Attachment C

Questions Request Form

Small Craft Repair HSLs 13&14 Restoration Part III

#
SOW/PWS Reference
Question
Answer
1.
RFP Package Attach B Price Schedule
Is it the Government’s desire to have the price for both craft 13 and 14 restoration and upgrade divided by 6 Months (i.e. Column C has Unit of Measure as Mth and Column D has Qty 6)
Yes. It is a total FFP for complete repairs restoration based on four monthly payments.

PoP revised to Four (4) months.

2.
COMBINED SYNOPSIS/SOLICITATION SUPPLEMENTAL INFORMATION, Sections 5.2 and 8.
Section 5.2 Requires Firm Fixed Unit Pricing for CLIN 0001. “See Attachment D, Price Schedule.” Section 8. Attachments - calls out, “Attachment B Price Schedule”. Attachment B Price Schedule is titled, “INDEPENDENT GOVERNMENT ESTIMATE (IGE)” on the “Services” worksheet. Which is correct, Attachment B or Attachment D that is not included with the solicitation?
It is a typo. It is attachment B
7.
N62306-16-R-0003, 5.4
5.4 Provide documentation to demonstrate evaluation factors capability. See attached Performance Work Statement for description of services." I am unclear on what documentation is being requested. Can you or can you direct me to someone who can help clarify what is being requested??
Documentation to provide capability of Evaluation per Section 7. Best Value Evaluation
8.
N62306-16-R-003
The Cummins engine with 301 BHP is a 5.9 NOT the 5.7. Will a 5.9 be accepted?
It is a typo. It should be 6.7.
9.
N62306-16-R-003
Can we inspect the vessels?
There is no scheduled site visit for the requirement.
10.
N62306-16-R-003
What is the year of the boats?
2000
11.
N62306-16-R-003
Who made the vessels?
United States Marine Inc.
12.
N62306-16-R-003
Can the Northern Lights Generator be replaced with a different manufacture?
Generators need to be Northern Lights to stay same as rest of class.
13.
N62306-16-R-003
I do not see an attachment D, price schedule. Is can this be sent to me or where can I find it?
It is a typo. It is attachment B
14.
N62306-16-R-0003

Attachment A 5.2.1.13

It states, provide and install new Morse control cables for the Emergency shutdown. Does the emergency shutdown need to be a mechanical shutdown (I.E. air flap on intake), or is electrical Emergency Stop Acceptable?
Electrical Stop is acceptable.
15.
N62306-16-R-0003

Attachment A 5.2.1.15

Is there a suitable seawater strainer and seacock valve in place currently?
Yes.
16.
N62306-16-R-0003

Attachment A 5.2.3.2

What coupling is on the HSL 16? Is the coupling direct drive or clutched? Inline or belt driven? And what is the required HP?
Inline, direct drive coupling. Hydraulic Pump is a Denison PV 15.
17.
N62306-16-R-0003
Do the new Cummins engines need to be 12VDC or 24VDC start/electronics?
24V
18.
N62306-16-R-0003 Attachment A 7.2.10
What recue pod and automatic release is currently installed? Model # Etc.?
Switlik CPR Cruising Passage Raft with Hammar 20 release.
20.
N623606-16-R-0003 Attachment A 5.2.1.7
Does the vessel have a dripless seal or a mechanical packing on the shaft log?
Mechanical packing.
21.
5.2.1.3
Are trolling valves required to be included with the new replacement transmissions?
Trolling valves are required.
22.
5.2.2.1
Does the generator require the S-4F panel with AC voltmeter, frequency meter, amp meter, DC start/stop, water temp, voltmeter, hour meterand oil pressure gauges OR the S-3C with just the , water temp, voltmeter, hour meterand oil pressure gauges
S-4F