WORK ORDER NO. 1362348

REQUEST FOR PROPOSAL

N62742-18-R-1301

FY18 MCON P-887, LHD PAD CONVERSION

AND NEW MV-22 LANDING PADS, MARINE

CORPS BASE HAWAII, KANEOHE, HI

LHD Pad Conversion and MV-22 Landing Pads, 1362348 Marine Corps Base Hawaii, Kaneohe, HI

RFP N62742-18-R-1301

SOLICITATION TABLE OF CONTENTS

TABLES OF CONTENTS

(1) PROPOSAL DOCUMENTS

(A) SOLICITATION, OFFER AND AWARD (SF1442) (Rev. 4-85)

(B) 00100 INSTRUCTIONS TO OFFERORS

(C) 00 01 15 LIST OF DRAWINGS

(D) 00202 EVALUATION FACTORS FOR AWARD

(E) 00600 REPRESENTATIONS AND CERTIFICATIONS

(F) 00700 CONTRACT CLAUSES

(G) 00800 STATE OF HAWAII GENERAL WAGE DECISION NO.

HI180000, MODIFICATION NO. 03, PUBLICATION DATE 03/09/2018

(H) NAVFAC SPECIFICATION WORK ORDER NO (WON) 1362348

(2) CONTRACT FORMS AND CONDITIONS OF THE CONTRACT

(A) SOLICITATION, OFFER AND AWARD (SF1442) (Rev. 4-85)

(B) 00 01 15 LIST OF DRAWINGS

(C) 00700 CONTRACT CLAUSES (FULL TEXT)

(D) 00800 STATE OF HAWAII GENERAL WAGE DECISION NO.

HI180000, MODIFICATION NO. 03, PUBLICATION DATE 03/09/2018

(E) NAVFAC SPECIFICATION WORK ORDER NO (WON) 1362348

See Doc 00100

SOLICITATION, OFFER AND AWARD (SF 1442), CONTINUED

PRICE PROPOSAL SCHEDULE

FOR

RFP NO. N62742-18-R-1301

WON #1362348, FY18 MCON P-887, LHD PAD CONVERSION AND MV-22 LANDING PADS,

MARINE CORPS BASE HAWAII, KANEOHE, HI

ITEM NO. DESCRIPTION QTY

UNIT OF

ISSUE

UNIT

PRICE AMOUNT

0001 BASE ITEM: The basis for CLIN 0001 is the entire work for FY18 MCON P-887 (WON

#1362348), LHD PAD AND MV-22

LANDING PADS complete in accordance with the specifications and drawings

1 Lump Sum $__________________

Notes:

1. See Document 00202 for the Price Evaluation.

Document 00100 – Table of Contents

DOCUMENT 00100

INSTRUCTIONS TO PROPOSERS

3/18

1.1 NUMBER OF COPIES/TIME OF RECEIPT

1.2 INSTRUCTION FOR OBTAINING THE REQUEST FOR PROPOSAL

1.3 INSTRUCTIONS FOR SUBMITTING QUESTIONS REGARDING SOLICITATION

1.4 AMENDMENTS

1.5 PREAWARD SURVEY/RESPONSIBILITY DETERMINATION

1.6 PARTNERSHIPS, JOINT VENTURES (JV), LIMITED LIABILITY COMPANIES (LLC), LIMITED

PARTNERSHIPS (LP), ETC.

1.7 SUBCONTRACTING PLAN

1.8 FAR 52.204-7, SYSTEM FOR AWARD MANAGEMENT (OCT 2016) / DFARS 252.204-7004

ALTERNATE A SYSTEM FOR AWARD MANAGEMENT (FEB 2014)

1.9 FAR 52.211-14, NOTICE OF PRIORITY RATING FOR NATIONAL DEFENSE, EMERGENCY

PREPAREDNESS, AND ENERGY PROGRAM USE (APR 2008)

1.10 FAR 52.215-1, INSTRUCTIONS TO OFFERORS--COMPETITIVE ACQUISITION (JAN 2017)

1.11 FAR 52.216-1, TYPE OF CONTRACT (APR 1984)

1.12 FAR 52.222-5, CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE

WORK (MAY 2014)

1.13 FAR 52.222-23, NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) *

1.14 FAR 52.225-12, NOTICE OF BUY AMERICAN REQUIREMENT--CONSTRUCTION MATERIALS

UNDER TRADE AGREEMENTS (MAY 2014) ALTERNATE I (MAY 2014), ALTERNATE II (JUN 2009)

