This federal contract opportunity notice solicits proposals for an 8(a) Design-Build/Design-Bid-Build Multiple Award Construction Contract to provide construction services at various locations throughout the state of Hawaii. Services include new construction, repair, alteration, and related demolition of existing infrastructure such as residential and nonresidential buildings, utilities, airfields, and roadways. The contract has a one-year base period plus four option periods not to exceed 60 months total, with a maximum value of $245 million. Task orders will range from $150,000 to $10 million. The solicitation is set aside for 8(a) firms in Hawaii serviced by the SBA Hawaii District Office or with a bona fide Hawaii business. Proposals are due by a specified date. Evaluation will consider technical approach, past performance, and price to award at least two IDIQ contracts. The Navy, Marine Corps, Air Force, and other federal agencies will issue task orders under this contract.
Seed Project - Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amd_3.pdf | ||
| Amd_2.pdf | ||
| Amd1.pdf | ||
| Notice_No._2.pdf | ||
| Seed_Project_-_FFD_HQ_B284_FULL_SIZE.pdf | ||
| Seed_Project_-_FFD_B284_Geotech_Report.pdf | ||
| Notice_No._1.pdf | ||
| N62478-19-R-4038_RFP.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
6/27/17
Clyde Higa
James Enoka
REPAVE PARKING LOT, FFD HQ, B284, JBPHH, OAHU, HAWAII 1379330
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 LIST OF DRAWINGS
00 41 00 BID SCHEDULES
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 20 00.00 20 PRICE AND PAYMENT PROCEDURES
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 17.00 20 COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS)
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 45 00.00 20 NAVFAC QUALITY CONTROL
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 PROJECT IDENTIFICATION
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMITTALS
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
02 84 16 HANDLING OF LIGHTING BALLASTS AND LAMPS CONTAINING PCBs
AND MERCURY
DIVISION 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 25 - INTEGRATED AUTOMATION
25 50 00.00 20 CYBERSECURITY OF FACILITY-RELATED CONTROL SYSTEMS
DIVISION 26 - ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 56 00 EXTERIOR LIGHTING
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 05 19 GEOTEXTILE
31 11 00 CLEARING AND GRUBBING
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID
PAVEMENTS
32 12 10 BITUMINOUS TACK AND PRIME COATS
32 12 17 HOT MIX BITUMINOUS PAVEMENT
32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE
FACILITIES
32 16 13 CONCRETE SIDEWALKS AND CURBS AND GUTTERS
32 17 23 PAVEMENT MARKINGS
PROJECT TABLE OF CONTENTS Page 1
DIVISION 33 - UTILITIES
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 2
DOCUMENT 00 01 15
LIST OF DRAWINGS
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
DWG. NAVFAC
NO. DWG. NO. TITLE
G-001 19066099 TITLE SHEET, LOCATION AND VICINITY MAPS AND INDEX OF
DRAWINGS
G-002 19066100 NOTES, ABBREVIATIONS AND LEGEND
C-101 19066101 EXISTING CONDITION AND DEMOLITION PLAN
C-102 19066102 SITE PLAN
C-103 19066103 SITE GRADING PLAN
C-104 19066104 CONCRETE PAVEMENT JOINTING PLAN
C-105 19066105 SITE STRIPING AND SIGNAGE PLAN
C-106 19066106 BORING LOGS AND GEOTECHNICAL NOTES
C-107 19066107 BORING LOGS
C-501 19066108 SIDEWALK CULVERT DETAILS
C-502 19066109 GRADING SECTIONS A AND B
C-503 19066110 GRADING SECTIONS C AND D
C-504 19066111 CONCRETE JOINT DETAILS
C-505 19066112 HANDICAP PARKING DETAILS
C-506 19066113 CIVIL DETAILS
C-507 19066114 MISCELLANEOUS DETAILS
C-508 19066115 CURB RAMP DETAILS
E-001 19066116 ELECTRICAL SYMBOLS AND GENERAL ELECTRICAL NOTES
E-002 19066117 DUCT SECTION DETAILS
E-200 19066118 DEMOLITION SITE ELECTRICAL PLAN
E-201 19066119 SITE POWER AND SIGNAL PLAN
E-202 19066120 SITE LIGHTING PLAN
E-300 19066121 LIGHT POLE DETAILS
E-301 19066122 ACCESS CONTROL DIAGRAM
E-302 19066123 MISCELLANEOUS DETAILS
-- End of Document --
DOCUMENT 00 01 15 Page 1
SECTION 00 41 00
BID SCHEDULES
PART 1 GENERAL
1.1 BASIS OF BIDS
1.1.1 Bid Item
This contract is solicited with bid item. A description of the bid items is contained in Standard Form SF 1442, "Solicitation, Offer and Award."
