This document contains responses to contractor questions on a Navy solicitation to replace electrical equipment at Naval Support Activity Monterey in California. The firm fixed price design-build project involves replacing two medium voltage fuse disconnect switches, a step-down transformer, and a low voltage switchboard. Only women-owned small businesses are eligible for consideration. The proposal due date remains unchanged at September 2022. The Navy intends to award the contract prior to the end of the 2022 fiscal year but proposals must remain valid for the time stated in the solicitation. The work includes replacing underground conduits and secondary conductors along with the electrical equipment. The Navy will remove debris and temporary buildings from the work area and handle reconnecting services.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE NAVY
NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND SOUTHWEST
750 PACIFIC HIGHWAY
SAN DIEGO CA 92132-5190
25 August 2022
Subj: AMENDMENT 002 – SOLICITATION NO. N6247322R3206: REPLACE UNIT SUBSTATION, BLDG. NO. 216, NAVAL SUPPORT ACTIVITY MONTEREY (NSAM), CA 93943-5035
A. Subject amendment incorporates Government responses to offerors’ Requests for Information (RFIs) into the solicitation.
B. The due date for contractor submission of RFIs remains unchanged.
C. The proposal due date remains unchanged.
D. All other paragraphs, provisions, and conditions of this solicitation remain unchanged.
E. The following attachment is incorporated into the solicitation via Amendment 002:
1. Image - Shed Power Panel
REQUESTS FOR INFORMATION (RFIs)
1. “Is this solicitation only available to WOSB contractors if this is the case do you know any that are bidding on this project so I may offer pricing?”
Government Response: Only Women Owned Small Business (WOSB) firms are eligible for consideration under this solicitation. The Government is unable to provide further information.
2. “The Drawings seem incomplete they ask to replace the riser to the existing meter structure per E4 and there is no E4 in the documents.”
Government Response: The drawings provided in RFP - Part 6 are "as-built" drawings from prior projects.
The drawings are not construction drawings for this project. They are provided to help give a general understanding of the power distribution system for the Lab Rec Area and Bldg. No. 216. Offerors shall not use the provided drawings as instructions for construction. The Designer of Record (DOR) will determine any required new design features. Reference RFP - Part 3 for project scope.
3. “There is no way to determine the length of the 4160v feeders from the drawings there are no site drawings with a scale nor any footages shown.”
Government Response: Offerors are responsible for identifying and verifying field conditions for construction. All relevant as-built drawings are provided in RFP – Part 6. The Contractor must connect the new 4160V circuit B from Manhole 6 to the new 4160V sectionalizing switch input way. The output way of the new sectionalizing switch must connect to the GFE "4160V General Electric Vacuum Limit Amp Control Panel" located in Bldg. No. 216's Compressor Room. The Contractor must connect the new 4160V circuit C from Manhole 6 to the new 4160V sectionalizing switch input way. The output way of the new sectionalizing switch must connect to the new 750KVA transformer. The Designer of Record (DOR) will determine any required new design features for connecting new 4160V feeders in Manhole 6.
4. “There are no drawings of the existing switchgear or pad to determine how large the new one should be.”
Government Response: Offerors are responsible for identifying and verifying field conditions for construction. Offerors may request for information and as-built drawings if they exist. The Designer of Record (DOR) will determine any required new design features for the new replacement equipment.
5. “There are no specifications for the new switchgear.”
Government Response: See RFP - Part 3 Section 2.0 “Project Objectives.”
6. “Are there back-up generation requirements the power will be out for a long duration when replacing this switchgear”
Government Response: Back-up generation is only required for the computer network equipment connected at a transfer switch, which is fed from a 3-Pole breaker at slots 43, 45, and 47 in “Panel A.” The system cannot be down and is backed up by a UPS for a maximum of 10 minutes.
Back-up generation is not required for 4160V compressor system.
7. “Specification section 00 10 00, Part 1, Item #8 (Instructions for Electronic Submission of Proposals) indicates to provide, “Completed provision(s) *” along with the contractors proposal. Are these the Reps & Certs? Please advise.”
Government Response: Yes, the requirement for completed provisions refers to the contractor’s representations and certifications.
8. “Part 3 Statement of Work/Project Program does not specify replacing feeder wires to various panels and equipment within the Building 216. However, at the site visit it was indicated that the feeder wires to various panels/equipment within the Building are to be replaced as indicated on the Power Single Line Diagram, Sheet E103. Please confirm.”
