Offeror Pricing Schedule (AMD 0001).xlsx
XLSX spreadsheet 54 KB Posted
- Attached to
- Non-Recurring Work Contract for Carpet/Resilient Floor Replacement at Various Locations, Oahu, Hawaii
- Solicitation number
- N62478-20-R-2482
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 20-2482 Amendment No. 0002.pdf | ||
| 20-2482 Amendment No. 0001.pdf | ||
| 20-2482 Notice No. 4 Q&As.pdf | ||
| Offeror Pricing Schedule.xlsx | XLSX spreadsheet | |
| 20-2482 Notice No. 2 CCR EFT MISC.doc.pdf | ||
| 20-2482 Notice No. 1 General Info.doc.pdf | ||
| 20-2482 Notice No. 3 Conference.doc.pdf | ||
| N62478-20-R-2482 RFP.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Schedule of Work
| SCHEDULE OF WORK | ||||
| (TO BE COMPLETED AND SUBMITTED WITH THE OFFER) | ||||
| ITEM NO. | SUPPLIES/SERVICES | AMOUNT | ||
| 0001 | BASE PERIOD - NON-RECURRING WORK | |||
| Price to perform non-recurring work, for the 12-month Base Period, in accordance with all the terms of this contract. | EST | $ | 12,500.00 |
| 0002 | OPTION PERIOD ONE - NON-RECURRING WORK | |||
| Price to perform non-recurring work, for the 12-month Option Period One, in accordance with all the terms of this contract. | EST | $ | 12,500.00 |
| 0003 | OPTION PERIOD TWO - NON-RECURRING WORK | |||
| Price to perform non-recurring work, for the 12-month Option Period Two, in accordance with all the terms of this contract. | EST | $ | 12,500.00 |
| 0004 | OPTION PERIOD THREE - NON-RECURRING WORK | |||
| Price to perform non-recurring work, for the 12-month Option Period Three in accordance with all the terms of this contract. | EST | $ | 12,500.00 |
| 0005 | OPTION PERIOD FOUR - NON-RECURRING WORK | |||
| Price to perform non-recurring work, for the 12-month Option Period Four in accordance with all the terms of this contract. | EST | $ | 12,500.00 |
| TOTAL PRICE FOR CONTRACT LINE ITEM NUMBERS | ||
| (CLINs) 0001 THROUGH 0005 | $ | 62,500.00 |
| 9000 | Exhibit Line Items |
| See Attachment 0200000-07, Exhibit A - Base Period |
| 9001 | Exhibit Line Items |
| See Attachment 0200000-08, Exhibit B - Option Period One |
| 9002 | Exhibit Line Items |
| See Attachment 0200000-09, Exhibit C - Option Period Two |
| 9003 | Exhibit Line Items |
| See Attachment 0200000-10, Exhibit D - Option Period Three |
| 9004 | Exhibit Line Items |
| See Attachment 0200000-11, Exhibit E - Option Period Four |
BASE YR NON-RECURRING
ATTACHMENT J-0200000-08 OFFEROR
PROPOSED UNIT PRICE
Enter proposed unit price in this column. Price will automatically copy to the UNIT PRICE cell rounded to two decimal places.
Total Amount is Annual Price.
