Q&A 0013 Feb 3 2020.pdf

PDF 167 KB Posted

Attached to
Marine Corps Base Camp Pendleton and Naval Weapons Station Seal Beach Flooring IDIQ Under NAICS 238330
Solicitation number
N62473-20-R-0013
Issued by

View the file

Other files

File Type Posted
Q&A 0013 UPDATED FEB 5 2020.pdf PDF
Q&A 0013 Updated FEB 4 2020.pdf PDF
J-B-01 FLOORING ELINS UPDATED FEB 4 2020.xlsx XLSX spreadsheet
N6247320R0013 Amendment 0002.pdf PDF
Wage Determination Orange County Jan 27 2020 (2).pdf PDF
Q&A 0013.pdf PDF
Wage Determinations San Diego County Jan 27 2020.pdf PDF
Amendment 0001_N6247320R0013.pdf PDF
REVISED Exhibit H GENERIC UFGS Guides for projects.docx DOCX document
UPDATED Exhibit B - Experience - Offeror.docx DOCX document
Exhibit F Surety Form.docx DOCX document
Exhibit E Financial Questionnaire.docx DOCX document
SAN DIEGO COUNTY WD 122719.pdf PDF
LOS ANGELES COUNTY WD 122719.pdf PDF
N6247320R0013 RFP.pdf PDF
Exhibit C - PPQ.docx DOCX document
Exhibit D Safety Data.docx DOCX document
Exhibit A - Offeror Team Composition and Management.docx DOCX document
Exhibit G Revised RFI Form.docx DOCX document
REVISED J-B-01 FLOORING ELINS.xlsx XLSX spreadsheet
Exhibit J JOC IDIQ SAMPLE SUBMITTAL REGISTER.docx DOCX document
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION NO: N62473-20-R-0013

INDEFINITE DELIVERY INDEFINITE QUANTITY WOMEN OWNED SMALL

BUSINESS SET-ASIDE UNDER NAICS 238330 FOR NEW FLOORING WORK,

ADDITIONS, ALTERATIONS, MAINTINANCE, AND REPAIRS AT VARIOUS

GOVERNMENT INSTALLATIONS WITHIN THE MARINE CORPS BASE CAMP

PENDLETON AND NAVAL WEAPONS CENTER SEAL BEACH, CALIFORNIA

UNDER NAVAL FACILITIES ENGINEERING COMMAND SOUTHWEST (NAVFAC

SW) AREAS IF RESPONSIBILITY (AORs)

Questions & Answers

January 27, 2019

Question 1: I know the limit for contractor submitted experience data (Exhibit B) is 5 projects, but is there a limit to the number of client filled out PPQ’s ( Exhibit C) that can be submitted with the proposal beyond the projects that correspond with the 5 Exhibit B projects?

Answer: Per page 26 of the RFP, PPQs shall only be submitted when there is not a CCASS, ACASS, or CPARS for project included in Factor 2. Therefore, the maximum amount of

PPQs submitted should be 5.

Question 2: Will proposals be accepted via email or only hard copy mailed in?

Answer: Per page 21 of RFP, proposals must be delivered to NAVFAC SW hard copy by the date and time stated in Block 13 of SF 1442.

Question 3: I have reviewed the documents for the above referenced solicitation in SAMS and it states that if a site visit is required an amendment will be issued. Can you confirm that at this time there is not one scheduled? And if one is going to be scheduled will it be mandatory attendance?

Answer: There is no site visit scheduled. If a site visit were to be scheduled, it would not be mandatory attendance.

February 3, 2019

Question 4: The previous contract included LBP and ACM will the Government be adding to this one?

Answer: Please see pages 142-145 of the RFP: Additional Environmental Requirements.

Question 5: Lines A017-A019 State 18”x18” carpet tile. Due to availability can 24”x24” tiles be substituted.

Answer: Please propose in accordance with the RFP.