DOCUMENT 00 41 00 Page 1
Bid Items Form
N_____-__-B-____
(i) Basis of Bid for Item 0001 shall be the entire work complete in accordance with the drawings and specifications.
Bid Item 0001 $______
-- End of Document --
DOCUMENT 00 41 00 Page 2
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
The scope of work includes the reconstruction of deteriorated asphalt concrete pavement at the Building 284 parking lot. The south half of the parking lot shall be reconstructed with asphalt concrete pavement and the north half shall be reconstructed with concrete pavement. Fire truck training is often held in the area proposed for the concrete pavement. The northwest section of the parking lot shall be reconstructed with asphalt concrete pavement to support loading operations at the building. Pavement reconstruction work will also include construction of islands, pavement markings, signage, loop detector, rock filter drain, yard grading, and other incidental work.
The existing sidewalk along the east side of the building shall be demolished and replaced. A new sidewalk shall also be constructed along the north side of the building. Two other short segments of sidewalk shall be constructed along the handicapped parking area and to the side entrance to the south side of the building. Incidental sidewalk work shall include but not be limited to construction of sidewalk culvert, curbs, curb ramps, and root barriers.
The existing intercom box for the motor-controlled rolling gate at the driveway entrance is non-functional. A new intercom, remote control system, and motor shall be installed and the existing intercom and punch code system shall be demolished and removed. New data and communication lines from the intercom at the gate to the operations room in Building 284 shall be provided. New receptacles and control panels shall be installed in the operations room for the intercom and remote control system. The gate shall be capable of being operated remotely by a guard stationed in the operations room.
New energy efficient lighting shall be located at the north and east sides of the building along the fenceline and in the east parking lot.
1.1.2 Location
The work is located at Building 284, Federal Fire Department, adjacent to Center Drive, JBPHH, Oahu, Hawaii, approximately as indicated. The exact location will be shown by the Contracting Officer.
1.2 OCCUPANCY OF PREMISES
Building(s) will be occupied during performance of work under this Contract.
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
SECTION 01 11 00 Page 1
1.3 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation by following the procedures identified in Joint Base Pearl Harbor-Hickam Instruction JBPHHINST 11013. Allow a minimum of 20 working days to obtain the required Government signatures specified by JBPHHINST 11013. The Contractor is responsible for obtaining all Government signatures and consulting with the Hawaii One Call Center (HOCC). After signatures have been obtained, submit the digging permit to the Contracting Officer for JBPHH notifications to be issued via the APWO. Excavation work may start 14 working days after submitting the digging permit to the Contracting Officer with all the required Government signatures.
Comply with Installation requirements for locating and marking underground utilities. Scan the construction site with electromagnetic or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities or utilities encased in pier structures are discovered. Verify the elevations of existing piping, utilities, and any type of underground or encased obstruction not indicated to be specified or removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed.
Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground, pier deck or paved surface where existing underground utilities or utilities encased in pier structures are discovered. Verify the elevations of existing piping, utilities, and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.3.1 Notification Prior to Excavation
Notify the Contracting Officer at least 15 days prior to starting excavation work.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 2
SECTION 01 14 00
WORK RESTRICTIONS
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel; G
Personnel List; G
Vehicle List; G
Construction Phasing Plan; G
Statement of Acknowledgement Form SF 1413; G
1.2 SPECIAL SCHEDULING REQUIREMENTS
The Contractor shall meet with the Contracting Officer and Federal Fire Department and develop drawings showing the construction phasing and schedule for phasing. These construction phasing plan shall be submitted for review and comment as part of the required design submittals specified in Section 01 33 00 SUBMITTAL PROCEDURES. The construction phasing plan shall show the sequence of work and show how access will be provided for personnel at Building 284 during various phases of construction. The Contractor shall keep at least one entry gate with a route to the front of Building 284 open during construction and allow access to the front of the building for a semi-trailer truck making deliveries two to three times a week. In addition, a safe pedestrian path must be maintained from a designated grassed parking area outside of the parking lot to Building 284 for those temporarily parked in that area. The construction phasing plan shall be approved by the Contracting Officer prior to start of construction.
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
The Contractor shall notify the Contracting Officer at least 21 calendar days prior to start of construction in the area of the existing storage containers. The Contractor shall provide an accessible route and work area during this time period to allow the Government to move the storage containers off site.