| EXHIBIT LINE ITEM NUMBERS |
| SOLICITATION/CONTRACT # N62478-20-R-2482 |
| EXHIBIT A - CLIN 9000 |
| Line Item 0001 - Non-Recurring Work |
| Line Item 0001 - Non-Recurring Work - BASE PERIOD |
| PROVIDE PRICES FOR NONRECURRING WORK - IN ACCORDANCE WITH SECTION C, SPEC ITEM 4 |
| ELINs A700 through A762 |
| ELIN / | |||||||
| Sub-ELIN | Short Description | Description Extended | Estimated Quantity | Unit of Issue | Unit Price | Extended Price | IMAP CAC |
| A700 | Remove Non-Asbestos vinyl/vinyl composition floor tile or sheet/resilient flooring in Room/Corridor. Remove down to underlayment or bare concrete (Davis-Bacon Act Wages Apply). | The Contractor shall remove existing Non-Asbestos vinyl/vinyl composition floor tiles or sheet/resilient floorings in areas other than stairway such as rooms and corridors etc. Line item includes normal removal of adhesive, disposal of all debris and clean-up. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 2,500.00 | SF | 0.0000 | $ - 0 | |
| A701 | Remove Non-Asbestos vinyl/vinyl composition floor tile or sheet/resilient flooring in Stairway. | ||||||
| Remove down to underlayment or bare concrete (Davis-Bacon Act Wages Apply). | The Contractor shall remove existing Non-Asbestos vinyl/vinyl composition floor tiles or sheet/resilient floorings in stairway. Line item includes normal removal of adhesive, disposal of all debris and clean-up. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 625.00 | SF | 0.0000 | $ - 0 | ||
| A702 | Remove roll or tile carpet in Room/Corridor. | ||||||
| Remove down to underlayment or bare concrete. | The Contractor shall remove existing roll or tile carpets in areas other than stairway such as rooms and corridors etc. Line item includes normal removal of underlayer padding, grippers and/or adhesive, disposal of all debris and clean-up. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 2,500.00 | SY | 0.0000 | $ - 0 | ||
| A703 | Remove roll or tile carpet in Stairway. Remove down to underlayment or bare concrete. | The Contractor shall remove existing roll or tile carpets in stairway. Line item includes normal removal of underlayer padding, grippers and/or adhesive, disposal of all debris and clean-up. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 625.00 | SY | 0.0000 | $ - 0 | |
| A704 | Remove wooden or vinyl baseboard in Room/Corridor. | The Contractor shall remove existing wooden or vinyl baseboards in areas other than stairway such as rooms and corridors etc. Line item includes preparation and painting of wall surface where baseboards are removed, with same color and gloss as existing paint. Line item also includes removal of all debris and clean-up. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 1,250.00 | LF | 0.0000 | $ - 0 | |
| A705 | Remove wooden or vinyl baseboard in Stairway. | The Contractor shall remove existing wooden or vinyl baseboards in stairway. Line item includes preparation and painting of wall surface where baseboards are removed, with same color and gloss as existing paint. Line item also includes removal of all debris and clean-up. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 375.00 | LF | 0.0000 | $ - 0 | |
| A706 | Sampling & Testing: Asbestos Floor Tile and Adhesive (Non-Friable) Sampling and Testing of Vinyl, Vinyl Composition Tile, Vinyl sheet/resilient flooring in Room/Corridor/Stairway in buildings other than School (Davis-Bacon Act Wages Apply). | The Contractor shall provide all requirements of sampling and testing for Asbestos and Asbestos Containing Materials (ACM) in Vinyl and Vinyl Composition Tile, Vinyl sheet/resilient flooring and adhesives to include sampling and testing in accordance with all applicable Federal, State and Military Codes/Regulations in building other than Schools. Line item includes sampling, testing and independent laboratory analysis and delivery of all related reports. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 250.00 | EA | 0.0000 | $ - 0 | |
| A707 | Sampling & Testing: Lead Based Paint (LBP and/or Paint With Lead (PWL) related to flooring work (moldings, trim, fascias, baseboard) in Room/Corridor/Stairway in buildings other than School (Davis-Bacon Act Wages Apply). | The Contractor shall provide all requirements of sampling and testing for Lead Based Paint (LBP) and/or Paint With Lead (PWL) in accordance with all applicable Federal, State and Military Codes/Regulations in buildings other than School. Line item includes sampling, testing and independent laboratory analysis and delivery of all related reports. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 250.00 | EA | 0.0000 | $ - 0 | |