1.15 FAR 52.233-2, SERVICE OF PROTEST (SEP 2006)

1.16 FAR 52.236-27, SITE VISIT (CONSTRUCTION) (FEB 1995)

1.17 FAR 52.236-28, PREPARATION OF PROPOSALS--CONSTRUCTION (OCT 1997)

1.18 DFARS 252.204-7008, COMPLIANCE WITH SAFEGUARDING COVERED DEFENSE INFORMATION

CONTROLS (OCT 2016)

1.19 DFARS 252.215-7008, ONLY ONE OFFER (OCT 2013)

--End Document Table of Contents--

INSTRUCTIONS TO PROPOSERS

3/18

1.1 NUMBER OF COPIES/TIME OF RECEIPT

(a) PRICE PROPOSAL (PAPER): An original paper and one (1) paper copy of the price proposal shall be submitted on 9 May 2018, 2:00 P.M., H.S.T. in a sealed envelope and marked in the bottom right corner "PRICE PROPOSAL SUBMITTED UNDER RFP N62742-18-R-1301 - DO NOT OPEN IN MAILROOM." The PRICE PROPOSAL shall include the following:

(1) Signed* and completed SF 1442 (Solicitation, Offer and Award)

(2) Signed* and completed Bid Guarantee

(3) Representations and Certifications (See Section 00 45 00)

(4) Information required by paragraph 1.5, Pre-Award Survey/Responsibility Determination

(5) Information required by paragraph 1.6, Joint Ventures (JV), Limited Liability Companies (LLC), Limited Partnerships (LP), Etc.

*The offeror shall submit a document that appoints, in writing, one or more individuals, by name, each of whom will have full and independent authority to bind the offeror with respect to any act connected with this solicitation, including but not limited to: the submission and revisions of a proposal or proposals by the company, the conduct of discussion or negotiations, the submission of a Final Proposal Revision (FPR), and the execution of a contract and associated documents including bonds. Documents of appointment by a supporting resolution of the board of directors in the case of a corporation and by an instrument of similarly binding character in the case of an unincorporated entity.

*The proposal and each bond or other document submitted by or on behalf of the joint venture shall be executed by each joint venture partner and shall be accompanied by evidence of the authority of the signer. That authority shall be evidenced by a document satisfactory to the Contracting Officer, which would ordinarily be, in the case of a corporate joint venture partner, a certified copy of a resolution of the board of directors, and in the case of an unincorporated joint venture partner, an instrument of similarly binding character duly executed by that entity. If one individual signs for more than one partner, the individual must sign separately for each partner which he or she represents, and must state under each signature the capacity in which he or she is signing (See FAR 4.102).

(b) NON-PRICE PROPOSAL (FACTORS 1 THROUGH 3) (PAPER): An original paper and four (4) paper copies of the non-price proposal for Factors 1 and 2 shall be submitted on 9 May 2018, 2:00 P.M., H.S.T. in a sealed envelope/package/box and marked in the bottom right corner "TECHNICAL PROPOSAL SUBMITTED UNDER RFP N62742-18-R-1301 - DO NOT OPEN IN MAILROOM." Identify the original proposal as "Original" on the cover of the proposal. The NON-PRICE PROPOSAL shall be submitted in a three-ring binder with table of contents and tabbed. The NON-PRICE PROPOSAL shall include the following:

(1) All information required by Factor 1, Experience

(2) All information required by Factor 2, Past Performance

(3) All information required by Factor 3, Safety

(c) SUBCONTRACTING PLAN (PAPER): An original paper and one (1) paper copy of the subcontracting plan shall be submitted by 10 May 2018, 2:00 P.M., H.S.T. in a sealed envelope/package/box and marked in the bottom right corner "SUBCONTRACTING PLAN SUBMITTED UNDER RFP N62742-18-R-1301 - DO NOT OPEN IN MAILROOM." Identify the original proposal as "Original" on the cover of the proposal.

(1) All information required by 1.7, Small Business Subcontracting Plan

(d) PRICE AND NON-PRICE PROPOSALS (ELECTRONIC): An electronic copy of the price proposal, non-price proposal, and subcontracting plan shall be submitted in .pdf format on a CD-ROM with the paper copy of the Small Business Subcontracting Plan. The offeror is responsible for ensuring that all original paper and electronic copies are identical. Should there be a discrepancy between the paper and electronic versions, the paper copy shall govern.

