22-2498 Amendment No. 0001.pdf
PDF 2 MB Posted
- Solicitation number
- N62478-22-R-2498
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 22-2498 Amendment No. 0004.pdf | ||
| 22-2498 Amendment No. 0003.pdf | ||
| 22-2498 Offeror Pricing Schedule (Amendment No. 0003).xlsx | XLSX spreadsheet | |
| 22-2498 Amendment No. 0002.pdf | ||
| 22-2498 Offeror Pricing Schedule (Amendment No. 0002).xlsx | XLSX spreadsheet | |
| 22-2498 Notice No 4 QA Notice.pdf | ||
| 22-2498 Notice No 3 Site Visit-Conference.pdf | ||
| RFP No. N62478-22-R-2498.pdf | ||
| 22-2498 Offeror Pricing Schedule.xlsx | XLSX spreadsheet | |
| 22-2498 Notice No 1 General Info.pdf | ||
| 22-2498 Notice No 2 CCR EFT MISC.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ACQR5913537
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
RFP No. N62478-22-R-2498, MAINTENANCE, REPAIR, OPERATIONS OR OVERHAUL SERVICES FOR THE ADMIRAL CLAREY (FORD ISLAND)
BRIDGE FACILITY, PEARL HARBOR, HAWAII
The revised proposal receipt date is March 31, 2022, 2:00PM, HST.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 21-Mar-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N6247822R2498
X 9B. DATED (SEE ITEM 11)
28-Feb-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
21-Mar-2022
CODE
NAVFAC HAWAII
SERVICES ACQUISITION DIVISION (PRJ233)
400 MARSHALL ROAD
JBPHH HI 96860-3139
N62478 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N6247822R2498
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
SUMMARY OF CHANGES (REVISED)
SUMMARY OF CHANGES
SECTION C – DESCRIPTION/SPEC/WORK STATEMENT
Annex 0200000 – Replace in its entirety with the attached pages 1 through 30 (Amendment No. 0001).
Annex 15020000 – Replace in its entirety with the attached pages 1 through 14 (Amendment No. 0001).
SECTION F - DELIVERIES OR PERFORMANCE
Section F-1 – Replace page 41 of 50 with the attached page 41 of 50 (Amendment No. 0001).
SECTION J – LIST OF ATTACHMENTS
Attachment J-0200000-02 – Replace pages 13 through 31 with the attached pages 13 through 31 (Amendment No.
0001).
(End of Summary of Changes)
14-22-2498
0200000, Page 1 of 30 (Amendment No. 0001)
0200000 – Management and Administration
Spec Item Title
2 Management and Administration
2.1 Definitions and Acronyms
2.2 General Information
2.2.1 Government Regular Working Hours
2.2.1.1 Observed Federal Holidays
2.2.1.2 Restriction to Contractor Working Hours
2.2.2 Wage Determinations
2.2.3 Requirements Hierarchy
2.3 General Administrative Requirements
2.3.1 Required Conferences and Meetings
2.3.2 Training for Maintenance and Operation of New and Replacement Systems and Equipment
2.3.3 Partnering
2.3.3.1 Informal Partnering
2.3.3.2 Contract Partnering Administration
2.3.3.3 Contract Partnering Session Attendees
2.3.4 Permits and Licenses
2.3.5 Insurance
2.3.5.1 Certificate of Insurance
2.3.5.2 Minimum Insurance Amounts
2.3.6 Protection of Government Property
2.3.7 Government Information Technology (IT) System
2.3.8 Directives, Instructions, and References
2.3.9 Invoicing Procedures
2.3.10 Forms
2.3.11 Trademarks
2.4 Government-Furnished Property, Materials and Services
2.4.1 Government-Furnished Facilities (GFF)
2.4.2 Government-Furnished Utilities
2.4.3 Government-Furnished Materials (GFM)
2.4.4 Government-Furnished Equipment (GFE)
2.4.5 Government-Furnished Services (GFS)
2.5 Contractor-Furnished Items
2.6 Management
2.6.1 Safeguarding Information
2.6.2 Dissemination of Information
2.6.3 Work Reception
2.6.4 Work Control
2.6.5 Work Schedule
2.6.5.1 Annual Work Schedule
2.6.5.2 Monthly Work Schedule
2.6.5.3 Work Completion Schedule
2.6.6 Deliverables
2.6.7 Service Interruptions
2.6.8 Filing System
2.6.9 Quality Management System (QMS)
2.6.9.1 Quality Management (QM) Plan
2.6.9.2 Quality Inspection and Surveillance
2.6.9.3 Quality Inspection and Surveillance Report
2.6.10 Property Management Plan
2.6.11 System and Equipment Replacement
2.7 Personnel Requirements
0200000, Page 2 of 30 (Amendment No. 0001)
2.7.1 Key Personnel
2.7.1.1 Project Manager (PM)
2.7.1.2 Quality Manager
2.7.1.3 Site Safety and Health Officer (SSHO)
2.7.1.3.1 Additional Site Safety and Health Officer (SSHO) Requirements and Duties
2.7.1.4 Environmental/Energy Manager
2.7.2 Employee Requirements
2.7.2.1 Employee Certification and Training
2.7.2.2 Employee Appearance
2.7.2.3 Employee Conduct
2.7.2.4 Identification as Contractor Employee
2.7.2.5 Removal of Employees