| A708 | Remove Asbestos vinyl/vinyl composition floor tile or vinyl sheet/resilient flooring in Room/Corridor/Stairway of buildings other than School. Remove down to underlayment or bare concrete (Davis-Bacon Act Wages Apply). | The Contractor shall provide all requirements of Asbestos removal to include removal, disposal and sampling in accordance with all applicable Federal, State and Military Codes/Regulations and shall remove existing asbestos vinyl/vinyl composition floor tiles or vinyl sheet/resilient flooring, adhesives, or related Asbestos Containing Materials (ACM) in buildings other than School. Line item includes removal of adhesive, clean-up, and delivery of all asbestos waste to the appropriate disposal facility. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 1,250.00 | SF | 0.0000 | $ - 0 | |
| A709 | Remove Lead Based Paint (LBP and/or Paint With Lead (PWL) related to flooring work (moldings, trim, fascias, baseboard) in Room/Corridor/Stairway in buildings other than School (Davis-Bacon Act Wages Apply). | The Contractor shall provide all requirements of Lead Based Paint (LBP) and/or Paint With Lead (PWL) removal to include removal, disposal and sampling in accordance with all applicable Federal, State and Military Codes/Regulations and shall remove existing LBP and/or PWL associated with the flooring work. Line item includes removal of LBP/PWL, clean-up, and delivery of all LBP/PWL waste to the appropriate disposal facility. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 1,250.00 | SF | 0.0000 | $ - 0 | |
| A710 | Provide and install Twelve Inch (12" x 12") vinyl floor tile in Room/Corridor (Davis-Bacon Act Wages Apply). | The Contractor shall provide and install new vinyl floor tiles Twelve Inch (12 " x 12 ") in areas other than stairway such as rooms and corridors etc. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Line item includes application of synthetic resin under-coating on floor for smoothing and leveling, and waxing. On- Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 1,250.00 | SF | 0.0000 | $ - 0 | |
| A711 | Provide and install Twelve Inch (12" x 12") vinyl composition floor tile in Room/Corridor (Davis- Bacon Act Wages Apply). | The Contractor shall provide and install new vinyl composition floor tiles Twelve Inch (12" x 12") in areas other than stairway such as rooms and corridors etc. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Line item includes application of synthetic resin under-coating on floor for smoothing and leveling, and waxing. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 1,250.00 | SF | 0.0000 | $ - 0 | |
| A712 | Provide and install Twelve Inch (12" x 12") vinyl floor tile in Stairway (Davis- Bacon Act Wages Apply). | The Contractor shall provide and install new vinyl floor tiles Twelve Inch (12" x 12") in stairway. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Line item includes application of synthetic resin under-coating on floor for smoothing and leveling, and waxing. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 375.00 | SF | 0.0000 | $ - 0 | |
| A713 | Provide and install Twelve Inch (12" x 12") vinyl composition floor tile in Stairway (Davis-Bacon Act Wages Apply). | The Contractor shall provide and install new vinyl composition floor tiles Twelve Inch (12" x 12") in stairway. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Line item includes application of synthetic resin under-coating on floor for smoothing and leveling, and waxing. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 375.00 | SF | 0.0000 | $ - 0 | |
| A714 | Provide and install vinyl floor sheet/resilient flooring in Room/Corridor (Davis-Bacon Act Wages Apply). | The Contractor shall provide and install new vinyl floor sheet/resilient floorings in areas other than stairway such as rooms and corridors etc. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. | |||||
| Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Line item includes application of synthetic resin under-coating on floor for smoothing and leveling, and waxing if necessary. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 2,500.00 | SF | 0.0000 | $ - 0 | |||
| A715 | Provide and install vinyl floor sheet/resilient | ||||||