(e) Proposals shall be submitted as follows:

(1) If sent via U. S. Postal Mail:

Naval Facilities Engineering Command, Pacific Construction Contracts Branch (ACQ31) 258 Makalapa Drive, Suite 100 Pearl Harbor, HI 96860-3134

(2) If hand-carried/Private Courier (Delivery hours between 7:00 AM and 2:00 PM, Monday through Friday except Federal Holidays)

Naval Facilities Engineering Command, Pacific Construction Contracts Branch (ACQ31) 4256 Radford Drive, Building 62 (if facing the building office is on the right. DO NOT drop off at the Navy Federal Credit Union) Honolulu, HI 96818-3296

1.2 INSTRUCTION FOR OBTAINING THE REQUEST FOR PROPOSAL

The RFP, excluding the drawings, will be available through the NECO website https://www.neco.navy.mil. The RFP, including the drawings can be accessed at the following direct link https://www.fbo.gov/fedteds/TDPN6274218R1301. Printed copies of the RFP will not be issued. Contractors must register at the Federal Business Opportunities (FBO) website https://www.fbo.gov to obtain access to the RFP drawings. Registration instructions can be found on the FBO website. Once registered in FBO, the contractor must request explicit access to the drawings. An email will be forwarded once the contracting office has approved or declined the request. Approved contractors may view and/or download the drawings.

1.3 INSTRUCTIONS FOR SUBMITTING QUESTIONS REGARDING SOLICITATION

Questions regarding the solicitation shall be submitted in writing in WORD format via electronic mail to Casey Sugihara at casey.sugihara@navy.mil. Questions shall reference the drawing/detail and/or the specification section including paragraph number. Verbal queries will not be entertained. Responses to the questions will be provided in the form of a Notice and posted to the web site https://www.neco.navy.mil. The Government may not respond to questions submitted less than 10 days before the proposal receipt due date.

1.4 AMENDMENTS

Amendments will normally be posted to the NECO web site at https://www.neco.navy.mil. If the amendment contains drawings, the amendment, excluding the drawings, will be posted to http://www.neco.navy.mil. If the amendment contains drawings, the drawings can be accessed at the following direct link https://www.fbo.gov/fedteds/TDPN6274218R1301. It is highly recommended that firms register on the NECO and FBO websites as a planholder as this will be the only planholder’s list available. It is the offeror's responsibility to check the NECO and FBO websites periodically for any amendments to the solicitation.

1.5 PREAWARD SURVEY/RESPONSIBILITY DETERMINATION

FAR §9.104 requires prospective contractors to demonstrate, among other things, that they have adequate financial resources to perform the contract or the ability to obtain them, capability to comply with the required performance schedule, a satisfactory performance record, and be otherwise eligible to receive an award under applicable laws and regulations. The pre-award survey is not a part of the non-price evaluation. The following information shall be submitted:

(a) Company financial statements (balance sheets and income statements) for past three years.

(b) Financial resources available to perform the contract. Submit evidence of availability of working/operating capital that will be used for the performance of the contract. If the offeror plans to rely on financial support from other sources, identify the maximum lines of credit that will be available to include documentation to support the amounts. The maximum lines of credit should be based upon the inclusion of this contract effort. For joint ventures discuss the financial responsibilities for each partner.

(c) Newly-formed entities (e.g. limited liability companies (“LLC’s”), limited partnerships (“LTD’s”) and newly-created corporate subsidiaries) that is the entity liable for the contract ordinarily have no financial capability to support a responsibility determination. In such cases, the offeror may rely on the resources of the LLC member, parent, limited partner, or other entities related to the offeror for responsibility purposes where the offer submits a guaranty from the entity providing the resources. The offeror shall provide a guaranty agreement (See Form DCMA Form 1620 attached) for the contract price.

(d) A list of existing commercial and government business commitments to include contract numbers, names of Contracting Officers, telephone numbers, value of contract, completion date and percent complete. If the list of existing commitments is extensive, provide the required information on at least five projects of similar dollar value and a summary of the existing commitments to include number of contracts, total dollar value of all contracts, and total dollar value of work remaining.

(e) Copy of the email confirmation of receipt notification of successful submission of the VETS-4212.

The information submitted for the pre-award survey will not be considered in the non-price evaluation unless separately submitted pursuant to the non-price evaluation factor submission requirements.

1.6 PARTNERSHIPS, JOINT VENTURES (JV), LIMITED LIABILITY COMPANIES (LLC), LIMITED

PARTNERSHIPS (LP), ETC.

The Government will recognize the integrity and validity of contractor team arrangements; provided, the arrangements are identified and company relationships are fully disclosed in the Offer (see FAR 9.603).