2.7.2.6 Proof of Legal Residency
2.7.3 Service Contract Reporting (SCR)
2.8 Security Requirements
2.8.1 Employee Listing
2.8.2 Vehicles
2.8.3 Passes and Badges
2.8.4 Access to Installation
2.8.4.1 DBIDS Program
2.8.4.2 DBIDS Credentials
2.8.4.3 DBIDS Paper Passes
2.8.5 Access to Buildings
2.8.6 Access Arrangements
2.8.6.1 Escort Arrangement for Secured Areas
2.8.7 Security Clearances
2.8.8 Access to Sensitive Unclassified Information
2.8.9 Employee Status
2.9 Contractor Safety Program
2.9.1 Accident Prevention Plan (APP)
2.9.2 Activity Hazard Analysis (AHA)
2.9.3 Safety and Occupational Health (SOH) Risks and Compliance Plans
2.9.3.1 Alcohol and Drug Abuse Prevention Plan
2.9.3.2 Chemical Hazard Communication Program
2.9.3.3 Confined Space Program
2.9.3.4 Critical Lift Plan
2.9.3.5 Fall Prevention and Protection Plan
2.9.4 Crane Operations
2.9.4.1 Crane Inspections
2.9.4.2 Rigging Gear
2.9.4.3 Crane Operators
2.9.5 Accident and Damage Reporting
2.9.5.1 Accident Reporting and Notification Criteria
2.9.6 Fire Protection
2.9.7 Monthly On-Site Labor Report
2.9.8 OSHA Citations and Violations
2.9.9 Safety Inspections and Monitoring
2.9.10 Safety Certification
2.9.11 Safety Apparel on Jobsites
2.9.12 Emergency Medical Treatment
2.10 Environmental Management and Sustainability
0200000, Page 3 of 30 (Amendment No. 0001)
2.10.1 Energy Management Program
2.10.2 Environmental Protection
2.10.2.1 Non-Regulated Waste Disposal
2.10.2.2 Regulated Waste Disposal
2.10.2.3 Universal Waste
2.10.2.4 Spill Prevention, Containment, and Clean-up
2.10.2.5 Hazardous Material Management
2.10.2.6 Protection of Endangered and Threatened Species (Flora and Fauna)
2.10.2.7 Noise Control
2.10.2.8 Salvage
2.10.2.9 Asbestos Containing Material (ACM)
2.10.3 Sustainable Procurement and Practices
2.10.3.1 Environmentally Preferable Products
2.10.3.2 Use of Recovered Materials
2.10.3.3 Use of Bio-based Products
2.11 Disaster Preparedness
2.12 Technical Library
2.13 Warranty Management
2.14 Recurring Work Procedures
2.14.1 Notification to the Government for Work Above the Recurring Work Limitations
2.14.2 Recurring Work Exhibit Line Item Numbers (ELINs)
2.15 Non-Recurring Work
2.15.1 Unit Priced Task (UPT) Work (Non-Negotiated)
2.15.1.1 Acceptance and Performance
2.15.1.2 Invoicing and Receiving Payment
2.15.2 Unit Priced Labor (UPL)Work (Negotiated)
2.15.2.1 Non-recurring Preparation of Proposals
2.15.2.1.1 Labor Requirements
2.15.2.1.2 Direct Material and Construction Equipment Requirements
2.15.2.2 Issuance of Final Task Order
2.15.3 Non-Recurring Work ELINS
0200000, Page 4 of 30 (Amendment No. 0001)
0200000 - Management and Administration
Spec Item Title Description
2 Management and
Administration
2.1 Definitions and
Acronyms
Definitions and Acronyms are listed in J-0200000-01.
2.2 General
Information
2.2.1 Government
Regular Working
Hours
The Government's regular working hours are from 0700-1600, five days per week, Monday through Friday, except observed Federal holidays. Exceptions to the regular hours of operation are detailed in subsequent sections of this
PWS. Work in certain annexes or sub-annexes require Contractor continuous operations, 24 hours a day, every day of the year including holidays. The performance of other work requirements shall be accomplished within the
Government’s regular working hours unless the specific work requirement specified herein necessitates otherwise. Any other work outside Government regular working hours requires prior KO approval.
2.2.1.1 Observed Federal
Holidays
The Government observes the following holidays: New Year’s Day, Martin
Luther King Jr.’s Birthday, President’s Day, Memorial Day, Juneteenth Day, Independence Day, Labor Day, Columbus Day, Veterans’ Day, Thanksgiving
Day, and Christmas Day.
2.2.1.2 Restriction to
Contractor
Working Hours
If the Contractor wishes to work outside of the Government's regular working hours for the Contractor’s convenience, the Contractor shall submit a written
Request to Work Outside Government’s Regular Working Hours per Section
F. Excludes work to be performed during specified hours.
2.2.2 Wage
Determinations
Wage Determinations are included in J-0200000-02.
2.2.3 Requirements
Hierarchy
Requirements or definitions specified in each spec item of this contract apply to subordinate paragraphs. For example, requirements shown in spec item 3.1 would apply to spec items 3.1.1, 3.1.2, 3.1.2.1 and so on.
