This is a Statement of Work (SOW) for commercial aerial work platform support services for the USNS WALLY SCHIRRA (N23198).

The contractor shall provide two (2) aerial work platforms (manlifts), each with a vertical reach of 120-135 feet, delivered in clean, safe, and fully operational condition with full fuel tanks. The contractor is responsible for delivering and retrieving equipment at times and locations specified by the Point of Contact and must provide a safety and operational demonstration to designated personnel upon delivery. The contractor must also provide equipment support and replacement services, including delivery of a replacement unit within three (3) hours of notification in the event of equipment breakdown or safety discrepancies. The Period of Performance runs from 06 FEB 2026 @ 0800 to 03 MAR 2026 @ 1700. The Point of Contact information is redacted in the document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

COMMERCIAL AERIAL WORK PLATFORM /MANLIFT SUPPORT, USNS WALLY

SCHIRRA (N23198)

1. Scope of Work:

This Statement of Work outlines the requirements for a vendor to provide two (2) commercial Aerial Work Platforms (manlifts) for the USNS WALLY SCHIRRA.

2. Requirements:

The Contractor shall provide the following:

2.1 Equipment:

Two (2) aerial work platforms, each with a vertical reach of 120-135 feet.

All equipment must be delivered in a clean, safe, and fully operational condition.

Equipment must be delivered with a full fuel tank.

2.2 Service:

The Contractor must deliver and retrieve the equipment at the time and location specified by the

Point of Contact.

Upon delivery, the Contractor must provide a safety and operational demonstration for designated personnel.

2.3 Equipment Support and Replacement:

In the event of an equipment breakdown or safety discrepancy, the Contractor is required to provide a replacement unit within three (3) hours of notification.

3. Period of Performance:

06 FEB 2026 @ 0800 to 03 MAR 2026 @ 1700.