Government Response: Replace the existing branch circuit conductors from the secondary service switchgear to their respected panels and/or loads. Install quantity (2) spare 5” underground conduits from the secondary service switchgear to Bldg. No. 216. Reference UFC - 3-550-01: Exterior Electrical Power Distribution for spare conduit requirements.
Refer to response to Question 2 for RFP - Part 6 attachment "as-built" drawings for drawing references.
9. “Discussed at the site visit was a feeder circuit to an existing shed. However, the single line diagram (Sheet E103) provided with the RFP drawings does not show this feeder circuit. Please advise if this feeder circuit is to be replaced. And if so, please provide information on the wire size and feeder panel.”
Government Response: See response to Question 8.
The power service to the shed was recently installed and was not included in the as-built single line diagram.
Identify if the existing conductors are salvageable for utilizing at the new secondary service switchgear. If acceptable, utilize the existing branch conductor connected at 75 KVA transformer located in the existing shed when installing to the new secondary service switchgear. If replacement is necessary, size the conductor and circuit breaker accordingly to the existing system in the shed. The branch circuit from the secondary service switchgear serves a stepdown 75 KVA dry type 480V/208Y transformer.
10. “Please confirm that the equipment being replaced is limited to: 2ea—MV fused disconnect switches (HVS-2 & HVS-3); 1ea –Transformer (T-34); and 1ea—LV Service Entrance Switchboard and that only the feeder wires to other pieces of equipment are being replaced.”
Government Response: Yes, also include the material and equipment provided in the responses to Questions 3 and 9.
11. “During the replacement of the feeder wires to various panels and equipment, are there any critical pieces of equipment that must remain energized? Will short outages be acceptable without providing temporary power to specific pieces of equipment?”
Government Response: No. Short outages will not be acceptable. See response to Question 6.
12. “On a previous proposal, emailed proposals were acceptable. Please advise if emailed proposals are acceptable in lieu of submitting through PIEE.”
Government Response: Offerors should use PIEE to the maximum extent possible. However, if offerors are unable to use PIEE due to system error or inability to upload documents, submission of proposals via email are acceptable.
13. “When reviewing the existing transformer location and looking at the pad we notice there is no containment curb established.
a. When relocating the new transformer are we to include a containment basin within the new transformer pad?
b. Will this also require additional pipe bollards?
c. Are the new pipe bollards to match the existing in height above ground and the pipe diameter?”
Government Response:
a. Yes
b. Yes.
c. The Designer of Record (DOR) shall determine any required new design features.
14. “There is a small metal building to the Northeast of the transformer location with a power feed from the transformer.
a. Does that building need to remain energized during the disconnect and reconnect period?
b. What is the power draw for that building?
c. Can we get a picture of the electrical panel inside?”
Government Response: No, the building does not require back up power. Picture is attached and titled “Image - Shed Power Panel”.
15. “There is a tank located across from the transformer that we have been informed contains explosive materials.
a. Is that tank recharged through an underground piping system?”
Government Response: No, the tank is used for storage and has no connective piping.
16. “There is a large pile of debris across from the transformer location and between the explosive tank and the metal building against the fence that may hinder some of the work progress.
a. Are we to work around this debris or will the client have it moved?
b. Does the contractor move what needs to be moved in order to complete the work by relocating the debris to another section of the pile or is the contractor required to remove what the contractor disturbs?”
Government Response: No, the Government will be responsible for removing any debris from construction zone.
17. “Where will our staging area be located?”
Government Response: Staging area will be determined by the Post-Award Engineering Technician (ET) and will be located in the Lab-Rec Area.
18. “How far from the tank of explosives does the temporary generator need to be?”
Government Response: There is no minimum distance determined. The laydown plan will be approved by the Post-Award Engineering Technician (ET).
19. “What is the length of time the circuit can be down?”
Government Response: See response to Question 6.
20. “Is the 600 HP air compressor to be kept online while the cut over work is being completed?”
Government Response: No, back-up generation is not required for the 4160V compressor system.
21. “Will we require badge and ID to complete the work?”
Government Response: The worksite is outside the secured areas at Naval Support Activity - Monterey.
Visitor badges and/or passes are not required. If contractor needs access to main base, then visitor passes are required.
22. “Will the contractor have access to the gates, or will the client be onsite throughout the day to let us on and off of the work site location?”
Government Response: The gate to the golf course is open all day. Contractor will be given access to the gate to the Laboratory Area.
23. “Can any of the key personnel (i.e) Superintendent and/or QCM or SSHO be combined position? Or does each key personnel specified in section 01 31 19.05 20 POST AWARD MEETINGS 1.1 need to be dedicated?”