Likewise, Performance Standards specified at a lower digit level (i.e. spec item 3.1.1, 3.1.2, 3.1.2.1) apply when performance is assessed at a higher tier
(i.e., spec item 3.1) based on the composite work requirements.
2.3 General
Administrative
Requirements
2.3.1 Required
Conferences and
Meetings
The Contractor shall attend administrative and coordination meetings.
2.3.2 Training for
Maintenance and
Operation of New and Replacement
Systems and
Equipment
When construction, renovation, or repair work is performed by means other than this contract, the Contractor shall attend Government provided training, as applicable, for maintenance and operation of new and replacement systems and equipment at no additional cost to the Government.
2.3.3 Partnering To increase the likelihood of successful performance of this contract, the
Government requires cohesive partnerships with its Contractors and subcontractors. Key stakeholders, including the supported commands who will receive services, principal individuals from NAVFAC, the performance assessment team, and representative(s) of the installation(s) will be invited to participate in the partnering process. Key members of the prime and sub-contractor teams, including senior management personnel must participate.
The partnership will draw on the strength of each organization in an effort to
0200000, Page 5 of 30 (Amendment No. 0001) achieve quality contract services done right the first time, within the contract price, as scheduled, and without any safety mishaps.
Partnering should accomplish three goals:
- The first goal is to develop a cohesive team with common purpose, commitment and established communication processes.
- The second goal of partnering is contract specific, identifying risks and opportunities for the team to address.
- The third goal is to sustain the Partnership throughout the contract by identifying and addressing issues that affect the Partnership.
2.3.3.1 Informal Partnering The Contracting Officer shall organize the initial Partnering Meeting with key personnel of the project team, including Contractor's personnel and
Government personnel. The initial session will be scheduled concurrent with the Pre-Performance Conference and held no later than 30 days after award and will be held at a Government provided facility as designated by the KO.
The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by
Contracting Officer. The senior Government stakeholder present will lead the meeting, however, the Contractor’s PM or senior representative is encouraged to participate as co-lead.
The Partners will determine the frequency of the follow-on sessions.
2.3.3.2 Contract Partnering
Administration
Upon award, the ACO will contact the Contractor, supported command(s), Region, and Installation(s) stakeholders, and the performance assessment team to discuss implementation of partnering. A partnership agreement, The
Charter, should be in place as early as possible so issues arising, even before work begins, can be resolved using the issues resolution process.
Replacement of Core Management Team members (stakeholders who attended the initial session and manage the contract work day-to-day) is discouraged since it will disrupt the synergy that has been developed. If replacement of a team member proves to be unavoidable, a follow-on partnering session must be held to officially turn the responsibilities of the position over to the new member.
The Core Management Team consisting of the attendees below must be present during the initial and all follow-on partnering sessions. These are the core mandatory attendees. Other stakeholders may attend if they desire or as recommended by the partners.
2.3.3.3 Contract Partnering
Session Attendees
The Contractor shall bring the necessary personnel to successfully partner on this contract. Asterisk indicates mandatory personnel.
President/Vice President
* Project Manager
* Quality Manager
Site Safety and Health Officer
2.3.4 Permits and
Licenses
The Contractor shall obtain all required permits, licenses, and authorizations to perform work under this contract and comply with all the applicable
Federal, state and local laws and regulations. The Contractor shall submit copies of Permits and Licenses per Section F.
For permits required by the Clean Water Act, State of Hawaii Administrative
Rules (HAR) 11-55, and Section 10 of the Rivers and Harbors Act, the Navy will submit permit applications and notices of intent (NOIs) as the facility
0200000, Page 6 of 30 (Amendment No. 0001) owner. The Contractor shall fill in the required forms and provide information specific to the project. The Government will review the information for accuracy and completeness, sign the application or NOI and coordinate submittal and any inquiries with the State or the Army Corps of Engineers.
The Contractor shall implement measures to ensure no foreign matter or debris enters into the harbor waters. No maintenance or repair operations can discharge dust, debris, paints, solvents, etc. into the harbor. The Contractor shall inform the KO so the KO can coordinate requirements with CNRH to ensure that necessary environmental protection measures are met.
2.3.5 Insurance The Contractor shall submit a Certificate of Insurance per Section F as evidence of the existence of the following insurance coverage in amounts not less than the amounts specified below in accordance with the FAR Clause
52.228-5, INSURANCE – WORK ON A GOVERNMENT
INSTALLATION. This insurance must be maintained during the performance period.
2.3.5.1 Certificate of
Insurance
The Certificate of Insurance shall provide for at least 30 calendar days written notice to the KO by the insurance company prior to cancellation or material change in policy coverage. Other requirements and information are contained in the aforementioned insurance clause.
2.3.5.2 Minimum
Insurance Amounts
The Contractor shall procure and maintain, during the entire period of performance under this contract, the following minimum insurance coverage:
Comprehensive General Liability: $500,000 per occurrence
Automobile Liability: $200,000 per person, $500,000 per occurrence, $20,000 per occurrence for property damage
Workmen's Compensation: As required by Federal and state worker's compensation and occupational disease statutes
Employer's Liability coverage: $100,000, except in states where worker's compensation may not be written by private carriers
Other as required by state law.