1.3.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such
SECTION 01 14 00 Page 1 entry. Mark Contractor equipment for identification.
1.3.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.3.1.2 Identification Badges and Installation Access
Application for and use of badges will be as directed. Obtain access to the installation by participating in the Navy Commercial Access Control System (NCACS), or by obtaining passes each day from the Base Pass and Identification Office. Costs for obtaining passes through the NCACS are the responsibility of the Contractor. One-day passes, issued through the Base Pass and Identification Office, will be furnished without charge.
Furnish a completed EMPLOYMENT ELIGIBILITY VERIFICATION (DHS FORM I-9) form for all personnel requesting badges. This form is available at http://www.uscis.gov/portal/site/uscis by searching or selecting Employment Verification (Form I-9). Immediately report instances of lost or stolen badges to the Contracting Officer.
a. NCACS Program: NCACS is a voluntary program in which Contractor personnel who enroll, and are approved, are subsequently granted access to the installation for a period up to one year, or the length of the contract, whichever is less, and are not required to obtain a new pass from the Base Pass and Identification Office for each visit. The Government performs background screening and credentialing. Throughout the year the Contractor employee must continue to meet background screening standards. Periodic background screenings are conducted to verify continued NCACS participation and installation access privileges. Under the NCACS program, no commercial vehicle inspection is required, other than for Random Anti-Terrorism Measures (RAM) or in the case of an elevation of Force Protection Conditions (FPCON).
Information on costs and requirements to participate and enroll in NCACS is available at http://www.rapidgate.com or by calling 1-877-727-4342.
1.3.2 Working Hours
Regular working hours must consist of an 8 1/2 hour period, between 7 a.m.
and 3:30 p.m., Monday through Friday, excluding Government holidays.
1.3.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.
1.3.4 Utility Cutovers and Interruptions
a. No sewage and water outages will be allowed. Make other utility cutovers and interruptions after normal working hours or on Saturdays, SECTION 01 14 00 Page 2
Sundays, and Government holidays. Interruptions are limited to 4 hours, unless the outage duration occurs after normal working hours and is approved by the facility manager and the Contracting Officer.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, and fueling are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS. Such interruptions are further limited by the Contracting Officer and acctivity. This time limit includes time for deactivation and reactivation.
d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.
e. Services for utility interruptions shall be paid by the Contractor via minor work request.
1.3.5 Roads
Permission to interrupt any activity roads shall be requested in writing a minimum of 60 calendar days to less, if approved by the Contracting Officer, prior to the desired date of interruption. Interruptions of activity roads shall be allowed only when they will not cause interference with the operations of the activity.
1.3.6 Traffic Control
Direct traffic away from the work area a minimum of 10 feet and as necessary to ensure safety. The Contractor shall furnish and install barricades, signs, caution tape/rope, and light blinkers as necessary to control traffic in accordance with the Manual of Uniform Traffic Control Devices (MUTCD) and to the satisfaction of the Contracting Officer. The Contractor shall submit a traffic control plan with the work schedule to the Contracting Officer for approval prior to starting work to coordinate operations on or affecting roadways and parking areas.
1.3.7 Trucking
Loading all trucks leaving the site with loose debris in a manner that shall prevent dropping of materials on streets. Fasten suitable tarpaulins over the load before they enter surrounding streets.
1.3.8 Construction Site Maintenance
The Contractor shall store all supplies and equipment on project site so as to preclude mechanical and climatic damage. Maintain site in a neat and orderly manner.
1.3.9 Equipment on Site
Cover equipment that is to remain in place within the area of contract operations and protect it against damage or loss. Store equipment that is
SECTION 01 14 00 Page 3 removed in performance of work where directed or reuse in work as required by drawings and specifications. Equipment temporarily removed shall be protected, cleaned and replaced equal to its condition prior to starting work. Security for equipment or material that is to be reused and is removed for temporary storage shall be the sole responsibility of the Contractor.
1.3.10 Noise Control
The Contractor shall comply with all applicable Federal, State and Local laws, ordinances, and regulations relative to noise control.
1.3.11 Toilet Facilities
Contractor's personnel are not permitted to use toilet facilities on the premises. The Contractor shall provide temporary portable toilet facilities and dispose of stored waste off site in accordance with local, State and Federal regulations.
