This document provides an amendment to the solicitation and the related seed project specifications for contract N62478-19-R-4038. The solicitation is for an 8(a) Design-Build/Design-Bid-Build Multiple Award Construction Contract for various locations in Hawaii. It includes new construction, repair, alteration and demolition of infrastructure such as residential and nonresidential buildings, utilities, and roadways. The contract term is one base year plus four option years not to exceed 60 months. The total maximum value is $245 million. A minimum of two IDIQ contracts will be awarded. The proposal receipt date for the solicitation is amended to October 24, 2019. The period of performance for the seed project is amended from 115 to 200 calendar days from notice to proceed. Responses are provided to various questions relating to drawings, specifications, and other requirements.

Amendment No. 0003

View the file

Other files

File Type Posted
Amd_2.pdf PDF
Amd1.pdf PDF
Notice_No._2.pdf PDF
Seed_Project_-_FFD_HQ_B284_FULL_SIZE.pdf PDF
Seed_Project_-_FFD_B284_Geotech_Report.pdf PDF
Notice_No._1.pdf PDF
N62478-19-R-4038_RFP.pdf PDF
Seed_Project_-_FFD_B284_Specifications.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

N62478-19-R-4038, Indefinite Delivery Indefinite Quantity for Plumbing and Mechanical Related Work at Various Locations, State of Haw aii

The Revised Proposal Receipt Date is October 24, 2019, 10:00AM, HST.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 17-Oct-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6247819R4038

X 9B. DATED (SEE ITEM 11)

04-Sep-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

17-Oct-2019

CODE

NAVFAC HAWAII

CONSTRUCTION ACQUISITION DIV (OPHA2)

400 MARSHALL ROAD

JBPHH HI 96860-3139

N62478 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N6247819R4038

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

REVISED SUMMARY OF CHANGES

DOCUMENT 00900 – REQUEST FOR INFORMATION AND RESPONSES

Replace Section 00900, Request for Information and Responses, Amendment No. 0002 with Amendment No. 0003.

SEED PROJECT

Paragraph 10., Commencement, Prosecution and Completion of Work. The completion date is revised from 115 calendar days to 200 calendar days.

Document 00900 Amendment No. 0003

DOCUMENT 00900

REQUESTS FOR INFORMATION & RESPONSES

FOR

RFP NO. NO. N62478-19-R-4038

8(A) DESIGN-BUILD/DESIGN-BID-BUILD MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC),

VARIOUS LOCATIONS, STATE OF HAWAII

Q1. Since we didn’t see the other electrical panel at the site visit, would you be able to provide pictures?

A1. See Amendment No. 0002.

Q2. Is the entire Factor 2 section (inclusive of the EMR rates, DART rates, TRC rates, and the safety narrative) limited to two single-sided pages? It appears as though the 2-page limit only applies to the “Technical Approach for Safety” narrative and that there is no page limitation for the safety metrics.

A2. The two page limitation for Factor 2 – Safety is referring to the Technical Approach for Safety. Please comply with Document 00110, Paragraph 2.2.b.2., Factor 2 – Safety.

Q3. With regard to the Seed Project, the documents indicate that the government will relocate the containers in the northwest corner of the site. Will the containers be taken completely off-site or will we be required to work in phases around the site to accommodate container moves?

A3. Containers will be removed completely out of the limits of work.

Q4. The Geotech Report in Section 7.3.4 recommends “A subdrain system should be installed to collect surface water that accumulates in the UPB below the AC and concrete pavement sections…” Drawing C-103 appears to show drainage by sheet flow east to west. The south entrance drains to the sidewalk culvert. The center of the asphaltic concrete parking drains again to east to west but doesn’t appear to have anywhere to

go. The remainder of the area is concrete pavement with sheet flow to the east corner of the site draining 39,000 SF. According to the Geo-tech Report percolation is almost non-existent and would flow to the Kamehameha Highway. The plans and specs so not include any sub-drainage. Please confirm that no sub-drainage is required.

A4. The center of the ac parking lot is intended to drain to the curb along the sidewalk fronting the building and be directed to the grassed area and the concrete pavement area where it will flow toward Kamehameha highway, consistent with the direction of the flow in existing conditions. We will not be including subdrains.