2.3.6 Protection of
Government
Property
During execution of the work, the Contractor shall protect Government property. The Contractor shall return areas damaged as a result of negligence under this contract to their original condition at no cost to the Government.
2.3.7 Government
Information
Technology (IT)
System
Additional information about NMCI may be obtained at http://www.eds.com/nmci.
2.3.8 References, Instructions, and
Directives
Department of Defense (DoD), Secretary of the Navy (SECNAV), Chief of
Naval Operations (OPNAV), and other applicable Directives, Instructions, and References are listed in J-0200000-05. The Contractor shall comply with the most current version of directives, instructions, and references including versions published during the term of the contract.
2.3.9 Invoicing
Procedures
Refer to Section G for invoicing instructions. Refer to Invoice Form in J-
0200000-06 for sample.
2.3.10 Forms Forms referenced in this Annex, e.g. accident reporting, and damage reporting are included among the Forms in J-0200000-07.
2.3.11 Trademarks The contractor shall not assert any claim, in any jurisdiction, based on trademark or other name or design-based causes of action that are based on
0200000, Page 7 of 30 (Amendment No. 0001) rights the contractor believes it has in the term(s) [contracting officers shall list term(s) (typically the assigned nomenclature, or portions thereof)] (the
“Designation(s)”), against the Government or others authorized by the
Government to use the Designation(s) (including the word(s), name, symbol, or design) acting within the scope of such authorization (i.e. claims for trademark infringement, dilution, trade dress infringement, unfair competition, false advertising, palming off, passing off, or counterfeiting).
Such authorization shall be implied by the award of a Government contract to any party for the manufacture, production, distribution, use, modification, maintenance, sustainment, or packaging of the products and services identified under this contract, and the scope of such implied authorization is defined as the use of the Designation(s) in performance under such contract by the prime contractor and its subcontractors and suppliers at any tier. In all other cases, the scope of the authorization will be defined by the Government in writing.
2.4 Government-
Furnished
Property, Materials and Services
In accordance with the following paragraphs, the Government will furnish or make available to the Contractor certain Government-owned utilities for use in connection with this contract.
2.4.1 Government-
Furnished Facilities
(GFF)
None.
2.4.2 Government-
Furnished Utilities
Availability of Utilities is identified in J-0200000-08.
2.4.3 Government-
Furnished
Materials (GFM)
None.
2.4.4 Government-
Furnished
Equipment (GFE)
None.
2.4.5 Government-
Furnished Services
(GFS)
None.
2.5 Contractor-
Furnished Items
Except for items identified as Government Furnished, the Contractor shall provide all equipment, materials, parts, supplies, components, and facilities to perform the requirements of this contract. The KO may inspect Contractor-furnished items for adequacy and compliance with contract requirements.
Inadequate or unsafe items shall be removed and replaced by the Contractor at no cost to the Government. Materials containing asbestos, lead, and polychlorinated biphenyls (PCBs) shall not be brought onsite. Energy efficient tools and equipment shall be used when available. The KO may at any time require Samples, Safety Data Sheets (SDS) or Manufacturer’s Data
Cut Sheets of Materials used in this contract.
Where parts/components are worn out and cannot be restored to serviceability, the Contractor shall replace the parts/components with new parts/components. The Contractor shall hold all the damaged or defective parts/components for 10 working days after the job completion and make these parts/components available to the COR for Government inspection. At the Government’s request, the Contractor shall rework their previous repairs if suspect inferior materials, equipment, and components were used or if the quality of the repair was substandard. This rework shall be at no cost to the
Government.
0200000, Page 8 of 30 (Amendment No. 0001)
Except as specified herein, salvaged or used materials are not permitted in any work. The Contractor shall maintain within the State of Hawaii, an adequate stock of repair parts/components to provide quick response to trouble calls and to minimize downtime requirements for all repairs.
See Attachment J-0200000-09 for a list of spare parts required to be on hand at all times for use in this contract.
2.6 Management The Contractor shall manage the total work effort associated with the services required herein to meet the performance objectives and standards. Such management includes but is not limited to planning, scheduling, cost accounting, report preparation, establishing and maintaining records, and quality assurance. The Contractor shall provide a staff with the necessary management expertise to ensure performance objectives and standards are met.
2.6.1 Safeguarding
Information
The Contractor shall safeguard controlled unclassified information and information associated with Government property in accordance with the latest revision of CNSSI 1253, DoDI 8582.01, NIST SP 800-53, NIST SP
800-171, SECNAV Defense Industrial Base (DIB) Memo, and applicable contract clauses. At a minimum, this information shall be protected at the
Basic confidentiality level as defined in NIST SP 800-171.
Contractor information and data systems that contain information associated with Government property shall comply with DoD Risk Management
Framework (RMF).
The Contractor shall develop Plans of Action and Milestones (POA&Ms) per
NIST SP 800-171, track accomplishment, and submit to the Government.
If a cybersecurity incident is encountered or suspected related to any
(Contractor or Government) Information Technology (IT) or Operating
Technology (OT) systems, including Monitoring and Control Systems, the
Contractor shall notify the Government.