1.4 SECURITY REQUIREMENTS
1.4.1 Personnel List
Submit for approval, at least 15 days prior to the desired date of entry, an original alphabetical list of personnel who require entry into Government property to perform work on the project. Furnish for each person:
a. Name
b. Date and place of birth
c. Citizenship
d. Home address
e. Social security number
f. Current pass expiration date
g. Naturalization or Alien Registration number
h. Passport number, place of issue, and expiration date
The request for personnel passes must be accompanied with the following certification:
"I hereby certify that all personnel on this list are either born U.S.
citizens, naturalized U.S. citizens with the naturalization number shown, or legal aliens with the alien registration number indicated."
Signature/Firm Name
1.4.1.1 Citizenship Requirements
Clearance for aliens may require approximately 20 work days for approval.
SECTION 01 14 00 Page 4
1.4.1.2 Documents Acceptable for Proof of Citizenship
a. Birth registration card
b. Certificate of live birth, birth certificate
c. Certificate of Naturalization
d. Certificate of registration
e. DD-214 (Must Cite Birthplace)
f. DD Form 4 (Contract for Enlistment and Must Cite Birthplace)
g. DD 1966 (Application for Enlistment)
h. Military discharge papers (must cite birthplace)
i. Delayed birth certificate
j. Hawaii certificate of foreign birth
k. Hospital birth certificate
l. Marriage license certificate
m. Merchant marine certificate
n. Military officer ID card
o. Notification of birth registration
p. State of Hawaii ID card
q. USA passport
r. Verbal inquiry with State of Hawaii Vital Statistics Office
1.4.2 Vehicle List
Submit an original list of vehicles to be utilized at the work site with the following information for each vehicle:
a. Make
b. Year
c. Model
d. License number
e. Registered owner
f. Current NAVBASE Pearl Harbor pass expiration date.
1.4.3 Passes
Submit request for personnel and vehicle passes together. Include the Certificate of Insurance for Contractor and Subcontractor(s) and the
SECTION 01 14 00 Page 5
Statement of Acknowledgement Form SF 1413 with the submittal. Passes will normally be issued within 21 days.
1.4.3.1 Control
Maintain strict accountability over passes. Immediately report to the source of issue, passes missing or lost and the circumstances. If the Contractor has another active contract or one commencing immediately, employees' names may be transferred from one contract to the other. Final payment will not be effected until employees are transferred to another contract or the records are cleared. Furnish a signed letter, countersigned by the source of issue, stating that passes have been turned in.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 14 00 Page 6
SECTION 01 20 00.00 20
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP-1110-1-8 (2009) Construction Equipment Ownership and Operating Expense Schedule
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Earned Value Report; G
1.3 EARNED VALUE REPORT
1.3.1 Data Required
This contract requires the use of a cost-loaded Network Analysis Schedule (NAS). The information required for the Earned Value Report will be entered as an integral part of the Network Analysis Schedule. Within 45 calendar days of contract award, prepare and deliver to the Contracting Officer an Earned Value Report (construction contract) as directed by the Contracting Officer. Provide a detailed breakdown of the contract price, giving quantities for each of the various kinds of work, unit prices, and extended prices. Costs shall be summarized and totals provided for each construction category.
1.3.2 Schedule Instructions
Payments will not be made until the Earned Value Report from the cost-loaded NAS has been submitted to and accepted by the Contracting Officer. Identify the cost for site work, and include incidental work.
1.4 CONTRACT MODIFICATIONS
In conjunction with the Contract Clause "DFARS 252.236-7000, Modification Proposals-Price Breakdown," and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, equipment use rates shall be based upon the applicable provisions of the EP-1110-1-8.
SECTION 01 20 00.00 20 Page 1
1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.5.1 Content of Invoice
Requests for payment will be processed in accordance with the Contract Clause FAR 52.232-27, Prompt Payment Construction Contracts and FAR 52.232-5, Payments Under Fixed-Price Construction Contracts. The requests for payment shall include the documents listed below.
a. The Contractor's invoice, on NAVFAC Form 7300/30 furnished by the Government, showing in summary form, the basis for arriving at the amount of the invoice. Form 7300/30 shall include certification by Contractor and Quality Control (QC) Manager.
b. The Earned Value Report from the cost-loaded NAS, showing in detail:
the estimated cost, percentage of completion, and value of completed performance.
c. Updated Project Schedule and reports required by the contract.
d. Contractor Safety Self Evaluation Checklist.
e. Other supporting documents as requested.
f. Updated copy of submittal register.
g. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies.
h. Monthly Work-hour report.
i. Solid Waste Disposal Report.
