Attachment C
Questions Request Form
Small Craft Repair HSLs 13&14 Restoration Part III
| # |
| SOW/PWS Reference |
| Question |
| Answer |
| 1. |
| RFP Package Attach B Price Schedule |
| Is it the Government’s desire to have the price for both craft 13 and 14 restoration and upgrade divided by 6 Months (i.e. Column C has Unit of Measure as Mth and Column D has Qty 6) |
| Yes. It is a total FFP for complete repairs restoration based on four monthly payments. |
PoP revised to Four (4) months.
| 2. |
| COMBINED SYNOPSIS/SOLICITATION SUPPLEMENTAL INFORMATION, Sections 5.2 and 8. |
| Section 5.2 Requires Firm Fixed Unit Pricing for CLIN 0001. “See Attachment D, Price Schedule.” Section 8. Attachments - calls out, “Attachment B Price Schedule”. Attachment B Price Schedule is titled, “INDEPENDENT GOVERNMENT ESTIMATE (IGE)” on the “Services” worksheet. Which is correct, Attachment B or Attachment D that is not included with the solicitation? |
| It is a typo. It is attachment B |
| 7. |
| N62306-16-R-0003, 5.4 |
| 5.4 Provide documentation to demonstrate evaluation factors capability. See attached Performance Work Statement for description of services." I am unclear on what documentation is being requested. Can you or can you direct me to someone who can help clarify what is being requested?? |
| Documentation to provide capability of Evaluation per Section 7. Best Value Evaluation |
| 8. |
| N62306-16-R-003 |
| The Cummins engine with 301 BHP is a 5.9 NOT the 5.7. Will a 5.9 be accepted? |
| It is a typo. It should be 6.7. |
| 9. |
| N62306-16-R-003 |
| Can we inspect the vessels? |
| There is no scheduled site visit for the requirement. |
| 10. |
| N62306-16-R-003 |
| What is the year of the boats? |
| 2000 |
| 11. |
| N62306-16-R-003 |
| Who made the vessels? |
| United States Marine Inc. |
| 12. |
| N62306-16-R-003 |
| Can the Northern Lights Generator be replaced with a different manufacture? |
| Generators need to be Northern Lights to stay same as rest of class. |
| 13. |
| N62306-16-R-003 |
| I do not see an attachment D, price schedule. Is can this be sent to me or where can I find it? |
| It is a typo. It is attachment B |
Attachment A 5.2.1.13
| It states, provide and install new Morse control cables for the Emergency shutdown. Does the emergency shutdown need to be a mechanical shutdown (I.E. air flap on intake), or is electrical Emergency Stop Acceptable? |
| Electrical Stop is acceptable. |
Attachment A 5.2.1.15
| Is there a suitable seawater strainer and seacock valve in place currently? |
| Yes. |
Attachment A 5.2.3.2
| What coupling is on the HSL 16? Is the coupling direct drive or clutched? Inline or belt driven? And what is the required HP? |
| Inline, direct drive coupling. Hydraulic Pump is a Denison PV 15. |
| 17. |
| N62306-16-R-0003 |
| Do the new Cummins engines need to be 12VDC or 24VDC start/electronics? |
| 24V |
| 18. |
| N62306-16-R-0003 Attachment A 7.2.10 |
| What recue pod and automatic release is currently installed? Model # Etc.? |
| Switlik CPR Cruising Passage Raft with Hammar 20 release. |
| 20. |
| N623606-16-R-0003 Attachment A 5.2.1.7 |
| Does the vessel have a dripless seal or a mechanical packing on the shaft log? |
| Mechanical packing. |
| 21. |
| 5.2.1.3 |
| Are trolling valves required to be included with the new replacement transmissions? |
| Trolling valves are required. |
| 22. |
| 5.2.2.1 |
| Does the generator require the S-4F panel with AC voltmeter, frequency meter, amp meter, DC start/stop, water temp, voltmeter, hour meterand oil pressure gauges OR the S-3C with just the , water temp, voltmeter, hour meterand oil pressure gauges |
| S-4F |