2.6.2 Dissemination of
Information
If certain information cannot be provided to the public, state what information cannot be provided, when it will be provided, and to whom, e.g., DoD policy limits the dissemination of certain information. Instructions, Directives, and
References not releasable to the public, e.g., Floor Plans, Maps, Post Orders, and Standard Operating Procedures, will be made available after contract award to the successful offeror with appropriate credentials and a need to know.
2.6.3 Work Reception The Contractor shall provide the capability to receive, prioritize, correspond, and respond to trouble/service calls and task orders during Government regular working hours and provide a point of contact at a local or toll free number who can perform the above function during other than Government regular working hours.
2.6.4 Work Control The Contractor shall implement all necessary work control procedures to ensure timely accomplishment of work requirements, as well as to permit tracking and reporting of work in progress. The Contractor shall plan and schedule work to assure material, labor, and equipment are available to complete work requirements within the specified time limits and in conformance with the quality standards established herein. Verbal scheduling and work status updates shall be provided when requested by the KO or COR.
A status report of any item of work shall be provided within 2 hours of the
0200000, Page 9 of 30 (Amendment No. 0001) inquiry during regular working hours, and by 0900 the following work day for inquiries after regular working hours.
2.6.5 Work Schedule The Contractor's work shall not interfere with normal Government business.
In those cases where some interference is unavoidable, the Contractor shall minimize the impact and effects of the interference. The Contractor shall provide advance access of all of its work schedules to the Government. The
Contractor shall notify the KO and COR of any difficulty in scheduling work due to Government controls.
2.6.5.1 Annual Work
Schedule
Within 20 calendar days after the base year contract start date and within 15 calendar days of the Government’s notice of exercising an option, the
Contractor shall submit to the KO an annual schedule of planned performance of work in a format acceptable to the KO. The schedule shall indicate the day or days of the week that weekly or more frequent services will be accomplished, the week of the month that items of less than weekly frequency will be accomplished, the location to receive services, and the services to be accomplished.
2.6.5.2 Monthly Work
Schedule
The Contractor shall develop a monthly work schedule and shall submit this schedule to the KO for approval 5 working days prior to the start of the schedule month. Monthly invoices submitted prior to receipt of the required monthly work schedule will be considered incomplete and returned to the
Contractor. The schedule shall identify all work, including work ordered under the non-recurring portion of the contract. Non-Recurring quantity work by delivery order or job order number and title, the scheduled start and completion dates. Recurring services shall be identified and the date of performance indicated. Changes or additions to any job that prevent the
Contractor from completing the work on time or which change the scope of the work shall be reported to the KO in writing.
2.6.5.3 Work Completion
Schedule
A work completion schedule is required for all deficiencies which cannot be repaired/corrected within 2 working days of discovery.
The completion schedule shall be submitted within 2 working days of deficiency discovery, giving full details of work required, estimated labor and material/component costs, and estimated time of completion of repair work.
2.6.6 Deliverables Records and reports are specified in Section C and listed as deliverables in
Section F. The Contractor shall submit accurate and complete documents within the required timeframes as specified in Section F.
Government acceptance of deliverables will not relieve the Contractor of the responsibility for any error or omission which may exist in the deliverable, as the Contractor is responsible for all requirements of this contract.
2.6.7 Service
Interruptions
If any utilities or other services shall be discontinued (even temporarily) due to scheduled contract work, the Contractor shall notify the KO, affected tenants and customers 5 working days in advance. If the discontinued service is due to an emergency breakdown the Contractor shall notify the KO, affected tenants and customers as soon as practicable.
2.6.8 Filing System The Contractor shall create a filing system to store cumulative service/repair records for each system or bridge component in the inventory. A log book showing the date, person doing the maintenance and a brief statement of services performed shall be kept in a readily accessible place in the Control
House at pier 17. The log book shall have dedicated sections for each system or bridge component. A separate record file at the Contractor’s place of business shall be established and kept up to date for each system or bridge component. The records shall cover the following work:
0200000, Page 10 of 30 (Amendment No. 0001)
(a) Preventive maintenance inspection and service work.
(b) Trouble Calls.
(c) IDIQ Work.
(d) Renewed Components.
(e) Dates and times when the service(s) were scheduled, started, and completed.
(f) Full name(s) of the individual(s) who performed the services.
(g) Nature and extent of service and repair work performed, including:
completed preventive maintenance, description of conditions and deficiencies found during preventive maintenance visits, and deficiencies not completed during preventive maintenance visits; work performed during inspections and tests and disposition of deficiencies found during inspections/tests; quantity, description, and cost data of repair/replacement parts used and all required suppliers’ quotes.
Record entries shall be made within 2 working days from the completion of all work items performed under this contract.
2.6.9 Quality
Management
System (QMS)
The Contractor shall establish and maintain a complete QMS program in accordance with the provisions specified herein. The Contractor’s QMS program shall provide an effective and efficient means of identifying and correcting problems throughout the entire scope of operations. The
Contractor's QMS program shall address:
Accurate documentation of work processes, procedures, and output measures.
A systematic procedure for assessing compliance with performance objectives and standards.
Accurate documentation of quality inspections and surveillance conducted throughout the execution of work.
Assessment-driven corrective actions and process adjustments as appropriate in a timely manner.