1.5.2 Submission of Invoices
If DFARS Clause 5252.232-7006 is included in the contract, provide the documents listed in paragraph CONTENT OF INVOICE in their entirety as attachments in Wide Area Work Flow (WAWF) for each invoice submitted. The maximum size of each WAWF attachment is two megabytes, but there are no limits on the number of attachments. If a document cannot be attached in WAWF due to system or size restriction, provide it as instructed by the Contracting Officer.
1.5.3 Final Invoice
a. A final invoice shall be accompanied by the certification required by DFARS 252.247.7023 TRANSPORTATION OF SUPPLIES BY SEA, and the Contractor's Final Release. If the Contractor is incorporated, the Final Release shall contain the corporate seal. An officer of the corporation shall sign and the corporate secretary shall certify the Final Release.
b. For final invoices being submitted via WAWF, the original Contractor's Final Release Form and required certification of Transportation of Supplies by Sea must be provided directly to the respective Contracting Officer prior to submission of the final invoice. Once receipt of the original Final Release Form and required certification of Transportation of Supplies by Sea has been confirmed by the Contracting Officer, the Contractor shall then submit final invoice and attach a
SECTION 01 20 00.00 20 Page 2 copy of the Final Release Form and required certification of Transportation of Supplies by Sea in WAWF.
c. Final invoices not accompanied by the Contractor's Final Release and required certification of Transportation of Supplies by Sea will be considered incomplete and will be returned to the Contractor.
1.6 PAYMENTS TO THE CONTRACTOR
Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.
1.6.1 Obligation of Government Payments
The obligation of the Government to make payments required under the provisions of this contract will, at the discretion of the Contracting Officer, be subject to reductions and suspensions permitted under the FAR and agency regulations including the following in accordance with FAR 32.503-6:
a. Reasonable deductions due to defects in material or workmanship;
b. Claims which the Government may have against the Contractor under or in connection with this contract;
c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and
d. Failure to provide up to date record drawings not current as stated in Contract Clause "FAC 5252.236-9310, Record Drawings."
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 20 00.00 20 Page 3
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
View Location Map; G
Progress and Completion Pictures; G
1.3 VIEW LOCATION MAP
Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.
1.4 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten views from points located by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures. Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file. Include a date designator in file names. Cross reference submittals in the appropriate daily report. Photographs provided are for unrestricted use by the Government.
1.5 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 LIABILITY, SECTION 01 30 00 Page 1 during the entire period of performance under this contract. Provide other insurance coverage as required by State of Hawaii law.
Above insurance coverage are to extend to Contactor personnel operating Government owned equipment and vehicles.
The Certificate of Insurance shall provide for 30 calendar days written notice to the Contracting Officer by the insurance company to canceling or material change in policy coverage. Other requirements and information are contained in the aforementioned "INSURANCE" clause.
1.6 SUPERVISION
1.6.1 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.
1.6.2 Superintendent Qualifications
The project superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
1.6.2.1 Duties
The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.
The superintendent is required to attend NAVFAC Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.6.3 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.7 PRECONSTRUCTION MEETING
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and
SECTION 01 30 00 Page 2 safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work must also attend.
1.8 FACILITY TURNOVER PLANNING MEETINGS (NAVFAC Red Zone - NRZ)
Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start the turnover process at the Pre-Construction Conference meeting with a discussion of the NAVFAC Red Zone (NRZ) process and convene at regularly scheduled NRZ Meetings. Include the following in the facility Turnover effort:
1.8.1 NRZ Checklist
a. Contracting Officer's Technical Representative (COTR) will provide the Contractor a copy of the NRZ Checklist template prior to 75 percent completion.
b. Prior to 75 percent completion add/delete critical activities to the NRZ Checklist template as necessary to match the project scope, and schedule critical activities and insert planned completion dates in the NRZ checklist for each critical activity. Present the NRZ Checklist to COTR and review during a regularly scheduled QC Meeting.
1.8.2 Meetings
a. Upon Government acceptance of the NRZ Checklist, the Project Superintendent is required to lead regular NRZ Meetings beginning at approximately 75 percent project completion, or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first.
b. The Contracting Officer will determine the frequency of the meetings, which is expected to increase as the project completion draws nearer.
c. Using the NRZ Checklist as a Plan of Action and Milestones (POAM) and basis for discussion, review upcoming critical activities and strategies to ensure work is completed on time.
d. Coordinate with the COTR any upcoming activities that require Government involvement.
e. Maintain the NRZ Checklist by documenting the actual completion dates as work is completed and update the NRZ Checklist with revised planned completion dates as necessary to match progress. Distribute copies of the current NRZ Checklist to attendees at each NRZ Meeting.