Partnerships, Joint Ventures, Limited Liability Companies, Limited Partnerships and Mentor-Protégé arrangements shall submit the following additional documentation regarding their business entities:

a. A copy of the Partnership Agreement, JV Agreement(s), LLC Operating Agreement(s), LP Agreement(s), and/or Mentor-Protégé Agreement(s). Contractor shall provide an updated copy whenever any change is made to the agreement.

b. Together with its proposal, each corporate joint venture partner shall submit evidence satisfactory to the Contracting Officer that its board of directors has approved its participation in the joint venture. Such evidence shall be in the form of a copy of a resolution of the board of directors, certified by the Secretary of the Corporation.

c. Together with its proposal, each joint venture partner which is an unincorporated entity shall submit evidence satisfactory to the Contracting Officer that all persons or entities which must approve decisions affecting the joint venture partner have approved the participation of the joint venture partner in the joint venture.

d. A detailed statement outlining the following in terms of percentages where appropriate:

1. The relationship of the team/partners/parties in terms of business ownership, capital contribution, profit distribution or loss sharing.

2. The management approach in terms of who will conduct, direct, supervise, control, and the controlling partner’s authority to obligate the entity.

3. The structure and decision-making responsibilities of the partners/parties in terms of who will control the manner and method of performance of work.

4. Identify (by name and title) the personnel having the authority to legally bind the Offeror (including authority to execute the contract documents and bonds).

5. Procedures in the event the entity is dissolved.

e. A list of subcontractors/partners/parties, to include company name, DUNS and CAGE Numbers, Address, Point of Contract, Email address, phone number and facsimile number.

f. The information submitted herein regarding Offeror’s team arrangement will not be considered in the non-price evaluation unless separately provided pursuant to the non-price evaluation factor submission requirements.

1.7 SUBCONTRACTING PLAN

a. As stated in Document 00202, paragraph 2.1, EVALUATION CRITERIA AND BASIS OF AWARD, this is a lowest priced technically acceptable source selection. Accordingly, small business subcontracting is not included as a technical evaluation factor. However, large business concerns must submit a Small Business Subcontracting Plan that addresses the following:

1. Identify in terms of dollar value and percentage of the total acquisition, the extent of work you will perform as the prime contractor. If submitting an offer as a Joint-Venture, identify the percentage of work each member will be responsible for and indicate the size status of each member, e.g., LB, SB, SDB, WOSB, HUBZone SB, etc.

2. In accordance with FAR 52.219-9, submit a Small Business Subcontracting Plan utilizing the template at the end of this section for this project. To demonstrate commitment in using small business concerns, the Small Business Subcontracting Plan may list all subcontractors by name. If the proposed Small Business Subcontracting goals do not meet the minimum NAVFAC Small Business Subcontracting Targets, include a detailed explanation describing the actions taken to arrive at that determination, along with an explanation for the goals that actually were proposed.

In accordance with FAR 52.219-9, Alternate II, “failure to submit and negotiate a subcontracting plan shall make the offeror ineligible for award of a contract.”

b. NAVFAC's command-wide small business subcontracting targets are shown below. These may be higher or lower than percentages that would represent realistic, challenging small business subcontracting goals for this acquisition. Offerors representing as other than small businesses shall establish small business subcontracting plan goals that are consistent with their small business participation and commitment strategies submitted for evaluation under the small business utilization source selection factor in this solicitation and shall document in their subcontracting plans the basis for all proposed goals. Plans shall be submitted with initial offers.

SB 65%

SDB 15%

HUBZone SB 6%

WOSB 15%

SDVOSB 5%

1.8 FAR 52.204-7, SYSTEM FOR AWARD MANAGEMENT (OCT 2016) DFARS 252.204-7004, ALTERNATE

A, SYSTEM FOR AWARD MANAGEMENT (FEB 2014)

(a) Definitions. As used in this provision—

“System for Award Management (SAM) database” means the primary Government repository for contractor information required for the conduct of business with the Government.

“Commercial and Government Entity (CAGE) code” means—

(1) A code assigned by the Defense Logistics Information Service (DLIS) to identify a commercial or Government entity; or

(2) A code assigned by a member of the North Atlantic Treaty Organization that DLIS records and maintains in the CAGE master file. This type of code is known as an “NCAGE code.”

“Data Universal Numbering System (DUNS) number” means the 9-digit number assigned by Dun and Bradstreet, Inc. (D&B) to identify unique business entities.

“Data Universal Numbering System +4 (DUNS+4) number” means the DUNS number assigned by D&B plus a 4-character suffix that may be assigned by a business concern. (D&B has no affiliation with this 4-character suffix.)

This 4-character suffix may be assigned at the discretion of the business concern to establish additional SAM records for identifying alternative Electronic Funds Transfer (EFT) accounts (see FAR 32.11) for the same parent concern.

“Registered in the System for Award Management (SAM) database” means that—

(1) The contractor has entered all mandatory information, including the DUNS number or the DUNS+4 number, and Contractor and Government Entity (CAGE) code into the SAM database; and

(2) The contractor has completed the Core Data, Assertions, Representations and Certifications, and Points of Contact sections of the registration in the SAM database;

(3) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS). The Contractor will be required to provide consent for TIN validation to the Government as part of the SAM registration process; and

(4) The Government has marked the record “Active.”