2.6.9.1 Quality
Management (QM)
Plan
The Contractor shall develop and submit a QM Plan per Section F. The QM
Plan shall describe the QMS methodology and approaches used under this contract. If any changes are made during the period of performance, submit to the KO a revised QM Plan for acceptance.
The Contractor’s QM Plan shall include, at a minimum, the following:
• Policy and objectives of Quality Management System (QMS)
• Quality organization o List of personnel o Responsibilities & lines of authority o Training and qualifications
• Approach to assuring quality of services provided and conformance with performance objectives and standards
• Methods and procedures for effective planning, operation and control of processes and performance of work
• Procedures for inspection and surveillance of services o Scheduling and performance of inspection and surveillance o Measurement, data collection and analysis o Corrective action, preventive action, and continuous improvement o Oversight of subcontracted work
• Documentation and records management
0200000, Page 11 of 30 (Amendment No. 0001)
• Communication with government (customers)
2.6.9.2 Quality Inspection
and Surveillance
The Contractor shall establish and maintain an inspection and surveillance system in accordance with the FAR Clause 52.246-4, INSPECTION OF
SERVICES – FIXED PRICE, to ensure that the work performed conforms to the contract requirements. The Contractor shall document and maintain a file of all scheduled and performed inspections and surveillances, inspection and surveillance results, and dates and details of corrective and preventive actions. The quality inspection and surveillance file shall be the property of the Government and made available during the Government’s regular working hours. The file shall be submitted to the KO after termination of the contract per Section F.
2.6.9.3 Quality Inspection
and Surveillance
Report
The Contractor shall submit a copy of the Contractor Quality Inspection and
Surveillance Report per Section F. The Contractor Quality Inspection and
Surveillance Report shall include a summary and results of the quality inspection and surveillance events performed and assessment-driven corrective actions and process adjustments during the previous month. The
Government may adjust the frequency of the submittal based on the
Contractor’s quality of performance.
2.6.10 Property
Management Plan
The Contractor shall establish and maintain a plan that meets the contract clause requirements of Specification Item 2.4, Government-Furnished
Property, Materials and Services, of this Annex. This plan shall identify the
Contractor’s policies, procedures, and practices in receiving and performing physical inventories, repairing and maintaining, preserving and protecting, and reporting the disposition of accepted government property in its possession. The Property Management Plan shall be submitted per Section F.
2.6.11 System and
Equipment
Replacement
The Contractor shall maintain the integrity and performance of existing energy saving, water conservation or other sustainability design features of systems and equipment in the performance of repair and replacement work.
Except where otherwise specified, replacement components shall be of the same model/style or equivalent as the component being replaced. Substitutes for replacement components must be accepted by the KO prior to use. The
KO will furnish available information for the existing systems and equipment.
2.7 Personnel
Requirements
The Contractor shall comply with the personnel requirements stated below.
2.7.1 Key Personnel The Contractor shall submit a List of Key Personnel and Qualifications per
Section F. The Contractor shall provide any additional information requested by the KO necessary to certify their qualifications.
The Contractor shall submit an Organizational Chart per Section F showing lines of authority of the key personnel and on-site supervisor(s) for this contract. The chart shall include names of personnel and their position title in this contract. As a minimum, include the PM, Quality Manager, SSHO, and on-site supervisor(s) and who they will report directly to for this contract.
The key personnel shall be revised as applicable for the contract.
2.7.1.1 Project Manager
(PM)
The Contractor shall provide a PM and designated alternate, as applicable, who has the have full authority to act for the Contractor on all contract matters relating to this contract. The PM or alternate shall be on-site during the Government's regular working hours and shall be available on-site within one hour after the Government's regular working hours.
The PM shall have at least three years of experience in managing a workforce providing services on contracts of similar size, scope and complexity.
0200000, Page 12 of 30 (Amendment No. 0001)
2.7.1.2 Quality Manager The Contractor shall provide a Quality Manager or designated alternate shall be on-site within during the Government's regular working hours and shall be available on-site within two hours after the Government’s regular working hours. The Quality Manager must report directly to a senior corporate official and shall not report directly to the Project Manager.
The Quality Manager shall have fulfilled the following pre-requisite training and experiences before being hired as the Quality Manager under this contract: The Quality Manager shall have at least three years of experience in preparing and enforcing QMS programs on contracts of similar size, scope and complexity. The Quality Manager may be the same person as the SSHO.
2.7.1.3 Site Safety and
Health Officer
(SSHO)
The SSHO must meet the requirements of EM 385-1-1 Section 1 and ensure that the requirements of 29 CFR 1926.16 are met for the project. Provide a
Safety oversight team that includes a minimum of one Competent Person at each project site to function as the Site Safety and Health Officer (SSHO).
The SSHO or an equally-qualified Designated Representative/alternate shall be on-site at all times when work is being performed to implement and administer the Contractor's safety program and government-accepted
Accident Prevention Plan. The SSHO's training, experience, and qualifications shall be as required by EM 385-1-1 paragraph 01.A.17, entitled
SITE SAFETY AND HEALTH OFFICER (SSHO), and all associated sub-paragraphs.