1.9 PARTNERING
To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, the Contractor and their Subcontractors. Key personnel from the Supported Command, the End User (who will occupy the facility), the Government Design and Construction team and Subject Matter Experts, the Installation, the Contractor and Subcontractors, and the Designer of Record will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in
SECTION 01 30 00 Page 3 an effort to achieve a project that is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.
The Contracting Officer will provide Information on the Partnering Process and a list of key and optional personnel who should attend the Partnering meeting.
1.9.1 Informal Partnering
The Contracting Officer will organize the Partnering Sessions with key personnel of the project team, including Contractor personnel and Government personnel.
The Initial Partnering session should be a part of the Pre-Construction Meeting. Partnering sessions will be held at a location agreed to by the Contracting Officer and the Contractor (typically a conference room provided by the PWD FEAD/ROICC Resident Engineer office or the Contractor). The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by the Contracting Officer. The Partners will determine the frequency of the follow-on sessions, at no more than 3 to six month intervals.
1.10 ELECTRONIC MAIL (E-MAIL) ADDRESS
Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 days after contract award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats.
Multiple email addresses are not allowed.
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this email address.
1.10.1 Cybersecurity of Control Systems
Discuss Cybersecurity of building control system requirements and submittals as required for Section 25 50 00.00 20 CYBERSECURITY FOR
FACILITY-RELATED CONTROL SYSTEMS.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 30 00 Page 4
SECTION 01 32 17.00 20
COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS)
PART 1 GENERAL
1.1 DESCRIPTION
The Contractor is responsible for scheduling procurement, Contractor quality control and construction, acceptance testing and training. Refer to Specification Section 01 33 00 SUBMITTAL PROCEDURES to determine if any items require Government approval prior to construction; if any are required, include that submittal review time in the schedule.
The schedule is a tool to manage the project, both for Contractor and Government activities. It will also be used to report progress and evaluate time extensions. The Project NAS must be cost-loaded and will provide the basis for progress payments. Use the Critical Path Method (CPM) and the Precedence Diagram Method (PDM) to satisfy time and cost applications. For consistency, when scheduling software terminology is used in this specification, the terms in Primavera's scheduling programs are used.
1.2 SUBMITTALS
The use of a "G" following a submittal indicates that a Government approval action is required. Submit the following in accordance with Section
01 33 00 SUBMITTAL PROCEDURES.
SD-01 Preconstruction Submittals
Qualifications; G
Baseline Network Analysis Schedule (NAS); G
Submit a Baseline NAS within 45 calendar days of contract award.
SD-07 Certificates
Monthly Network Analysis Schedule Update; G
SD-11 Closeout Submittals
As-Built Schedule; G
1.3 SCHEDULE ACCEPTANCE PRIOR TO START OF WORK
Submit the Baseline Network Analysis Schedule (NAS) within 45 calendar days of contract award. Participate with the Contracting Officer in a preliminary meeting(s) to discuss the proposed schedule and requirements of this section prior to the Contractor preparing the Project Baseline Schedule. Government review comments on the Contractor's schedule(s) do not relieve the Contractor from compliance with requirements of the Contract Documents. Only bonds may be paid prior to acceptance of the Baseline Network Analysis Schedule (NAS) The acceptance of a Baseline NAS is a condition precedent to:
SECTION 01 32 17.00 20 Page 1
a. The Contractor starting work on the demolition or construction stage(s) of the contract.
b. Processing Contractor's invoices(s) for construction activities/items of work.
c. Review of any schedule updates.
Submittal of the Baseline Network Analysis Schedule, and subsequent schedule updates, is understood to be the Contractor's certification that the submitted schedule meets all of the requirements of the Contract Documents, represents the Contractor's plan on how the work will be accomplished, and accurately reflects the work that has been accomplished and how it was sequenced (as-built logic).
1.4 SOFTWARE
Prepare and maintain project schedules using Primavera P6. Importing data into P6 using data conversion techniques or third party software is cause for rejection of the submitted schedule. All Schedule submissions shall include the native P6 file exported to Version 8.2, or the government's most currently acceptable version."
A listing of Primavera P6 settings and parameters which must be used in preparing the Schedules are contained later in this specification section.
Deviation from these settings and parameters, without prior consent of the Contracting Officer, is cause for rejection of schedule submission.
1.5 QUALIFICATIONS
The designated Scheduler for the project must have prepared and maintained at least 3 previous schedules of similar size and complexity of this contract using Primavera P3, Primavera SureTrak, or Primavera P6. At least one of the three must be in Primavera P6. Submit a resume outlining the qualifications of the Scheduler. Payment will not be processed until an acceptable Scheduler is provided.