(b) (1) By submission of an offer, the offeror acknowledges the requirement that a prospective awardee shall be registered in the SAM database prior to award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.

(2) The Offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation “Unique Entity Identifier” followed by the unique entity identifier that identifies the Offeror’s name and address exactly as stated in the offer. The Offeror also shall enter its EFT indicator, if applicable. The unique entity identifier will be used by the Contracting Officer to verify that the Offeror is registered in the SAM database.

(c) If the Offeror does not have a unique entity identifier, it should contact the entity designated at www.sam.gov for establishment of the unique entity identifier directly to obtain one. The Offeror should be prepared to provide the following information:

(1) Company legal business name.

(2) Tradestyle, doing business, or other name by which your entity is commonly recognized.

(3) Company Physical Street Address, City, State, and Zip Code.

(4) Company Mailing Address, City, State and Zip Code (if separate from physical).

(5) Company telephone number.

(6) Date the company was started.

(7) Number of employees at your location.

(8) Chief executive officer/key manager.

(9) Line of business (industry).

(10) Company Headquarters name and address (reporting relationship within your entity).

(d) If the Offeror does not become registered in the SAM database in the time prescribed by the Contracting Officer, the Contracting Officer will proceed to award to the next otherwise successful registered Offeror.

(e) Processing time, which normally takes 48 hours, should be taken into consideration when registering. Offerors who are not registered should consider applying for registration immediately upon receipt of this solicitation.

(f) Offerors may obtain information on registration at https://www.acquisition.gov .

1.9 FAR 52.211-14, NOTICE OF PRIORITY RATING FOR NATIONAL DEFENSE, EMERGENCY

PREPAREDNESS, AND ENERGY PROGRAM USE (APR 2008)

Any contract awarded as a result of this solicitation will be _ DX rated order; X DO-C2 rated order certified for national defense, emergency preparedness, and energy program use under the Defense Priorities and Allocations System (DPAS) (15 CFR 700), and the Contractor will be required to follow all of the requirements of this regulation.

1.10 FAR 52.215-1, INSTRUCTIONS TO OFFERORS--COMPETITIVE ACQUISITION (JAN 2017)

(a) Definitions. As used in this provision—

“Discussions” are negotiations that occur after establishment of the competitive range that may, at the Contracting Officer’s discretion, result in the offeror being allowed to revise its proposal.

“In writing,” “writing,” or “written” means any worded or numbered expression that can be read, reproduced, and later communicated, and includes electronically transmitted and stored information.

“Proposal modification” is a change made to a proposal before the solicitation’s closing date and time, or made in response to an amendment, or made to correct a mistake at any time before award.

“Proposal revision” is a change to a proposal made after the solicitation closing date, at the request of or as allowed by a Contracting Officer as the result of negotiations.

“Time,” if stated as a number of days, is calculated using calendar days, unless otherwise specified, and will include Saturdays, Sundays, and legal holidays. However, if the last day falls on a Saturday, Sunday, or legal holiday, then the period shall include the next working day.

(b) Amendments to solicitations. If this solicitation is amended, all terms and conditions that are not amended remain unchanged. Offerors shall acknowledge receipt of any amendment to this solicitation by the date and time specified in the amendment(s).

(c) Submission, modification, revision, and withdrawal of proposals.

(1) Unless other methods (e.g., electronic commerce or facsimile) are permitted in the solicitation, proposals and modifications to proposals shall be submitted in paper media in sealed envelopes or packages (i) addressed to the office specified in the solicitation, and (ii) showing the time and date specified for receipt, the solicitation number, and the name and address of the offeror. Offerors using commercial carriers should ensure that the proposal is marked on the outermost wrapper with the information in paragraphs (c)(1)(i) and (c)(1)(ii) of this provision.

(2) The first page of the proposal must show—

(i) The solicitation number;

(ii) The name, address, and telephone and facsimile numbers of the offeror (and electronic address if available);

(iii) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item;

(iv) Names, titles, and telephone and facsimile numbers (and electronic addresses if available) of persons authorized to negotiate on the offeror’s behalf with the Government in connection with this solicitation; and

(v) Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent’s authority, unless that evidence has been previously furnished to the issuing office.

(3) Submission, modification, revision, and withdrawal of proposals.

(i) Offerors are responsible for submitting proposals, and any modifications or revisions, so as to reach the Government office designated in the solicitation by the time specified in the solicitation. If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that proposal or revision is due.