A Competent Person shall be provided for all of the hazards identified in the
Contractor's Safety and Health Program in accordance with the accepted
Accident Prevention Plan, and shall be on-site at all times when the work that presents the hazards associated with their professional expertise is being performed. Provide the credentials of the Competent Persons(s) to the
Contracting Officer for acceptance in consultation with the Safety Office.
The Contractor shall provide a SSHO whose primary duty and responsibility is to prepare and enforce the Contractor’s safety program on this contract.
The SSHO shall have fulfilled the following pre-requisite training and experiences before being hired as the SSHO under this contract:
The SSHO shall have completed five years of satisfactory experience in preparing and enforcing safety programs on contracts of similar size and complexity in the past or three years’ experience if he possesses a Certified
Safety Professional (CSP) or safety and health degree. The SSHO shall have completed the OSHA 30-hour construction safety class or equivalent and maintain competency through 24 hours of formal safety and health related coursework every four years. The SSHO may be the same person as the project manager but shall have fulfilled the pre-requisite qualification and experience.
2.7.1.3.1 Additional Site
Safety and Health
Officer (SSHO)
Requirements and
Duties
The SSHO must have completed a 40-hour contract safety awareness course based on the content and principles of EM-385-1-1, and instructed in accordance with the guidelines of ASSE/SAFE Z490.1, by a trainer meeting the qualifications of paragraph QUALIFIED TRAINER REQUIREMENTS.
If the SSHO does not have a current certification, certification must be obtained within 60 days, maximum of contract award.
As a minimum, this course shall provide the participant with knowledge of the unique EM 385-1-1 U.S. Army Corps of Engineers Safety and Health requirements. NAVFAC P-307 Management of Weight Handling Equipment
0200000, Page 13 of 30 (Amendment No. 0001)
Manual, Hazard Identification, Recommending Hazard Abatement Methods, Properly preparing a site specific Accident Prevention Plan (APP). Activity
Hazard Analysis (AHA), and other skills necessary to effectively manage a safety program for Contractors doing business with the U.S. Navy, NAVFAC, U.S. Army Corps of Engineers, and other Government DoD agencies.
The 40 Hour Construction Safety Hazard Awareness Course will include a written examination that will cover the following safety topics as it applies to the requirements identified in the
1) EM 385-1-1 U.S. Army Corps of Engineers Safety and Health
Requirements Manual.
The NAVFAC P-307 Management of Weight Handling Equipment Manual.
2.7.1.4 Environmental/
Energy Manager
The Contractor shall provide an Environmental/Energy Manager whose primary duty and responsibility is to ensure Contractor operations adhere to the goals and policies of the Environmental Management System, the
Installation Energy Plan, and other specified Sustainability requirements affecting this contract. The Environmental/Energy Manager shall develop, implement and monitor environmental strategies, policies and programs that promote sustainable development and examine the contract activities to establish where improvements can be made and ensure compliance with environmental legislation and energy policy.
The Environmental/Energy Manager shall have a minimum two years’ experience with environmental procedures similar to those of this contract;
familiarity with Environmental Management Systems (EMSs); and knowledge of environmental regulations and federal energy laws and policy
(including energy and water reduction requirements and renewable energy requirements) that are applicable to operations similar to those of this contract.
2.7.2 Employee
Requirements
The Contractor shall provide experienced, qualified, and capable personnel to perform the work in this contract. Personnel shall be fully knowledgeable of all safety, environmental, and energy requirements associated with the work they perform. Personnel shall speak, read, and comprehend English to the extent that they can perform the contract requirements and comply with installation emergency procedures.
2.7.2.1 Employee
Certification and
Training
The Contractor shall maintain personnel certification, training, and licensing records for employee requirements specified herein and within all technical annexes/sub-annexes. Certification, training, and licensing records shall be kept current and on file for the duration of the contract including all option periods. Records shall be made available for Government review within 4 hours of request.
2.7.2.2 Employee
Appearance
The Contractor shall ensure that all employees present a professional appearance that is appropriate for their position. The KO reserves the right to determine the acceptability of any clothing worn. All
Contractor/subcontractor employees working under this contract shall be identified by a distinctive nameplate, emblem, or patch attached in a prominent place on an outer garment. Employee identification shall not be substituted for station required passes or badges.
2.7.2.3 Employee Conduct Contractor employees shall conduct themselves in a proper, efficient, courteous and businesslike manner.
0200000, Page 14 of 30 (Amendment No. 0001)
2.7.2.4 Identification as
Contractor
Employee
Contractor employees shall identify themselves as Contractor personnel by introducing themselves or being introduced as Contractor personnel and displaying distinguishing badges or other visible identification for meetings with Government personnel. All Contractor employees shall appropriately identify themselves as contractor employees in telephone conversations and in formal and informal written correspondence.
2.7.2.5 Removal of
Employees
The Contractor shall remove from the site any individual whose continued employment is deemed by the KO to be contrary to the public interest or inconsistent with the best interests of National Security.
2.7.2.6 Proof of Legal
Residency
No employee or representative of the Contractor will be admitted to the site of work unless satisfactory Proof of Legal Residency is submitted per Section
F.
2.7.3 Service Contract
Reporting (SCR)
The Contractor shall report total dollar amount invoiced and all contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: https://www.sam.gov.
Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the
FY, all data shall be reported no later than October 31 of each calendar year.
Contractors may direct questions to the help desk, linked at https://www.sam.gov.
2.8 Security
Requirements
The Contractor shall comply with all Federal, state, and local security statutes, regulations, and requirements. The Contractor shall become acquainted with and comply with all Government regulations as posted, or as requested by the KO when required to enter a Government site. The
Contractor shall ensure that all security/entrance clearances are obtained.
2.8.1 Employee Listing The Contractor shall maintain a current Employee List and submit per Section
F. The list shall include employee’s name, supervisor, company, and level of security clearance.
2.8.2 Vehicles The company name shall be displayed on each of the Contractor's vehicles in a manner and size that is clearly visible. All vehicles shall display a valid state license plate that complies with State Vehicle Code. Vehicles shall meet all other requirement of the State Vehicle Code, such as safety standards, and shall carry proof of insurance and state registration, if applicable.
2.8.3 Passes and Badges All Contractor employees shall obtain the required employee and vehicle passes. The Contractor employees must be able to obtain Common Access
Cards (CAC) in accordance with security requirements. Each employee shall wear the Government issued badge over the front of the outer clothing. When an employee leaves the Contractor's service, the employee's Passes and
Badges shall be returned within 10 calendar days.
2.8.4 Access to
Installation
All Contractor personnel shall obtain access to the installation through enrollment and registration into the Defense Biometric Identification System
(DBIDS).
The Contractor shall provide the KO with the name of their designated
Service Contractor Administrator (SCA) for enrollment in DBIDS. Once enrolled, the Contractor must provide the DBIDS Registrar with an approved employee list and then direct their employees to register into DBIDS.
2.8.4.1 DBIDS Program DBIDS is an enterprise identity management and perimeter installation access control solution in which Contractor personnel who enroll, and are approved, 0200000, Page 15 of 30 (Amendment No. 0001) are subsequently granted access to the installation for a period up to three years, or the length of the contract, whichever is less, and are not required to obtain a new pass from the Base Pass and Identification Office for each visit.
There are no fees associated with obtaining a DBIDS credential.
The Government performs background screening and credentialing.
Throughout the year the Contractor employee must continue to meet background screening standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.
2.8.4.2 DBIDS Credentials Contractor employees shall furnish a completed copy of the SECNAV 5512/1 form to obtain the required background check and visit the local Navy
Installation Visitor Control Center to obtain a DBIDS credential once approved. The SECNAV 5512/1 form and additional information about
DBIDS can be found at: https://www.cnic.navy.mil/om/dbids.html.
The Contractor may initiate the adjudication process when a background screen failure results in disqualification from participation in DBIDS and the
Contractor employees do not agree with the reason for disqualification. The
Contractor may also apply for a waiver when a background screening failure results in disqualification from participation in DBIDS. The Commanding
Officer will be the final waiver determination authority.
The Contractor shall immediately collect employee DBIDS credentials and notify the KO in writing:
(1) That an employee has departed the company without having properly returned or surrendered their DBIDS credentials.
(2) That there is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the installation or anyone therein.
2.8.4.3 DBIDS Paper
Passes
In the event that a visitor, vendor, or Contractor employee elects not to participate in DBIDS, the individual will be issued a DBIDS paper pass from the Base Pass and Identification Office in order to access the installation. The time standard for the validity of a pass to access an installation will be not more than thirty (30) days and may be further restricted based on local policy or by Federal, DOD, Navy, and CNIC guidance.
The Government will not be responsible for any cost or lost time associated with obtaining paper passes or added vetting or inspections incurred by non-participants in the DBIDS credentialing process.
2.8.5 Access to
Buildings
The Contractor shall monitor and control access into restricted areas under their responsibility, allowing only those individuals who have been properly cleared into restricted areas or other controlled access areas. The Contractor shall comply with security requirements, plus those imposed by the installation Commander at all times. Personnel with access to special areas will have the appropriate screening and/or security clearance, and personnel requiring routine access to restricted areas will wear special badges authorizing access for those areas. Contractor personnel shall not enter restricted or controlled areas or installation facilities unless specifically authorized in performance of their duties. The Contractor shall secure all buildings and facilities entered during non-duty hours and will secure all
0200000, Page 16 of 30 (Amendment No. 0001) building and facilities under the Contractor’s cognizance at the end of each work day or shift period.
2.8.6 Access
Arrangements
The Contractor shall make all arrangements through the appropriate office necessary to obtain access to buildings, facilities and other work areas, and when necessary, arrange for them to be opened and closed by the controlling authority. The Government may issue keys to the Contractor. The
Contractor shall use due diligence and be responsible for compromised security systems to include replacement costs that result from its action or inaction.
2.8.6.1 Escort
Arrangement for
Secured Areas
The Contractor shall make arrangements for Government escort into secured areas requiring escort. The KO will provide information on applicable buildings, spaces and the appropriate point of contact.
The Contractor may experience delays while waiting for escorts. The
Government estimates the wait period can be up to 15 minutes. The
Contractor shall notify the Government Performance Assessment
Representative (PAR) and appropriate point of contract if an escort is not available after 15 minutes and access…