Attachment 1 - hangar 5500 layout.docx

DOCX document 255 KB Posted

Attached to
V-22 Maintenance Repair and Overhaul (MRO) Production Line Installation Hangar 5500 MCAS Iwakuni, Japan
Solicitation number
N6264926RC001
Issued by

About this file

This file is a facility layout diagram for Hangar 5500 at Marine Corps Air Station (MCAS) Iwakuni, Japan. The document visually depicts the spatial configuration and dimensions of the hangar space where the V-22 Maintenance Repair and Overhaul (MRO) production line will be installed. The layout shows the hangar's structural elements, floor plan, and available square footage, providing contractors with critical facility information necessary for planning the installation of MRO equipment, workstations, and operational areas within the designated space.

This attachment serves as a planning and reference tool for prospective quoters responding to solicitation N6264926RC001. Contractors must use the hangar layout to assess their ability to design and execute the production line installation, including equipment placement, workflow efficiency, personnel movement, and compliance with facility constraints. The layout is essential for developing accurate cost estimates and technical proposals, particularly for contractors authorized to operate in Japan under DFARS 225.1103(3) requirements.

View the file

Other files

File Type Posted
Attachment 3 - OSHE Provisions.docx DOCX document
Attachment 2 - V22 MRO Line Install GFE Lists.xlsx XLSX spreadsheet
Solicitation - N6264926RC001.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment (1) 12 January 2026

Attachment 1 – MCAS Iwakuni Facilities Diagram

1. Hangar 5500

1.1 Hangar 5500 V-22 MRO Production Line General Layout

The contractor shall provide final design and layout drawings for three (3) V-22 maintenance slots in the South Bay of Hangar 5500 (see Figure 1).

South Bay North Bay

Figure 1 - V-22 MRO Production PMI Line Hangar Layout

1.2 Assigned Contractor’s Working Area

The U.S Government will provide the following working areas:

1. Hangar space: South Bay with power outlets (120 V - 4 units, 270/115 V - 4 units), and North Bay (270/115 V – 1 unit).

2. The Aircraft Paint Booth is located in Hangar 2700 (“Corrosion Control Hangar”). – CORROSION CONTROL HANGAR

3. Office space (climate controlled): approximately 53 of office area with power outlets (120 V – 12 units), and six (6) Ethernet LAN drops.

4. Warehouse space (not climate controlled): approximately 91 of warehouse area for tools, support equipment (SE), etc.

NOTE: Contractor’s assigned Office and Warehouse areas are TENTATIVE. Once the contract for this project is awarded, the USG will work with the contractor to finalize those assigned areas.