(ii)(A) Any proposal, modification, or revision received at the Government office designated in the solicitation after the exact time specified for receipt of offers is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition; and—

(1) If it was transmitted through an electronic commerce method authorized by the solicitation, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals; or

(2) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of offers and was under the Government’s control prior to the time set for receipt of offers; or

(3) It is the only proposal received.

(B) However, a late modification of an otherwise successful proposal that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.

(iii) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the proposal wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.

(iv) If an emergency or unanticipated event interrupts normal Government processes so that proposals cannot be received at the office designated for receipt of proposals by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation, the time specified for receipt of proposals will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.

(v) Proposals may be withdrawn by written notice received at any time before award. Oral proposals in response to oral solicitations may be withdrawn orally. If the solicitation authorizes facsimile proposals, proposals may be withdrawn via facsimile received at any time before award, subject to the conditions specified in the provision at 52.215-5, Facsimile Proposals. Proposals may be withdrawn in person by an offeror or an authorized representative, if the identity of the person requesting withdrawal is established and the person signs a receipt for the proposal before award.

(4) Unless otherwise specified in the solicitation, the offeror may propose to provide any item or combination of items.

(5) Offerors shall submit proposals in response to this solicitation in English, unless otherwise permitted by the solicitation, and in U.S. dollars, unless the provision at FAR 52.225-17, Evaluation of Foreign Currency Offers, is included in the solicitation.

(6) Offerors may submit modifications to their proposals at any time before the solicitation closing date and time, and may submit modifications in response to an amendment, or to correct a mistake at any time before award.

(7) Offerors may submit revised proposals only if requested or allowed by the Contracting Officer.

(8) Proposals may be withdrawn at any time before award. Withdrawals are effective upon receipt of notice by the Contracting Officer.

(d) Offer expiration date. Proposals in response to this solicitation will be valid for the number of days specified on the solicitation cover sheet (unless a different period is proposed by the offeror).

(e) Restriction on disclosure and use of data. Offerors that include in their proposals data that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, shall—

(1) Mark the title page with the following legend:

This proposal includes data that shall not be disclosed outside the Government and shall not be duplicated, used, or disclosed—in whole or in part—for any purpose other than to evaluate this proposal. If, however, a contract is awarded to this offeror as a result of—or in connection with—the submission of this data, the Government shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting contract. This restriction does not limit the Government's right to use information contained in this data if it is obtained from another source without restriction. The data subject to this restriction are contained in sheets [insert numbers or other identification of sheets]; and

(2) Mark each sheet of data it wishes to restrict with the following legend:

Use or disclosure of data contained on this sheet is subject to the restriction on the title page of this proposal.

(f) Contract award.

(1) The Government intends to award a contract or contracts resulting from this solicitation to the responsible offeror(s) whose proposal(s) represents the best value after evaluation in accordance with the factors and subfactors in the solicitation.

(2) The Government may reject any or all proposals if such action is in the Government’s interest.

(3) The Government may waive informalities and minor irregularities in proposals received.

(4) The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a cost or price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.

(5) The Government reserves the right to make an award on any item for a quantity less than the quantity offered, at the unit cost or prices offered, unless the offeror specifies otherwise in the proposal.

(6) The Government reserves the right to make multiple awards if, after considering the additional administrative costs, it is in the Government’s best interest to do so.

(7) Exchanges with offerors after receipt of a proposal do not constitute a rejection or counteroffer by the Government.

(8) The Government may determine that a proposal is unacceptable if the prices proposed are materially unbalanced between line items or subline items. Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more line items is significantly overstated or understated as indicated by the application of cost or price analysis techniques. A proposal may be rejected if the Contracting Officer determines that the lack of balance poses an unacceptable risk to the Government.

(9) If a cost realism analysis is performed, cost realism may be considered by the source selection authority in evaluating performance or schedule risk.

(10) A written award or acceptance of proposal mailed or otherwise furnished to the successful offeror within the time specified in the proposal shall result in a binding contract without further action by either party.

(11) If a post-award debriefing is given to requesting offerors, the Government shall disclose the following information, if applicable:

(i) The agency’s evaluation of the significant weak or deficient factors in the debriefed offeror’s offer.

(ii) The overall evaluated cost or price and technical rating of the successful and the debriefed offeror and past performance information on the debriefed offeror.

(iii) The overall ranking of all offerors, when any ranking was developed by the agency during source selection.

(iv) A summary of the rationale for award.

(v) For acquisitions of commercial items, the make and model of the item to be delivered by the successful offeror.

(vi) Reasonable responses to relevant questions posed by the debriefed offeror as to whether source-selection procedures set forth in the solicitation, applicable regulations, and other applicable authorities were followed by the agency.

1.11 FAR 52.216-1, TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a firm-fixed price contract resulting from this solicitation.