| flooring in Stairway (Davis- Bacon Act Wages Apply). | The Contractor shall provide and install new vinyl floor sheet/resilient floorings in stairway. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Line item includes application of synthetic resin under-coating on floor for smoothing and leveling, and waxing if necessary. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 625.00 | SF | 0.0000 | $ - 0 | ||
| A716 | Provide and install Twenty Four Inch (24" x 24") tile carpet in Room/Corridor. | The Contractor shall provide and install new tile carpets Twenty Four Inch (24" x 24") in areas other than stairway such as rooms and corridors etc. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Line item includes application of synthetic resin under-coating on floor for smoothing and leveling. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 250.00 | SY | 0.0000 | $ - 0 | |
| A717 | Provide and install Twenty Four Inch (24" x 24") tile carpet in Stairway. | The Contractor shall provide and install new tile carpets Twenty Four Inch (24" x 24") in stairway. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Line item includes application of synthetic resin under-coating on floor for smoothing and leveling. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 125.00 | SY | 0.0000 | $ - 0 | |
| A718 | Provide and install STANDARD GRADE | ||||||
| "HEAVY" roll carpet with urethane carpet cushion installation suitable for carpet. Installation process is "Stretch in" over cushion secured to "Tackless Carpet Stripping" in Room/Corridor. Standard Grade "Heavy" carpet suitable for normal office use. | The Contractor shall provide and install new STANDARD GRADE "HEAVY" roll carpets with cushion with installation process used as "Stretch in" over cushion secured to "Tackless Carpet Stripping" in areas other than stairway such as rooms and corridors etc. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Line item includes application of synthetic resin under- coating on floor for smoothing and leveling. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 1,250.00 | SY | 0.0000 | $ - 0 | ||
| A719 | Provide and install SUPERIOR GRADE | ||||||
| "HEAVY" roll carpet with urethane carpet cushion installation suitable for carpet. Installation process is "Stretch in" over cushion secured to "Tackless Carpet Stripping" in Room/Corridor. Superior Grade "Heavy" carpet suitable for normal office use, but superior presentation. | The Contractor shall provide and install new SUPERIOR GRADE "HEAVY" roll carpets with cushion with installation process used as "Stretch in" over cushion secured to "Tackless Carpet Stripping" in areas other than stairway such as rooms and corridors etc. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Line item includes application of synthetic resin under- coating on floor for smoothing and leveling. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 625.00 | SY | 0.0000 | $ - 0 | ||
| A720 | Provide and install COMMERCIAL GRADE |
"SEVERE" roll carpet with urethane carpet cushion installation suitable for carpet. Installation process is "Stretch in" over cushion secured to "Tackless Carpet Stripping" in Room/Corridor.
| Commercial Grade "Severe" carpet suitable for high traffic offices/areas like clubs or office foyers, corridors. | The Contractor shall provide and install new COMMERCIAL GRADE "SEVERE" roll carpets with cushion with installation process used as "Stretch in" over cushion secured to "Tackless Carpet Stripping" in areas other than stairway such as rooms and corridors etc. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Line item includes application of synthetic resin under-coating on floor for smoothing and leveling. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 625.00 | SY | 0.0000 | $ - 0 |
| A721 | Provide and install PLUSH COMMERCIAL GRADE | ||||
| "HEAVY" roll carpet with urethane carpet cushion installation suitable for carpet. Installation process is "Stretch in" over cushion secured to "Tackless Carpet Stripping" in Room/Corridor. Plush Commercial Grade "Heavy" carpet suitable for Flag/VIP offices like Admiral's or CO's offices. | The Contractor shall provide and install new PLUSH COMMERCIAL GRADE "HEAVY" roll carpets with cushion with installation process used as "Stretch in" over cushion secured to "Tackless Carpet Stripping" in areas other than stairway such as rooms and corridors etc. Line item includes application of synthetic resin under-coating on floor for smoothing and leveling. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 250.00 | SY | 0.0000 | $ - 0 |
