Amend 0001 20R6000.pdf
PDF 811 KB Posted
- Attached to
- Building 17 and 17A Renovation and Addition
- Solicitation number
- N6247020R6000
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Large Cabinet.jpg | JPG image | |
| Tabernacle.jpg | JPG image | |
| 08 62 00 Translucent Wall Panels.pdf | ||
| Organ (2).jpg | JPG image | |
| Grand Piano.jpg | JPG image | |
| Baptismal Font.jpg | JPG image | |
| Organ (1).jpg | JPG image | |
| Altar (2).jpg | JPG image | |
| Amnd 0006 20R6000 Final.pdf | ||
| Altar (1).jpg | JPG image | |
| Amnd 0005 20R6000 Final.pdf | ||
| Amnd 0004 20R6000 Final.pdf | ||
| Amnd 0003 20R6000 Final.pdf | ||
| Amnd 0002 20R6000 Final.pdf | ||
| NAVFAC DWG 60025678.pdf | ||
| NAVFAC DWG 60025676.pdf | ||
| N4008519B0095 Drawings_Part8.pdf | ||
| N4008519B0095 Drawings_Part3.pdf | ||
| N4008519B0095 Drawings_Part6.pdf | ||
| N4008519B0095 Specs.pdf | ||
| N4008519B0095 Drawings_Part7.pdf | ||
| 19-0095 Asbestos Survey 011020.pdf | ||
| N4008519B0095 Drawings_Part2.pdf | ||
| N4008519B0095 Drawings_Part5.pdf | ||
| RFP N62470-20-R-6000.pdf | ||
| N4008519B0095 Drawings_Part1.pdf | ||
| 19-0095 Lead Survey 011020.pdf | ||
| N4008519B0095 Drawings_Part4.pdf | ||
| N4008519B0095 Drawings_Part9.pdf | ||
| Master PPI Form Template.xls | XLS spreadsheet |
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICIATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 11)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPIRATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
19-0095 Building 17 and 17A Renovation and Addition Solicitation N6247020R6000 Marine Corps Base Camp Lejeune, North Carolina Amendment 0001
Block 14. DESCRIPTION OF AMENDMENT (cont.)
A. The following provides the Government’s responses to pre-award inquiries:
REFERENCE QUESTION GOVERNMENT RESPONSE
Page Section Para.
2 RFP 12 The project RFP indicates that one person may fill the roles of Superintendent and Safety & Health Officer, if duly qualified, as defined in the project specification. The Quality Control Manager must be a stand-alone position. However, Spec Section 01 30 00, Paragraph 1.6, Spec Section, Paragraph 1.3 and Spec Section 01 45 10, Paragraph 1.5.1.1 indicates that the Superintendent can also fill the roles of the QC Manager and SSHO if qualified for all three positions? Can one person fill the roles of the Superintendent, QC Manager and SSHO if qualified for all three positions?
The project RFP is correct.
One person may fill the roles of Superintendent and Safety & Health Officer, if duly qualified, as defined in the project specification. The Quality Control Manager must be a stand-alone position.
9 03 30
1.6.5.1 Spec Section 03 30 00, Paragraph 1.6.5.1
indicates that the concrete quality manager must hold a current license as a professional engineer in a U.S. state or territory with experience on at least five similar projects. Evidence of extraordinary proven experience may be considered by the Contracting Officer as sufficient to act as the Quality Manager. The concrete work required for the project is minor in nature and having a PE onsite while this work is being performed will add significant unnecessary cost to the project. Can this requirement be removed by Amendment?
Concrete quality control manager does not need to be a professional engineer.
19-0095 Building 17 and 17A Renovation and Addition Solicitation N6247020R6000 Marine Corps Base Camp Lejeune, North Carolina Amendment 0001
10 03 30
1.6.7 Spec Section 03 30 00, Paragraph 1.6.5.1
indicates that all sampling and testing must be performed by an approved, onsite, independent, accredited laboratory. The concrete work required for the project is minor in nature and setting up & staffing an onsite testing lab while this work is being performed will add significant unnecessary cost to the project. Can the requirement for an on site Concrete Testing Lab be removed by Amendment?
The requirement for an onsite lab can be deleted.
Change accredited to qualified.
D-101 D-102 D-103
PD101
MD101_
ED101
Demo Notes Demo Notes Demo Notes Demo Notes Demo Notes Demo Notes
Note 1-7 Note 1,2,7 Note 1-3 Note 1,3 Note 1-4, 6, 9, 10 Note 2
There is no reference in the RFP, bid form, or the specifications to demolish 17C or 17D, however, demolition drawings refer to the demolishment of 17C and 17D. Are we to include buildings 17C and 17D in the estimate for heavy demolition? If these buildings are to be demolished, where on the bid form would these be included?
Include the demolition of 17C in the heavy demolition. Include the demolition of 17D as a separate line item.
B. All other contract terms and conditions remain unchanged.
| Amnd 0001 20R6000 |
| Untitled |
| Untitled |
Pg2 Amnd 0001 20R4064
| IDCode: |
| Page: 1 |
| Pages: 3 |
| AmendNo: AMENDMENT NO. 0001 |
| EffDate: 05/08/20 |
| ReqNo: |
| ProjNo: 19-0095 |
| IssCode: ROICC81 |
| IssuedBy: OICC FLORENCE |
ROICC FLORENCE CAMP LEJEUNE
1121A HAMMOND ROAD
CAMP LEJEUNE, NC 28547
| AdmCode: |
| AdminBy: See Item 6 |
| ContName: |
| ContStrt: |
| ContCnty: |
| ContSt: |
| ContZIP: |
| Code: |
| FacCode: |
| SolChgYs: Yes |
| SolChgNo: Off |
| SolAmdNo: N6247020R6000 |
| AmendDate: 04/16/20 |
| ModNo: |
| ModDate: |
| NoCopies: 1 |
| Amended: Yes |
| OffrExt: Off |
| OffrNoEx: No |
| ApprData: |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: |
N6247020R6000 Building 17 and 17A Renovation and Addition
The date and the hour for the receipt of proposals remains 18 May 2020 no later than 2:00 pm (EST).