1.12 FAR 52.222-5, CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK

(MAY 2014)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror’s request for a wage determination for a secondary site of the work.

1.13 FAR 52.222-23, NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) *

(a) The offerors attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation Goals for female for each trade participation for each trade

69.1 6.9

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246 as amended, and the regulations in 41 CFR 60.4 shall be based on its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. T he Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60.4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the--

(1) Name, address, and telephone number of the subcontractor; (i) Employer identification number of the subcontractor;

(2) Estimated dollar amount of the subcontract;

(3) Estimated starting and completion dates of the subcontract; and

(4) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Honolulu.

1.14 FAR 52.225-12, NOTICE OF BUY AMERICAN REQUIREMENT--CONSTRUCTION MATERIALS

UNDER TRADE AGREEMENTS (MAY 2014)

(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “designated country construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American—Construction Materials Under Trade Agreements” (Federal Acquisition Regulation (FAR) clause 52.225-11).

(b) Requests for determination of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of FAR clause 52.225-11 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction materials, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(4)(i) of FAR clause 52.225-11.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign construction material, other than designated country construction material, that is not listed by the Government in this solicitation in paragraph (b)(3) of FAR clause 52.225-11, the offeror also may submit an alternate offer based on use of equivalent domestic or designated country construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of FAR clause 52.225-11 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of FAR clause 52.225-11 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic or designated country construction material, and the offeror shall be required to furnish such domestic or designated country construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

1.15 FAR 52.233-2, SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the General Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from NAVFACENGCOM, Pacific (ACQ31), Construction Contracts Branch, 258 Makalapa Drive, Suite 100, Pearl Harbor, HI 96860-3134.

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

1.16 FAR 52.236-27, SITE VISIT (CONSTRUCTION) (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigation and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) A one-time pre-proposal site visit has been scheduled for [Tuesday 24 April at 9:00 A.M., H.S.T. This site visit is to provide Offerors with an opportunity to familiarize themselves with the job sites and conditions to be encountered and is not for the purpose of answering questions.

(c) Offerors interested in attending the pre-site visit shall complete the forms located at the end of Document 00100 and must email the following information to Ms. Casey Sugihara at casey.sugihara@navy.mil on or before 11 April 2018, 2:00 P.M,. H.S.T.:

FIRM:

VISITOR’S NAME (FIRST & LAST NAME):

VISITOR’S SSN:

DRIVER’s LICENSE NO.:

DATE OF BIRTH:

MAKE/MODEL OF VEHICLE:

LICENSE PLATE:

An attendee may not be able to join the site visit if the “Marine Corps Base Hawaii Contractor/Vendor/Service Provider Access Request” form is submitted after the due date and time specified. Additionally, the specified due date and time for submission of the information and form is firm. No late submission of additional vehicles will be accepted.

*If the person is NOT a U.S. citizen, the alien registration number and working VISA number shall be provided.

(d) Attendees must meet at the MCBH Bowling Alley Parking Lot, where a short Safety Briefing will be given prior to the start of the Site Visit. A map with directions to the parking lot is located at the end of Document 00100.

(e) This is an escorted site visit and parking is limited at certain locations; therefore, each company should limit the NUMBER OF ATTENDEES TO FOUR (4). Carpooling is highly recommended because parking will be limited.

(f) Also, please be informed:

(1) All attendees must stop at the MCBH Pass House to register their vehicle.

(2) RapidGate credentials with authorized MCBH access are honored, but no DBIDS credentials will be honored.

(3) Be sure to have current Hawaii: vehicle registration, safety inspection, and valid vehicle no-fault insurance.

(g) The above information furnished by you and protected under the Privacy Act shall not be released unless permitted by law and/or you have consented to such release. The information is required pursuant to the following:

AUTHORITY: 5 U.S.C. 552a; SECNAVINST 5211.5E; and MCO 5110.1C

PRINCIPAL PURPOSE: To record data for all vehicles to be registered aboard Marine Corps Base Hawaii.

ROUTINE USES: The social security will be used to complete the Marine Corps Base Hawaii access application process. This information is entered into National Crime Information Center (NCIC) and the Consolidated Law Enforcement Operations Center (CLEOC) to conduct a criminial history check on the person requesting access to Marine Corps Base Hawaii.

DISCLOSURE IS VOLUNTARY: The social security number is used to positively identify the applicant requesting access to Marine Corps Base Hawaii, and as a conduit to check criminal records. Disclosure is voluntary, however failure to provide the requested information may deny you access to Marine Corps Base Hawaii.

1.17 FAR 52.236-28, PREPARATION OF PROPOSALS--CONSTRUCTION (OCT 1997)

(a) Proposals must be (1) submitted on the forms furnished by the Government or on copies of those forms, and (2) manually signed. The person signing a proposal must initial each erasure or change appearing on any proposal form.