| A722 | Provide and install STANDARD GRADE | ||||
| "HEAVY" roll carpet with urethane carpet cushion installation suitable for carpet. Installation process is "Stretch in" over cushion secured to "Tackless Carpet Stripping" in Stairway. Standard Grade "Heavy" carpet suitable for normal office use. | The Contractor shall provide and install new STANDARD GRADE "HEAVY" roll carpets with cushion with installation process used as "Stretch in" over cushion secured to "Tackless Carpet Stripping" in Stairway. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Line item includes application of synthetic resin under-coating on floor for smoothing and leveling. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 1,250.00 | SY | 0.0000 | $ - 0 |
| A723 | Provide and install SUPERIOR GRADE | ||||
| "HEAVY" roll carpet with urethane carpet cushion installation suitable for carpet. Installation process is "Stretch in" over cushion secured to "Tackless Carpet Stripping" in Stairway. Superior Grade "Heavy" carpet suitable for normal office use, but superior presentation. | The Contractor shall provide and install new SUPERIOR GRADE "HEAVY" roll carpets with cushion with installation process used as "Stretch in" over cushion secured to "Tackless Carpet Stripping" in Stairway. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Line item includes application of synthetic resin under-coating on floor for smoothing and leveling. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 625.00 | SY | 0.0000 | $ - 0 |
| A724 | Provide and install COMMERCIAL GRADE | ||||
| "SEVERE" roll carpet with urethane carpet cushion installation suitable for carpet. Installation process is "Stretch in" over cushion secured to "Tackless Carpet Stripping" in Stairway. Commercial Grade "Severe" carpet suitable for high traffic offices/areas like clubs or office foyers, corridors. | The Contractor shall provide and install new COMMERCIAL GRADE "SEVERE" roll carpets with cushion with installation process used as "Stretch in" over cushion secured to "Tackless Carpet Stripping" in Stairway. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Line item includes application of synthetic resin under-coating on floor for smoothing and leveling. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 625.00 | SY | 0.0000 | $ - 0 |
| A725 | Provide and install PLUSH COMMERCIAL GRADE | ||||
| "HEAVY" roll carpet with urethane carpet cushion installation suitable for carpet. Installation process is "Stretch in" over cushion secured to "Tackless Carpet Stripping" in Stairway. Plush Commercial Grade "Heavy" carpet suitable for Flag/VIP offices like Admiral's or CO's offices. | The Contractor shall provide and install new PLUSH COMMERCIAL GRADE "HEAVY" roll carpets with cushion with installation process used as "Stretch in" over cushion secured to "Tackless Carpet Stripping" in Stairway. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Line item includes application of synthetic resin under-coating on floor for smoothing and leveling. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 125.00 | SY | 0.0000 | $ - 0 |
| A726 | Provide and install STANDARD GRADE | ||||
| "HEAVY" roll carpets with "Glue-down" method in Rooms/Corridors. Standard Grade "Heavy" carpet suitable for normal office use. | The Contractor shall provide and install new STANDARD GRADE "HEAVY" roll carpets with installation process used as "Glue- down" method in areas other than stairway such as rooms and corridors etc. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Line item includes application of synthetic resin under-coating on floor for smoothing and leveling. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 625.00 | SY | 0.0000 | $ - 0 |
| A727 | Provide and install SUPERIOR GRADE | ||||
| "HEAVY" roll carpets with "Glue-down" method in Rooms/Corridors. Superior Grade "Heavy" carpet suitable for normal office use, but superior presentation. | The Contractor shall provide and install new SUPERIOR GRADE "HEAVY" roll carpets with installation process used as "Glue- down" method in areas other than stairway such as rooms and corridors etc. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Line item includes application of synthetic resin under-coating on floor for smoothing and leveling. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 625.00 | SY | 0.0000 | $ - 0 |
| A728 | Provide and install COMMERCIAL GRADE |
"SEVERE" roll carpets with "Glue-down" method in Rooms/Corridors.
