Amendment_0002.doc
DOC document 63 KB Posted
- Solicitation number
- N62387-15-R-2036
About this file
Amendment 0002
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP-RFQ_Q_AND_A_UUV_15-R-2036_(3).pdf | ||
| RFP-RFQ_Q_AND_A_UUV_15-R-2036_(2).pdf | ||
| RFP-RFQ_Q_AND_A_UUV_15-R-2036_(1.0).pdf | ||
| 15-R-2036_Amendment_0001.pdf | ||
| 15-R-2036.doc | DOC document | |
| Attachment_C_-_UUV_Procedures.docx | DOCX document | |
| Attachment_B.docx | DOCX document | |
| SynopsisUpdated.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
The following have been modified:
ATTACHMENT A
ATTACHMENT A
Attachment A
UUV LNR DABOB BAY NOTIONAL SCHEDULE – Base Period
| Day |
| Activity |
| Berthing & |
Meals
Wed
14 Oct 0800: Barge/tug arrive at NASNI pier for loading GFE, UUV, and support equipment
Vessels required – Barge / Tug
Note: Tug only required to deliver barge to NASNI.
Thu
15 Oct Contractor installs cradle system. Continue Loading GFE, UUV, and support equipment
Vessels required - Barge
Fri
16 Oct Contractor installs cradle system. Continue Loading GFE, UUV, and support equipment
Vessels required - Barge
Sat
17 Oct Contractor installs cradle system. Continue Loading GFE, UUV, and support equipment
Vessels required - Barge
Sun
18 Oct Contractor installs cradle system. Continue Loading GFE, UUV, and support equipment
Vessels required - Barge
Mon
19 Oct Complete loading of all GFE, UUV, and support equipment.
Barge departs NASNI for Hood Canal.
Vessels required - Barge / Tug
Tues, 20 Oct -
Wed, 28 Oct Transit North
Vessels required - Barge / Tug
Thu
29 Oct 0800 Tug/barge arrive at Naval Base Kitsap (NBK), Hood canal. NBK tugs assist mooring the barge to Service Pier. Space will be available at Service Pier for the tug or tug may depart for fuel/servicing.
Vessels required - Barge / Tug
Fri
30 Oct UUV preps in-port
Vessels required - Barge
Sat
31 Oct UUV preps in-port
Vessels required - Barge
Sun
01 Nov UUV preps in-port
Vessels required - Barge
Mon
02 Nov 1000: UUV is launched and towed to the range for preliminary runs. Tug takes UUV under tow with Gov’t Range vessels supporting.
1500: UUV is recovered to the barge.
Vessels required – Barge / Tug
Tue
03 Nov 0500: UUV is placed in the water. Tug tows UUV to Dabob Bay for ops. Tug stands by during ops and returns UUV to pier upon completion of ops.
Vessels required – Barge / Tug
Wed
04 Nov Government personnel conduct UUV replenishment. No support required from tug
Vessels required - Barge
Thu
05 Nov 0500: UUV is placed in the water. Tug tows UUV to Dabob Bay for ops. Tug stands by during ops and returns UUV to pier upon completion of ops.
Vessels required – Barge / Tug
Fri
06 Nov 0500: UUV is placed in the water. Tug tows UUV to Dabob Bay for ops. Tug stands by during ops and returns UUV to pier upon completion of ops.
Vessels required – Barge / Tug
| Sat, 07 Nov – Wed, 11 Nov |
| Government personnel conduct UUV replenishment. No support required from tug |
Vessels required - Barge
Thu
12 Nov 0500: UUV is placed in the water. Tug tows UUV to Dabob Bay for ops. Tug stands by during ops and returns UUV to pier upon completion of ops.
Vessels required – Barge / Tug
Fri
13 Nov 0500: UUV is placed in the water. Tug tows UUV to Dabob Bay for ops. Tug stands by during ops and returns UUV to pier upon completion of ops.
Vessels required – Barge / Tug
Sat
14 Nov GFE, UUV, and support equipment stowed for sea.
Vessels required - Barge
Sun
15 Nov GFE, UUV, and support equipment stowed for sea.
Vessels required - Barge
Mon
16 Nov GFE, UUV, and support equipment stowed.
Barge departs Hood Canal for NASNI.
Vessels required - Barge / Tug
Tues, 17 Nov -
Tues, 24 Nov Transit South
Vessels required - Barge / Tug
Wed
25 Nov Barge/tug arrive at NASNI pier for demobilization of GFE, UUV, and support equipment
Vessels required – Barge / Tug
Thu, 26 Nov –
Sun, 29 Nov Demobilization continues
Vessels required - Barge
Mon
30 Nov Demobilization complete. Barge departs NASNI NLT 1600
Vessels required – Barge / Tug
The following have been deleted:
ATTACHMENT C
(End of Summary of Changes)