Government Response: The Superintendent may serve as the SSHO for this project.
24. “Are there any hazardous materials? If so can you provide a hazardous materials report for all affected structures/areas?”
Government Response: There are no hazardous materials expected to be encountered.
25. “There are two temporary buildings adjacent to the LRB that appear to be hardwired into the system through an existing electrical feed that runs from the west end of the building against the building. These building will need to be moved for the contractor to have access to the wall for the work that needs to be done.
a. Will the client perform that Scope of Work or will that be the contractors responsibility?
b. Will the client perform the disconnect and reconnect services to these buildings or will that be the responsibility of the contractor?”
Government Response:
a. The Government will be responsible for moving the two (2) temporary buildings away from construction zone.
b. The Government will be responsible for disconnecting and reconnecting services to the two temporary buildings.
26. “Per the job walk, it was discussed that the Medium Voltage conductor between the GE Vacuum Limit Amp Control to the Siemens Induction Motor located in Equipment Room 105 needed to be replaced.
Please confirm that Conductor between GE Vacuum Limit Amp Control and the Siemens Induction Motor shall be replaced.”
Government Response: No, do not replace conductors between GE Vacuum Limit Amp control and the Siemens Induction Motor. See response to Question 3 for direction with medium voltage conductor replacements.
27. “Per the job walk, it was mentioned that medium voltage conductor from HVS-3 to Compressor inside building 216 must be replaced, existing raceway shown during job walk would be undersized for the new MV conductor. Please confirm that the intent is to replace the complete raceway and MV conductor from new HVS-3 Location all the way to GE Vacuum Limit Amp Control Unit inside equipment room.”
Government Response: Confirmed, the intent is to replace the complete raceway and MV conductor from the new HVS-3 Location all the way to the GE Vacuum Limit Amp Control Unit inside the equipment room.
28. “Per job walk, it was discussed that the exterior wall of the building is 24” thick with double rebar matt.
Please confirm?”
Government Response: Bldg. No. 216 was constructed as an engine test cell and the exterior walls are very heavy with reinforced concrete. Actual wall dimensions shall be confirmed by the contractor.
29. “Please confirm that Sheet E122 (As_built_drawing_B216_Power_Plan_First_Floor) is just for reference and showing existing equipment location only. No new work or equipment is expected per this sheet.”
Government Response: Correct, attached "as-built" drawings are provided for reference.
See response to Question 2.
30. “Who is responsible for start-up and working verification of the 4160V Compressor located inside the equipment room?”
Government Response: The end-user will be responsible for assisting with start-up and working verification of the 4160V compressor system. Contractor will standby during start-up to trouble shoot any construction deficiencies.
31. “Please confirm that during scheduled outages contractor would only be responsible for providing temporary generator power to Building 216.”
Government Response: See response to Question 6.
32. “Please clarify the intent or confirm, re-connecting secondary loads to new building 216 switchgear would extend existing underground conduit to new gear location and all secondary conductors will be replaced.”
Government Response: The intent is to replace the existing underground conduit.
See responses to Questions 8 and 9 for secondary conductor replacements.
33. “Will a Commissioning Agent be required?”
Government Response: No.
34. “Can The QC Manager, SSHO and Superintendent be one person?”
Government Response: See response to Question 23.
35. “Will a Fire Protection Engineer be required?”
Government Response: No.
36. “Due to the current state of the market the time for procurement of long lead items can take up to 52+ weeks after the product submittal has been approved by the Government. Contractor would recommends that the period of performance be changed from 550 calendar days to 655 calendar days due to Design Phase, Procurement Long Lead times and Unknown impact on lead times due to COVID‐19 impact.”
Government Response: The request for the period of performance to be extended is not necessary beyond 550 calendar days because the contractor will have the ability to request additional time if equipment is delayed due to COVID-19 impacts.
37. “Once RFI questions are answered we are requesting that the proposal due date be extended by 21 calendar days.”
Government Response: This work is targeted for a FY22 Q4 award, meaning that the solicitation is targeted for award prior to 30 September 2022. A proposal extension of 21 days is not feasible for the Government’s end of Fiscal Year (FY) deadline.
38. “Contractor would recommend that the project be awarded within 30 days of proposal submission as the manufactures and vendors will only hold their price for no more than 30 days due to the current state of the market.”
Government Response: The Government intends to award this solicitation prior to 30 September 2022.
However, proposals must still remain valid for the identified time listed within this RFP. This requirement remains unchanged.
Ashley N. Thornton Contracting Officer