Q5. Non-Price Evaluation Factors Section 00110 Construction Experience:

Submit a maximum of five (5) relevant construction projects in which the Offeror was the Prime Contractor that best demonstrates the Offeror’s experience on relevant projects that are similar in size, scope, and complexity to the Request for Proposal (RFP). Out of the maximum of five (5) construction projects, at least two (2) projects shall be new construction and one (1) project shall be repair/alteration or related demolition of existing infrastructure. For purposes of this evaluation, a relevant project is defined as new construction and/or repair, alteration and related demolition of existing infrastructure completed within the past five years of the issue date for this RFP. Infrastructure is defined as: 1) residential building construction; 2) construction for industrial buildings and warehouses; 3) nonresidential buildings, other than industrial buildings and warehouses; or 4) improvements such as utilities, landscaping, airfields and roadways. “New Construction” is defined as construction that provides for new or expanded facilities or infrastructure. New construction does not include repair and/or modernization of an existing facility nor does it include replacement or upgrade to an existing infrastructure. The Offeror must have been a Prime Contractor for the relevant projects and each relevant project shall be $1,000,000 or more in dollar value and be completed within the past five (5) years of the date of issuance of this RFP.

Proposals that do not contain any projects that demonstrate experience for the Offeror or its DOR will not be considered.

Non-Price Evaluation Factors Section 00110 Past Performance:

Offerors lacking relevant past performance history will not be evaluated favorably or unfavorably in past performance and will receive a NEUTRAL Confidence rating.

Question: The Corporate Experience evaluation factor does not contain the same statement regarding offerors who lack relevant past performance, which states that they will not be evaluated favorably or unfavorably. Does this statement apply to both evaluation factors, i.e. will a new 8(a) who has managers with relevant construction experience but no contracts to reference be considered eligible for selection?

A5. Document 00110, Evaluation Factors for Award, Part II – Evaluation Criteria, Paragraph 2.2.b.3.(b)(3), “Offerors lacking relevant past performance history will not be evaluated favorably or unfavorably in past performance and will receive a NEUTRAL Confidence rating” applies to past performance only.

Q6. We are requesting the addition to your Solicitation for Design Build Construction Services Number:

N6247819R4038 FAR clause 52.208-9 which adds the Mandatory purchase requirements for AbilityOne products.

A6. FAR clause 52.208-9 will not be added to Request for Proposal N62478-19-R-4038.

Q7. Will a teaming agreement that does not involve a Mentor-Protégé arrangement or the formation of a separate legal entity, be recognized and qualify under the provisions of Section 00100, 1.5.a of the solicitation?

A7. Yes. See Document 00100, Paragraph 1.5.

Q8. Please indicate whether the past performance of each participant in a teaming agreement will be considered and evaluated equally?

A8. Yes.

Q9. G-002, Utility Notes: 1. states, ”…Existing utilities whether shown or not, which have been damaged as a result of the construction work, shall be restored immediately to its original or better condition at the contractors expense.” Will the Government please provide estimated quantity for bidding purposes of the existing utilities not shown to standardize all bidders’ proposals, or will any unforeseen utilities damaged be governed by FAR 52.236-2?

A9. The plans show all known existing utilities in the project site based on our available records. It is not anticipated that any other utilities exist within the limits of work.

Q10. Has existing soil been tested for characterization report for the reuse/removal from federal property to

PVT? If so, will the government please provide? If not, is any contamination of soil to be governed by

FAR 52.236-2?

A10. Soil has not been tested for reuse/removal requirements and shall be tested by the Contractor as required by

PVT prior to disposal.

Q11. Will the government please indicate if a “Partnership Agreement” referred to in Section 00100, 1.5.a is the same thing as a Teaming Agreement if the team members are partners?

A11. Yes.

Q12. Must the original binder contain manual signatures on forms, or may offerors use electronic signatures?

A12. Offerors may use electronic signatures.

Q13. For narrative sections, 11-point font is extremely space limiting in allowing Offerors to highlight their best value experience and approaches to the Government. Would the Government kindly consider allowing Offerors to use 10-point font for the narratives as allowed in previous NAVFAC MACC proposals?

A13. Please follow the requirements in the solicitation.

Q14. May offerors use a smaller font for graphics and tables as long as the text is clear and legible?

A14. See answer to Question 13.