1.6 NETWORK SYSTEM FORMAT
The system must include time-scaled logic diagrams and specified reports.
1.6.1 Diagrams
Provide Time-scaled Logic Diagram printed in color on ANSI D size sheets.
The diagram must clearly show activities on the critical path. Include the following information for each activity:
a. Activity ID
b. Activity Description
c. Original Duration in Work Days
d. Remaining duration in Work Days
e. Physical Percent Complete
f. Start Date
SECTION 01 32 17.00 20 Page 2
g. Finish Date
h. Total Float
1.6.2 Schedule Activity Properties and Level of Detail
The NAS must identify all Government, Construction Quality Management (CQM), Construction activities planned for the project and all other activities that could impact project completion if delayed. Create separate activities for each Phase, Area, Floor Level and Location the activity is occurring. Activity categories included in the schedule are specified below.
With the exception of the Contract Award and Contract Completion Date (CCD) milestone activities, no activity shall be open-ended; each activity must have predecessor and successor ties. No activity must have open start or open finish (dangling) logic. Minimize redundant logic ties. Once an activity exists on the schedule it must not be deleted or renamed to change the scope of the activity and must not be removed from the schedule logic without approval from the Contracting Officer. While an activity cannot be deleted, where said activity is no longer applicable to the schedule but must remain within the logic stream for historical record, it can be changed to a milestone. Document any such change in the milestone's "Notebook", including a date and explanation for the change. The ID number for a deleted activity must not be re-used for another activity. Within the Baseline Schedule no more than 20 percent of the activities shall be critical or near critical. Critical is defined as having zero days of Total Float. "Near Critical" is defined as having Total Float of 1 to 14 days. Contractor activities must be driven by calendars that reflect Saturdays, Sundays and all Federal Holidays as non-work days.
1.6.2.1 Activity Categories
1.6.2.1.1 Procurement Activities
Examples of procurement activities include, but are not limited to;
Material/equipment submittal preparation, submittal and approval of material/equipment; material/equipment fabrication and delivery, and material/equipment on-site. As a minimum, separate procurement activities will be provided for critical items, long lead items, items requiring Government approval and material/equipment procurement for which payment will be requested in advance of installation. Show each delivery with relationship tie to the Construction Activity specifically for the delivery.
1.6.2.1.2 Government Activities
Government and other agency activities that could impact progress must be clearly identified. Government activities include, but are not limited to;
Government approved submittal reviews, Government conducted inspections/tests, environmental permit approvals by State regulators, utility outages, and delivery of Government Furnished Material/Equipment.
1.6.2.1.3 Quality Management (QM) Activities
The Preparatory Phase and Initial Phase for each Definable Feature of Work identified in the Contractor's Quality Control Plan must be added to each Three-Week Look Ahead Schedule referenced in the paragraph THREE-WEEK LOOK AHEAD SCHEDULE. The Follow-up Phase will be represented by the Construction Activities in the Baseline Schedule and in the schedule
SECTION 01 32 17.00 20 Page 3 updates.
1.6.2.1.4 Construction Activities
No on-site construction activity may have a duration in excess of 20 working days. Contractor activities must be driven by calendars that reflect Saturdays, Sundays and all Federal Holidays as non-work days, unless otherwise defined in this contract.
1.6.2.1.5 Turnover and Closeout Activities
Include activities with all items on the NAVFAC Red Zone Checklist/POAM that are applicable to this project. As a minimum, include all testing, specialized inspection activities, Pre-Final Inspection, Punch List Completion, Final Inspection and Acceptance. Add a milestone for the Facility Turnover Planning Meeting at approximately 75 percent construction contract completion or three to six months prior to Contract Completion Date (CCD), whichever is sooner.
1.6.2.2 Contract Milestones and Constraints
1.6.2.2.1 Project Start Date Milestones
Include as the first activity on the schedule a start milestone titled "Contract Award", which must have a Mandatory Start constraint equal to the Contract Award Date.
1.6.2.2.2 Facility Turnover Planning Meeting Milestones
See paragraph ACTIVITY CATEGORIES above.
1.6.2.2.3 Substantial Completion Milestone
Include an unconstrained finish milestone on the schedule titled "Substantial Completion". Substantial Completion is defined as the point in time the Government would consider the project ready for beneficial occupancy wherein by mutual agreement of the Government and Contractor, Government use of the facility is allowed while construction access continues in order to complete remaining items (e.g. punch list and other close out submittals).