| Commercial Grade "Severe" carpet suitable for high traffic offices/areas like clubs or office foyers, corridors. | The Contractor shall provide and install new COMMERCIAL GRADE "SEVERE" roll carpets with installation process used as "Glue-down" method in areas other than stairway such as rooms and corridors etc. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Line item includes application of synthetic resin under-coating on floor for smoothing and leveling. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 375.00 | SY | 0.0000 | $ - 0 | ||
| A729 | Provide and install PLUSH COMMERCIAL GRADE | ||||||
| "HEAVY" roll carpets with "Glue-down" method in Rooms/Corridors. Plush Commercial Grade "Heavy" carpet suitable for Flag/VIP offices like Admiral's or CO's offices. | The Contractor shall provide and install new PLUSH COMMERCIAL GRADE "HEAVY" roll carpets with installation process used as "Glue-down" method in areas other than stairway such as rooms and corridors etc. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Line item includes application of synthetic resin under-coating on floor for smoothing and leveling. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 125.00 | SY | 0.0000 | $ - 0 | ||
| A730 | Provide and install EXTERIOR GRADE | ||||||
| "HEAVY" roll carpets with "Glue-down" method in Rooms/Corridors. Exterior Grade "Heavy" carpet suitable for all outside applications. | The Contractor shall provide and install new EXTERIOR GRADE "HEAVY" roll carpets with installation process used as "Glue- down" method in areas other than stairway such as rooms and corridors etc. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Line item includes application of synthetic resin under-coating on floor for smoothing and leveling. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 375.00 | SY | 0.0000 | $ - 0 | ||
| A731 | Provide and install STANDARD GRADE | ||||||
| "HEAVY" roll carpets with "Glue-down" method in Stairway. Standard Grade "Heavy" carpet suitable for normal office use. | The Contractor shall provide and install new STANDARD GRADE "HEAVY" roll carpets with installation process used as "Glue- down" method in Stairway. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Line item includes application of synthetic resin under-coating on floor for smoothing and leveling. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 125.00 | SY | 0.0000 | $ - 0 | ||
| A732 | Provide and install SUPERIOR GRADE | ||||||
| "HEAVY" roll carpets with "Glue-down" method in Stairway. Superior Grade "Heavy" carpet suitable for normal office use, but superior presentation. | The Contractor shall provide and install new SUPERIOR GRADE "HEAVY" roll carpets with installation process used as "Glue- down" method in Stairway. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Line item includes application of synthetic resin under-coating on floor for smoothing and leveling. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 125.00 | SY | 0.0000 | $ - 0 | ||
| A733 | Provide and install COMMERCIAL GRADE | ||||||
| "SEVERE" roll carpets with "Glue-down" method in Stairway. Commercial Grade "Severe" carpet suitable for high traffic offices/areas like clubs or office foyers, corridors. | The Contractor shall provide and install new COMMERCIAL GRADE "SEVERE" roll carpets with installation process used as "Glue-down" method in Stairway. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Line item includes application of synthetic resin under-coating on floor for smoothing and leveling. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 125.00 | SY | 0.0000 | $ - 0 | ||
| A734 | Provide and install PLUSH COMMERCIAL GRADE | ||||||
| "HEAVY" roll carpets with "Glue-down" method in Stairway. Plush Commercial Grade "Heavy" carpet suitable for Flag/VIP offices like Admiral's or CO's offices. | The Contractor shall provide and install new PLUSH COMMERCIAL GRADE "HEAVY" roll carpets with installation process used as "Glue-down" method in Stairway. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Line item includes application of synthetic resin under- coating on floor for smoothing and leveling. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 125.00 | SY | 0.0000 | $ - 0 | ||
| A735 | Provide and install EXTERIOR GRADE | ||||||
| "HEAVY" roll carpets with "Glue-down" method in Stairway. Exterior Grade "Heavy" carpet suitable for all outside applications. | The Contractor shall provide and install new EXTERIOR GRADE "HEAVY" roll carpets with installation process used as "Glue- down" method in Stairway. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Line item includes application of synthetic resin under-coating on floor for smoothing and leveling. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 125.00 | SY | 0.0000 | $ - 0 | ||
| A736 | Provide and install wooden baseboard in Room/Corridors. | The Contractor shall provide and install new wooden baseboards in areas other than stairway such as rooms and corridors etc. Normal surface preparation. Clean and scrape surface of foreign materials prior to installation. Line item includes preparation and painting of new wooden baseboards. Color and gloss of painting will be designated by customer. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 625.00 | LF | 0.0000 | $ - 0 | |
| A737 | Provide and install wooden baseboard in Stairway. | The Contractor shall provide and install new wooden baseboards in stairway. Normal surface preparation. Clean and scrape surface of foreign materials prior to installation. Line item includes preparation and painting of new wooden baseboards. Color and gloss of painting will be designated by customer. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 125.00 | LF | 0.0000 | $ - 0 | |