(b) The proposal form may require offerors to submit proposed prices for one or more items on various bases, including--

(1) Lump sum price;

(2) Alternate prices;

(3) Units of construction; or

(4) Any combination of subparagraphs (b)(1) through (b)(3) of this provision.

(c) If the solicitation requires submission of a proposal on all items, failure to do so may result in the proposal being rejected without further consideration. If a proposal on all items is not required, offerors should insert the words "no proposal" in the space provided for any item on which no price is submitted.

(d) Alternate proposals will not be considered unless this solicitation authorizes their submission.

1.18 DFARS 252.204-7008, COMPLIANCE WITH SAFEGUARDING COVERED DEFENSE INFORMATION

CONTROLS (OCT 2016)

(a) Definitions. As used in this provision—

“Controlled technical information,” “covered contractor information system,” “covered defense information,” “cyber incident,” “information system,” and “technical information” are defined in clause 252.204-7012, Safeguarding Covered Defense Information and Cyber Incident Reporting.

(b) The security requirements required by contract clause 252.204-7012, shall be implemented for all covered defense information on all covered contractor information systems that support the performance of this contract.

(c) For covered contractor information systems that are not part of an information technology service or system operated on behalf of the Government (see 252.204-7012(b)(2)—

(1) By submission of this offer, the Offeror represents that it will implement the security requirements specified by National Institute of Standards and Technology (NIST) Special Publication (SP) 800-171 “Protecting Controlled Unclassified Information in Nonfederal Information Systems and Organizations” (see http://dx.doi.org/10.6028/NIST.SP.800-171) that are in effect at the time the solicitation is issued or as authorized by the contracting officer not later than December 31, 2017.

(2)(i) If the Offeror proposes to vary from any of the security requirements specified by NIST SP 800-171 that are in effect at the time the solicitation is issued or as authorized by the Contracting Officer, the Offeror shall submit to the Contracting Officer, for consideration by the DoD Chief Information Officer (CIO), a written explanation of—

(A) Why a particular security requirement is not applicable; or

(B) How an alternative but equally effective, security measure is used to compensate for the inability to satisfy a particular requirement and achieve equivalent protection.

(ii) An authorized representative of the DoD CIO will adjudicate offeror requests to vary from NIST SP 800-171 requirements in writing prior to contract award. Any accepted variance from NIST SP 800-171 shall be incorporated into the resulting contract.

1.19 DFARS 252.215-7008, ONLY ONE OFFER (OCT 2013)

(a) After initial submission of offers, the Offeror agrees to submit any subsequently requrested additional cost or pricing data if the Contracting Officer notifies the offeror that—

(1) Only one offer was received; and

(2) Additional cost or pricing data is required in order to determine whether the price is fair and reasonable or to comply with the statutory requirement for certified cost or pricing data (10 U.S.C. 2306a and FAR 15.403-3).

(b) Requirement for submission of additional cost or pricing data. Except as provided in paragraph (c) of this provision, the Offeror shall submit additional cost or pricing data as follows:

(1) If the Contracting Officer notifies the Offeror that additional cost or pricing data are required in accordance with paragraph (a) of this clause, the data shall be certified unless an exception applies (FAR 15.403-1(b)).

(2) Exceptions from certified cost or pricing data. In lieu of submitting certified cost or pricing data, the Offeror may submit a written request for exception by submitting the information described in the following paragraphs. The Contracting Officer may require additional supporting information, but only to the extent necessary to determine whether an exception should be granted, and whether the price is fair and reasonable.

(i) Identification of the law or regulation establishing the price offered. If the price is controlled under law by periodic rulings, reviews, or similar actions of a governmental body, attach a copy of the controlling document, unless it was previously submitted to the contracting office.

(ii) Commercial item exception. For a commercial item exception, the Offeror shall submit, at a minimum, information on prices at which the same item or/ similar items have previously been sold in the commercial market that is adequate for evaluating the reasonableness of the price for this acquisition. Such information may include—

(A) For catalog items, a copy of or identification of the catalog and its date, or the appropriate pages for the offered items, or a statement that the catalog is on file in the buying office to which the proposal is being submitted. Provide a copy or describe current discount policies and price lists (published or unpublished), e.g., wholesale, original equipment manufacturer, or reseller. Also explain the basis of each offered price and its relationship to the established catalog price, including how the proposed price relates to the price of recent sales in quantities similar to the proposed quantities;

(B) For market-priced items, the source and date or period of the market quotation or other basis for market price, the base amount, and applicable discounts. In addition, describe the nature of the market; or

(C) For items included on an active Federal…