1.6.2.2.4 Projected Completion Milestone
Include an unconstrained finish milestone on the schedule titled "Projected Completion". Projected Completion is defined as the point in time the Government would consider the project complete. This milestone must have the Contract Completion (CCD) milestone as its only successor.
1.6.2.2.5 Contract Completion Date (CCD) Milestone
Include as the last activity on the schedule a finish milestone titled "Contract Completion (CCD)". Calculation of schedule updates must be such that if the finish of the "Projected Completion" milestone falls after the contract completion date, then negative float will be calculated on the longest path and if the finish of the "Projected Completion" milestone falls before the contract completion date, the float calculation must reflect positive float on the longest path.
SECTION 01 32 17.00 20 Page 4
1.6.2.3 Work Breakdown Structure & Activity Code
At a minimum, the Contractor must establish a Work Breakdown Structure (WBS) and provide activity codes identified as follows:
1.6.2.3.1 Work Breakdown Structure (WBS)
Group all activities and milestones within appropriate WBS categories including, at a minimum, the following:
a. Project Milestones:
(1) Management Milestones
(2) Project Administrative Meetings
b. Pre-Construction Phase:
(1) Submittals and Reviews
(2) Procurement
c. Construction Phase; Create multiple sub-sections in accordance with project specific categories of work including in WBS descending order as follows:
(1) General Area
(a) Type of Work Item
1. Location
d. Commissioning & Testing:
(1) Specific area/locations of commissioning
(2) Final Testing
(3) Training
e. Project Closeout: Include activity items such as Punchlist, Demobilization, O&M, As-built Drawings, and As-built NAS.
f. Modifications: Create multiple sub-sections as the project progresses identified by modifications issued.
1.6.2.3.2 Responsibility Code
All activities in the project schedule must be identified with the party responsible for completing the task. Activities must not belong to more than one responsible party.
1.6.2.3.3 Construction Specification Institute (CSI) Masterformat Code
Identify all activities in the project schedule with its respective Specification Section number. Activities must not belong to more than one Section number. If an activity does not have an applicable CSI Code (e.g.
Mobilize), the code must be "0000".
SECTION 01 32 17.00 20 Page 5
1.6.2.3.4 Drawing Code
Identify all activities in the project schedule with its respective Drawing Code. The Drawing Code is the Sheet Number on the primary project drawing which indicates work to be performed. If an activity does not have an applicable Drawing Code (e.g. Mobilize), the code must be "0000".
1.6.2.4 Anticipated Weather Lost Work Days
Use the following schedule of anticipated monthly non-work days due to adverse weather as the basis for establishing a "Weather Calendar" showing the number of anticipated non-workdays for each month due to adverse weather, in addition to Saturdays, Sundays and all Federal Holidays as non-work days.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAYS (Joint Base Pearl Harbor Hickam)
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
3 2 2 0 0 0 0 0 0 1 2 3
Assign the Weather Calendar to any activity that could be impacted by adverse weather. The Contracting Officer will issue a modification in accordance with the contract clauses, giving the Contractor a time extension for the difference of days between the anticipated and actual adverse weather delay if the number of actual adverse weather delay days exceeds the number of days anticipated for the month in which the delay occurs and the adverse weather delayed activities are critical to contract completion. A lost workday due to weather conditions is defined as a day in which the Contractor cannot work at least 50 percent of the day on the impacted activity.
1.6.2.5 Anticipated Restricted Delays
In addition to Section 01 14 00 WORK RESTRICTIONS, allow in the schedule a total of 5 lost workdays per calendar year for instances where access to the project site is not permitted due to a restriction or closure which causes a delay in the work. A lost workday is defined as a day which the Contractor cannot work at least 50 percent of the day. If access to the project site is not permitted for a period longer than 5 lost workdays per calendar year, the Contracting Officer will issue a no cost contract modification as applicable in accordance with the contract clauses extending the contract completion date where the critical path has been impacted.
1.6.2.6 Cost Loading
1.6.2.6.1 Cost Loading Activities
Assign Material and Equipment Costs, for which payment will be requested in advance of installation, to their respective procurement activity (i.e., the material/equipment on-site activity). Assign cost for material/equipment, paid for after installation; labor; and construction equipment to their respective Construction Activities. The value of commissioning, testing and closeout WBS section may not be less than 10 percent of the total costs for Procurement and Construction Activities.
Evenly disperse overhead and profit to each activity over the duration of the project.
SECTION 01 32 17.00 20 Page 6
1.6.2.6.2 Quantities and Units of Measure
Each cost loaded activity must have a detailed…