Q15. We strive to reduce the onus on our Government clients who need to complete the same PPQs repeatedly for proposals. Also, contracting representatives are reluctant to (or even discouraged from) completing PPQ forms if formal performance CPARS evaluations have been completed. Will Huntsville please consider allowing offerors to submit completed CPARS evaluations or previously completed/signed PPQs in lieu of new PPQ forms?

A15. Document 00110, Evaluation Factors for Award, Paragraph 2.2.b.3.(a)(1) states in part, “If a completed

Construction Contractor Appraisal Support System (CCASS)/Contractor Performance Assessment Report (CPAR) evaluation is available, it shall be submitted with the proposal for each relevant project included in Factor 1 for construction experience.” If you have PPQs utilizing the exact same form from other procurements, you may submit it.

Q16. Document 00110, Page 25 of 121, Paragraph (iv) Design Experience states, “there shall only be on designer of record”. Given that Hawaii has a small construction market with a finite number of A-E firms capable of performing designs commensurate with the level of complexity expected on the 8(a) MACC, there is the possibility that a Designer of Record (DOR) could be conflicted from performing design on a given task order. It would be preferable that Offerors may propose their Primary DOR, but also alternate DORs in case of a conflict. This is in the best interest of NAVFAC and taxpayers, so all awarded offerors can bid on ever task order. Additionally, this has been a NAVFAC precedent on previous Hawaii MACC solicitations.

a. Please confirm that Offerors may propose other A-E firms as Alternate DORs only in the event of a conflict, in addition to their Primary DOR.

b. Otherwise, can the Primary DOR have a teaming agreement/subcontract to another A/E firm and provide an organizational conflict of interest plan to get around the issue?

c. Or once an offeror is awarded a contract, would it be up to the KO’s discretion to allow us to use an A-E partner not included in our original proposal in the case of a conflict?

A16. Please comply with Document 00110, Paragraph 2.2.b.1. – Factor 1, Corporate Experience.

Q17. Factor 2 Safety states that safety narratives may be up to one (1) double-sided 8.5” x 11” pages or two (2) single-sided 8.5” x 11” pages in length. Please confirm our understanding that the two-page limit only applies to the Technical Approach for Safety narrative and that the EMR, DART, and TRC rates are excluded from that page count.

A17. See answer to Question 2.

Q18. Are there other pricing documents the Government requires beyond those listed in the Solicitation and Seed

Project Specifications (Pricing appears to be 1 LSUM)? Is this correct?

A18. See Document 00110, Evaluation Factors for Award, Paragraph 2.2.a.1.(a) for Solicitation Submittal Requirements for Price.

Q19. Would it benefit the Government to evaluate a completely itemized proposal with Labor, Materials, Subcontractors, etc. broken out by CSI Divisions?

A19. No.

Q20. Reference Spec 10 11 00, paragraph 1.1.1 Summary of Work. The SOW describes a remote gate control from the ‘Operations Control Room’ inside Building 284. This room is not identified in the drawings.

Please:

a. Provide current drawings with the location of Operations Room.

b. Include location, elevation, and circuit designation of the required receptacle.

c. Provide location and elevation of the required control panel.

A20. The Operations Room is located at the northeast corner of Building 284 – see the room with the phone called out on drawing E-201. Assume there is an existing circuit available. Assume that there is space available on the inside south wall of the Operations Room for the new equipment.

Q21. Reference E-201, Note 8. Site plan shows ¾” conduit to Telecom Jack. This location was unidentifiable at the site visit. The phone location called out on E-201 appears to be incorrect. The Floor Plan is inconsistent with current conditions. Please provide exact location of telephone interface.

A21. Connect to telephone outlet as shown on plan.

Q22. Reference E-201, Note 7. The Server Room was not accessible at the site visit. Please provide details for point of connection at the server, including layout of the server room, elevation of cabinets, ceiling type, and address at the server.

A22. See photos in Amendment No. 2.

Q23. Reference E-202. Existing Panel ‘H’ and time clock were not accessible at the site visit. Please provide details for panel ‘H,’ including voltage characteristics, brand, and panel schedule.

A23. See photos in Amendment No. 2.

Q24. Reference E-202, E-002, E-300 detail 2. The #10 AWG conductor is shown on the duct section; however, #8 AWG is shown on the pole details. Please confirm the conductor size for the exterior light poles.

A24. Provide #10 AWG conductors.