| A738 | Provide and install Four Inch (4") vinyl baseboard in Room/Corridor. | The Contractor shall provide and install new Four Inch (4") vinyl baseboards in areas other than stairway such as rooms and corridors etc. Normal surface preparation. Clean and scrape surface of foreign materials prior to installation. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 625.00 | LF | 0.0000 | $ - 0 | |
| A739 | Provide and install Six Inch (6") vinyl baseboard in Room/Corridor. | The Contractor shall provide and install new Six Inch (6") vinyl baseboards in areas other than stairway such as rooms and corridors etc. Normal surface preparation. Clean and scrape surface of foreign materials prior to installation. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 625.00 | LF | 0.0000 | $ - 0 | |
| A740 | Provide and install Four Inch (4") vinyl baseboard in Stairway. | The Contractor shall and install provide new Four Inch (4") vinyl baseboards in stairway. Normal surface preparation. Clean and scrape surface of foreign materials prior to installation. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 250.00 | LF | 0.0000 | $ - 0 | |
| A741 | Provide and install Six Inch (6") vinyl baseboard in Stairway. | The Contractor shall and install provide new Six Inch (6") vinyl baseboards in stairway. Normal surface preparation. Clean and scrape surface of foreign materials prior to installation. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 250.00 | LF | 0.0000 | $ - 0 | |
| A742 | Install GFM tile carpet in Room/Corridor. | The Contractor shall install tile carpet furnished by the Government, in areas other than stairway such as rooms and corridors etc. | |||||
| Adhesive and other materials necessary to complete GFM carpet installation, are furnished by the Contractor. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 125.00 | SY | 0.0000 | $ - 0 | |||
| A743 | Install GFM tile carpet in Stairway. | The Contractor shall install tile carpet furnished by the Government, in stairway. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Adhesive and other materials necessary to complete GFM carpet installation, are furnished by the Contractor. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 125.00 | SY | 0.0000 | $ - 0 | |
| A744 | Install GFM roll carpet and Contractor provided cushion. Installation process is "Stretch in" over cushion secured to "Tackless Carpet Stripping" in Room/Corridor. | The Contractor shall install roll carpet furnished by the Government, in areas other than stairway such as rooms and corridors etc. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Underlayer cushion, adhesive and other materials necessary to complete GFM carpet installation, are furnished by the Contractor. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 125.00 | SY | 0.0000 | $ - 0 | |
| A745 | Install GFM roll carpet and Contractor provided cushion. Installation process is "Stretch in" over cushion secured to "Tackless Carpet Stripping" in Stairway. | The Contractor shall install roll carpet furnished by the Government, in Stairway. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Underlayer cushion, adhesive and other materials necessary to complete GFM carpet installation, are furnished by the Contractor. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 125.00 | SY | 0.0000 | $ - 0 | |
| A746 | Install GFM roll carpet, "Glue-down" installation method in Room/Corridor. | The Contractor shall install roll carpet furnished by the Government, with installation process used as "Glue-down" method in areas other than stairway such as rooms and corridors etc. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Adhesive and other materials necessary to complete GFM carpet installation, are furnished by the Contractor. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 125.00 | SY | 0.0000 | $ - 0 | |
| A747 | Install GFM roll carpet, "Glue-down" installation method in Stairway. | The Contractor shall install roll carpet furnished by the Government, with installation process used as "Glue-down" method in Stairway. Normal concrete/floor surface preparation. Clean and scrape floor surface of foreign materials prior to installation. Floor is prepared for installation with minimal concrete surface filling of chips and leveling. Adhesive and other materials necessary to complete GFM carpet installation, are furnished by the Contractor. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to complete the work. | 125.00 | SY | 0.0000 | $ - 0 | |
| A748 | Remove existing metal strip. | The Contractor shall remove existing metal strip at edge of floor covering. Line item includes disposal of all debris and clean-up. On- Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and equipment to | |||||
| complete the work. | 625.00 | LF | 0.0000 | $ - 0 | |||
| A749 | Provide and install metal strip. | The Contractor shall provide and install new metal strip at edge of floor covering. On-Site work shall commence as soon as practical and be completed within 30 days after receiving the request for service. The Contractor shall be responsible to schedule the service with the customer or building tenant. The unit prices shall include all labor, material, parts, travel time, mobilization, supervision and | |||||
| equipment to complete the work. | 1,250.00 | LF | 0.0000 | $ - 0 |