This document contains a notice and questions and answers related to solicitation number N6274222R1325. The solicitation is for the design and construction of up to 178 single-story duplex units totaling three or four bedrooms each for enlisted personnel housing at Andersen Air Force Base in Guam. Phase IV will construct 62 units, Phase V will construct 68 units, and Phase VI will construct 48 units. The houses will have reinforced concrete roofs, walls, frames and floors supported by concrete footings and be designed to withstand Guam's hot, humid environment, typhoon winds and strong earthquakes. The notice provides answers to submitted questions, clarifying that three-story buildings will not meet relevant experience criteria and confirming a four-week extension was granted to the June 2nd proposal submission date via amendment number 0004.

View the file

Other files

File Type Posted
22R1325_AMD06.pdf PDF
22R1325 Note 6.pdf PDF
22R1325_AMD05.pdf PDF
22R1325_AMD04.pdf PDF
22R1325_AMD03.pdf PDF
22R1325 Note 4.pdf PDF
22R1325_AMD2.pdf PDF
22R1325 Note 3.pdf PDF
22R1325_AMD1.pdf PDF
22R1325 Note 2.pdf PDF
22R1325 Note 1.pdf PDF
22R1325-RFP.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Notice No. 5 1 June 2022

PRE-PROPOSAL QUESTIONS & ANSWERS

RFP N62742-22-R-1325

FY23 FHCON H-366, H-283, & H-375 REPLACE ANDERSEN HOUSING PHASE IV, V, &

VI, NAVAL SUPPORT ACTIVITY ANDERSEN, GUAM

NOTE: The following questions and answers are provided for INFORMATION ONLY. The RFP remains unchanged unless it is amended in writing on a Standard Form 30.

8. Relevant Experience. The RFP states that relevant Design Projects for design experience shall meet the following criteria. “Design of new single-family or multi-family housing, consisting of twenty-five (25) or more one and/ or two-story units, approximately $5 million or more in dollar value, completed or substantially completed within fifteen (15) years of the date of issuance of this RFP.”

If a project consists of 3-story buildings but is made up of single-story units on each of the three floors, does it meet the design experience criteria for relevant projects? Please advise.

ANSWER: No, three-story buildings will not be considered as relevant projects. An amendment will be issued for clarification.

9. To ensure a competitive and comprehensive package for the Phase-One submission requirements, we would like to request for a 4-week time extension to the current submission date of June 02, 2022.

ANSWER: The proposal due date was extended via Amendment No. 0004.

End of Notice

DEPARTMENT OF THE NAVY

NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND, PACIFIC

258 MAKALAPA DRIVE, SUITE 100

JOINT BASE PEARL HARBOR HICKAM, HAWAII 96860-3134

File details come from the government source that posted it. Updated .