Q25. Reference E-202. Please confirm the electrical conduit from new HH-1 is sized adequately to provide for the conductors as shown on E-300 detail 2 (Concrete Base Detail).

A25. The new conduit is sized adequately.

Q26. Reference E-002 detail 2 (Duct Section Details, section C) and sheet E-201. Please identify the termination point of conduit #4 at the gate location and at Building 284.

A26. Provide connections identified on diagrams on sheet E-301.

Q27. Reference sheets C-101, 102, and 103. Please:

a. Confirm the existing concrete ramps at Building 285 and the adjacent open pad are to remain for reuse after removal of existing asphalt and readjustment of civil profile.

b. Confirm existing wooden pedestrian ramp at loading dock shall NOT be removed to provide a continuous application of pavement at the loading area.

A27. a. Existing concrete ramps at B285 and the adjacent open pad are to remain. Provide transition from asphalt to the existing concrete ramp.

b. Existing wooden pedestrian ramp at loading dock to remain in place.

Q28. Reference C-103. Please provide specifications and details for ‘Root Barrier’ requirements.

A28. Provide chemical root barrier consisting of spunbonded polypropylene geotextile fabric with imbedded composite nodules impregnated with a root-controlling chemical. Install at a minimum depth of 19.5 inches. Provide in accordance with manufacturer’s instructions.

Q29. Shall the contractor be required to pay for temporary water and power?

A29. Reasonable amounts of water and power will be made available to the Contractor at the prevailing rates.

See Spec Section 01 50 00, Para 3.2.2

Q30. Reference G-002, General Note 11. Please:

a. Identify the location and size of the ‘Temporary Grassed Parking Area’ as described in General Note 11.

b. Identify the gate to be used to access the temporary grass parking area.

A30. a. The location of the “Temporary Grassed Parked Area” is along Center Drive directly south of the southern limits of disturbed area for new pavement shown on C-101.

b. There is no gate to the temporary grass parking area. The area is accessible directly off Center Drive. The Contractor should coordinate with the Contracting Officer to provide temporary fencing to protect their staging area as needed.

Q31. Reference Section 01 50 00, 3.4.2 Administrative Field Offices: Please confirm that the contractor will be required to provide onsite office trailers.

A31. The Contractor is not required to provide onsite office trailers.

Q32. Reference Section 01 35 26, 1.7.1.1, Site Safety and Health Officer (SSHO)

a. Please confirm SSHO cannot serve as QC Manager.

b. Will the SSHO be allowed to serve in any other capacity (i.e., Superintendent)?

A32. a. SSHO cannot serve as QC Manager. See Spec Section 01 35 26, para 1.7.1.2

b. SSHO may serve as Superintendent as long as they meet the minimum SSHO requirements indicated in Spec Section 01 35 26, para 1.7.1.1.

Q33. Reference Section 01 45 00.00, 1.5.1.1

a. Please confirm that the QC Manager will have no other duties and is to be a standalone position.

b. Will the Alternate QC Manager be allowed to have additional duties and responsibilities (i.e., Superintendent) or is this to be a standalone position?

c. In part 1.5.4 contractor is to “provide separate QC Specialist at the work site…” Is the contractor to provide these as separate standalone positions?

A33. a. The duties of the QC Manager are as stated in Spec Section 01 45 00.00 20 para 1.5.1.1 Duties.

b. One designated Alternate QC Manager is required as stated in Spec Section 01 45 00.00 20 para

1.5.3. The duties are that of the QC Manager as stated in Spec Section 01 45 00.00 para 1.5.1.1.

c. QC Specialists may perform production related duties but must be allowed sufficient time to perform their assigned quality control duties. See Spec Section 01 45 00.00 20 para 1.5.4

Q34. Reference Plan sheet C-104. Plan sheet C-104, Concrete Pavement Jointing Plan, has a legend that calls out

"EJ Doweled Expansion Joint, See Det. 3 sheet C-504". However, the referenced detail does not show dowels. Please clarify if the expansion joints require dowels.

A34. The expansion joints require dowels. Add a dowel to 1-inch diameter and 16-inch long smooth epoxy coated dowel at 12” O.C. to Detail 3/C-504. The dowel will be located at a depth of 4-1/4 inches below to top of the concrete pavement. Paint and oil one half of the dowel. The dowel will be similar to the dowel shown on detail 2/C-504.

