ESTIMATE | |||||
| NUMBER | UNIT | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | ||
| G10 | SITE PREPARATION | ||||||||
| G1010 | Site Clearing | sq.m | |||||||
| G1030 | Mobilization | ls | |||||||
| De-mobilization | ls | ||||||||
| Design and drawing | ls | ||||||||
| Construction of temporary facilities | ls | ||||||||
| G30 | SITE CIVIL/ MECHANICAL UTILITIES | ||||||||
| Water supply and electricity connection | units | ||||||||
| Septic tank | units | ||||||||
| X | FIELD REQUIREMENTS, OFFICE OVERHEAD & PROFIT | ||||||||
| X20 | Office Overhead | ||||||||
| X30 | Profit | ||||||||
| Total | |||||||||
| Total CLIN 001 |
| CLIN 002 Renovation of DFAC | QUANTITY | MATERIAL COST | LABOR COST | ENGINEERING ESTIMATE | |||||
| NUMBER | UNIT | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | ||
| B20 | EXTERIOR CLOSURE | ||||||||
| Repair exterior ceiling | sq.m | ||||||||
| D20 | PLUMBING | ||||||||
| Lavatory with the structures, accessories, and finish | units | ||||||||
| D2020 | Clean water distribution lines | ls | |||||||
| D2030 | Waste water distribution lines | ls | |||||||
| D30 | HVAC | ||||||||
| Air Conditioning | BTU | ||||||||
| D40 | FIRE PROTECTION | ||||||||
| Fire extingusher | pcs | ||||||||
| D50 | ELECTRICAL | ||||||||
| D5010 | Electrical Service and Distribution | ls | |||||||
| D5020 | Lighting & Branch Wiring | ls | |||||||
| E10 | EQUIPMENTS | ||||||||
| Freestanding cooker with oven | units | ||||||||
| Chiller | units | ||||||||
| Freezer | units | ||||||||
| Projector | units | ||||||||
| Whiteboard | units | ||||||||
| E20 | FURNISHINGS | ||||||||
| Stainless steel shelves | units | ||||||||
| Pulldown screen | units | ||||||||
| Dining chair | units | ||||||||
| Dining table | units | ||||||||
| X | FIELD REQUIREMENTS, OFFICE OVERHEAD & PROFIT | ||||||||
| X10 | Field Requirements | ||||||||
| X20 | Office Overhead | ||||||||
| X30 | Profit | ||||||||
| Total |
| Table 2: SITEWORK | |||||||||
| CLIN 002 Renovation of DFAC | QUANTITY | MATERIAL COST | LABOR COST | ENGINEERING ESTIMATE | |||||
| NUMBER | UNIT | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | ||
| G10 | SITE PREPARATION | ||||||||
| G1010 | Site Clearing | sq.m | |||||||
| G1030 | Mobilization | ls | |||||||
| De-mobilization | ls | ||||||||
| G30 | SITE CIVIL/ MECHANICAL UTILITIES | ||||||||
| Water supply and electricity connection | units | ||||||||
| X | FIELD REQUIREMENTS, OFFICE OVERHEAD & PROFIT | ||||||||
| X20 | Office Overhead | ||||||||
| X30 | Profit | ||||||||
| Total | |||||||||
| Total CLIN 002 |
| CLIN 003 Renovation of Training Facility | QUANTITY | MATERIAL COST | LABOR COST | ENGINEERING ESTIMATE | |||||
| NUMBER | UNIT | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | ||
| D30 | HVAC | ||||||||
| Air Conditioning | BTU | ||||||||
| D40 | FIRE PROTECTION | ||||||||
| Fire extingusher | pcs | ||||||||
| D50 | ELECTRICAL | ||||||||
| D5010 | Electrical Service and Distribution | ls | |||||||
| D5020 | Lighting & Branch Wiring | ls | |||||||
| E10 | EQUIPMENTS | ||||||||
| Projector | units | ||||||||
| Whiteboard | units | ||||||||
| E20 | FURNISHINGS | ||||||||
| Instructor desk | units | ||||||||
| Student desk | units | ||||||||
| Ergonomic chairs | units | ||||||||
| Pulldown screen | units | ||||||||
| X | FIELD REQUIREMENTS, OFFICE OVERHEAD & PROFIT | ||||||||
| X10 | Field Requirements | ||||||||
| X20 | Office Overhead | ||||||||
| X30 | Profit | ||||||||
| Total |
| Table 2: SITEWORK | |||||||||
| CLIN 003 Renovation of Training Facility | QUANTITY | MATERIAL COST | LABOR COST | ENGINEERING ESTIMATE | |||||
| NUMBER | UNIT | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | ||
| G10 | SITE PREPARATION | ||||||||
| G1010 | Site Clearing | sq.m | |||||||
| G1030 | Mobilization | ls | |||||||
| De-mobilization | ls | ||||||||
| X | FIELD REQUIREMENTS, OFFICE OVERHEAD & PROFIT | ||||||||
| X20 | Office Overhead | ||||||||
| X30 | Profit | ||||||||
| Total | |||||||||
| Total CLIN 003 |
| CLIN 004 Renovation of Shore Maintenance Facility | QUANTITY | MATERIAL COST | LABOR COST | ENGINEERING ESTIMATE | |||||
| NUMBER | UNIT | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | ||
| D40 | FIRE PROTECTION | ||||||||
| Fire extingusher | pcs | ||||||||
| D50 | ELECTRICAL | ||||||||
| D5010 | Electrical Service and Distribution | ls | |||||||
| D5020 | Lighting & Branch Wiring | ls | |||||||
| E10 E20 | EQUIPMENTS AND FURNISHINGS | ||||||||
| Industrial Work Bench | units | ||||||||
| Storage shelf rack | units | ||||||||
| Tool cabinet | units | ||||||||
| Work Table | units | ||||||||
| Storage locker | units | ||||||||
| Toolboard | units | ||||||||
| Bench vise | units | ||||||||
| Personal Protective Equipment (PPE) locker | units | ||||||||
| Ergonomic chairs | units | ||||||||
| Office desk | units | ||||||||
| X | FIELD REQUIREMENTS, OFFICE OVERHEAD & PROFIT | ||||||||
| X10 | Field Requirements | ||||||||
| X20 | Office Overhead | ||||||||
| X30 | Profit | ||||||||
| Total |
| Table 2: SITEWORK | |||||||||
| CLIN 004 Renovation of Shore Maintenance Facility | QUANTITY | MATERIAL COST | LABOR COST | ENGINEERING ESTIMATE | |||||
| NUMBER | UNIT | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | ||
| G10 | SITE PREPARATION | ||||||||
| G1010 | Site Clearing | sq.m | |||||||
| G1030 | Mobilization | ls | |||||||
| De-mobilization | ls | ||||||||
| X | FIELD REQUIREMENTS, OFFICE OVERHEAD & PROFIT | ||||||||
| X20 | Office Overhead | ||||||||
| X30 | Profit | ||||||||
| Total | |||||||||
| Total CLIN 004 |
Total All CLINs and Option CLINs
_x000D_&1#&"Calibri"&14&K000000 SENSITIVE BUT UNCLASSIFIED
Sheet2
_x000D_&1#&"Calibri"&14&K000000 SENSITIVE BUT UNCLASSIFIED
Sheet3
_x000D_&1#&"Calibri"&14&K000000 SENSITIVE BUT UNCLASSIFIED
File details come from the government source that posted it. Updated .