Q35. Reference Plan sheet E-200. Plan sheet E-200 indicates removing existing underground duct lines. Please provide as-built drawings for the existing lines that are to be removed.

A35. No as-builts are available

Q36. Reference On plan sheet E-200, there are callouts for note 7 next to the existing lights and bollards. Please clarify if that callout corresponds to note 6. "See C-101 for civil demolition plan."

A36. There is no note 7.

Q37. Reference Plan sheet C-101. C-101, Existing Conditions and Demolition Plan, has a callout for "EXIST

GATE RAIL TO REMAIN." Please indicate the type jointing between the new concrete pavement and the existing concrete supporting the gate rail.

A37. Provide expansion joint.

Q38. Reference Seed Project for RFP No. N62478-19-R-4038; Section 10(a) Notice to Proceed. This section states: “A "Notice to Proceed" is deemed to be given by the Government to the Contractor 30 calendar days after the contract award date.” Can the Government please provide an anticipated date of award for the seed project?

A38. If the seed project is awarded, it will be awarded as a task order on the same day as the basic contract award.

Q39. Reference Section 01 50 00, 3.4.3 Storage Area. Please indicate acceptable locations for:

a. Contractor laydown/staging area

b. Stockpiling

A39. a. Contractor laydown/staging area may be located in the grassed area outside of the fence line directly south of the parking lot – approximately 6000 square feet (see A30). The staging area may also be located within the project site if the Contractor opts to phase his work and move the staging area as needed.

b. Stockpile may be located in the grassed area outside the fence line directly south of the parking lot

– approximately 6000 square feet (see A30). The stockpile may also be located within the project site if the Contractor opts to phase his work and move the stockpile location accordingly.

Q40. Reference Document 00100, Paragraph 1.5 Joint Ventures (JV), Limited Liability Companies (LLC), Limited Partnerships (LP), Etc. The contractor is required to respond to Document 00100, Paragraph 1.5.

Please clarify where within the proposal to include these documents.

A40. See Document 00100, Paragraph 1.1.a.(3).

Q41. Does the government intend to uphold the requirement for a licensed Civil engineer or a licensed geotechnical engineer to visit the site at least 3 times a week during the progress of all portions of work listed in the table found in Section 01 45 00.00 20 part 1.5.4?

A41. Amend to a minimum requirement of one visit per week during progress of earthwork, excavation, subgrade preparation, filling and backfilling, pavement construction, and utility installation for area of responsibility indicated in Section 01 45 00.00 20 para 1.5.4 table.

Q42. Will the individuals mentioned in the same table be additional QC specialist who are to be a part of the contractors staff or can they be subcontractors to the prime contractor

A42. QC Specialists may be subcontractors to the prime contractor. QC Specialists must report directly to the

QC Manager.

Q43. In the RFP for the seed project it says our period of performance for the project is 115 calendar days from the NTP. In Section 01 57 19, 3.1.2.2 Notice of Intent for Construction Activities, it says the contractor shall submit the NOI Package for NPDES coverage (project over 1 acre) a minimum of 90 calendar days prior to the start of the permitted activity. In doing the math, it doesn’t look like its possible to get on the project before liquidated damages

A43. The Government is completing the NPDES and it will be in hand prior to the start of construction.

Section 01 57 19, paragraph 3.1.2.2 Notice of Intent for Construction Activities shall be amended to read, “The Government will obtain a Notice of Intent (NOI) for NPDES coverage under the State of Hawaii's NPDES general permit authorizing discharges of storm water associated with construction activity (HAR 11-55, Appendix C) in accordance with HAR 11-55 and State of Hawaii guidelines.

The permit will be obtained prior to the commencement of construction.” The Government, not the Contractor, shall prepare the submittal on the State's e-Permitting Portal.

Q44. Per specification testing requirements Section 01 57 19 Page 5, please clarify that the soil testing quantity requirements are correct. We estimate over 7,000 cubic yards of material will be removed from this site, which would require 112 days of sampling from our sub-contractor to complete. The total project duration is listed at 115 days.

A44. Section 01 57 19, paragraph 1.2.9.6, third paragraph is revised to read, “The following JBPHH excess soil testing requirements area applicable for material to be disposed of at a permitted landfill: TCLP 8 Metals at 1 sample per 400 cubic yards of surplus soil and PCBs (Total Aroclor) at 1 sample per 400 cubic yards of surplus soil.”