Statement of Work Summary
This is a Statement of Work (SOW) for the East Coast Site Seating project located at DeFlorez Building, NSA Orlando, prepared by NAWCTSD Orlando. The contractor must purchase 70 office chairs meeting GSA Grade 3 (High-Performance Ergonomic) specifications and distribute them across eight remote military installations. Chair specifications include black color, non-plastic base, minimum 5 castors, 20" x 30" back, 20" x 20" seat, 16"-23" seat height range, 300-pound capacity, mesh back, fabric cushioned seat, adjustable lumbar support, and adjustable pneumatic seat height, tilt tension, tilt lock/recline limiter, recline, and armrest height/width/forward-back positioning. All chairs must include a minimum 10-year warranty on moving components, pneumatic cylinders, and frame structures.
Distribution requires shipping chairs to NAS Jacksonville (22 chairs), MCAS Cherry Point (5 chairs), Norfolk (14 chairs), NAS Pensacola (11 chairs), NAS Meridian (2 chairs), NAS Corpus Christi (4 chairs), MCAS Miramar (9 chairs including one for Yuma), and NAS North Island (3 chairs). The delivery deadline is not later than February 2, 2027, with FOB Destination terms. The contractor must submit three copies of Safety Data Sheets, Statement of Nonuse of Ozone Depleting Substances, Accident Prevention Plan with Activity Hazard Analysis, Work Schedule, Bonds and Insurance, worker citizenship information, and standard drawings in ACAD LT 2012 and PDF format within seven calendar days after award. All work must comply with federal, state, and local codes, including OSHA standards, and contractors must obtain proof of U.S. citizenship and security clearances as required. Working hours are established by the Contracting Officer between 6 a.m. and 6 p.m., Monday through Friday, excluding Government holidays, with no power disruptions permitted during normal working hours.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CLIN Structure_R1.xlsx | XLSX spreadsheet | |
| QandA10Nov2026.xlsx | XLSX spreadsheet | |
| CLIN Structure.xlsx | XLSX spreadsheet | |
| SOURCES SOUGHT_Chairs_Final.pdf | ||
| SOW-East Coast Site Seating_Final .pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Title: East Coast Site Seating Activity Location: DeFlorez Building, NSA Orlando Scope of Work Prepared by: NAWCTSD, Orlando
PART 1 GENERAL
1 GENERAL INFORMATION:
It is the declared and acknowledged intention and meaning to provide new seating for 8 remote sites. Chair must be delivered NLT 2 February 2027. Invoice for payment must be submitted in Waide Area Workflow NLT 2 February 2027. FOB Destination.
Detailed Project Description
Phase 1: Purchase 70 office chairs from approved vendor. Chairs must meet the following specifications, equivalent to GSA’s Grade 3 (High-Performance Ergonomic) criteria:
• Color: Black
• Non-Plastic Base
• Minimum of 5 castors
• Back Min: 20” x 30”
• Seat Min: 20” X 20”
• Seat Hight Range: 16” – 23”
• Lbs Cap: 300lbs
• Mesh Back
• Fabric Cushioned Seat
• Adjustable Lumbar Support
• Adjustments:
• Pneumatic Seat Height
• Tilt Tension
• Tilt Lock / Recline Limiter
• Recline
• Armrest Heigh/Width/Forward and Back
• Warranty of at least 10 years on moving components, pneumatic cylinders, and frame structures
Phase 2: Ship the number of chairs indicated to the following locations:
• NAS Jacksonville – Qty 22
NAWCTSD ISEO
Attn: Kerri Zalman Yorktown Avenue, Building #512 Jacksonville, Fl. 32212
(904) 546-4087
• MCAS Cherry Point – Qty 5
Attn: Jim Slape, 252-466-7676 Bldg 4066, 6th Ave.
MCAS Cherry Point Cherry Point, NC 28532
• Norfolk – Qty 14
Attn: Michael Trapkin 466 Bellinger Blvd Bldg SP-381 Room 1017 Norfolk, VA 23511
• NAS Pensacola – Qty 11
Attn: Shawn Cutchins 217 San Carlos Rd.
Bldg. 3268 Pensacola, FL 32508
(850) 452-3823
• NAS Meridian – Qty 2
Attn: C. Doss, B. Barner, or D. Taylor Bldg. 150, Rm 165A 150 Fuller Road Meridian, MS 39309
(601) 679-3306
• NAS Corpus Christi –Qty 4
Attn: Victor Rodriguez Simulator Building BLDG 83, room 103 401 Bataan Street NAS Corpus Christi, Texas 78419
(316) 961-3826
• MCAS Miramar – Qty 9 (includes one for Yuma)
Attn: Jesse Thien 8656 Edson Rd MCAS Miramar San Diego, CA 92145
(858) 978-5816
• NAS North Island – Qty 3
Attn: Scott Scharmann Bldg 646, S O Street, 2nd Floor NAS North Island San Diego, CA 92135
Several requirements for this project phase are as follows:
• All applicable federal, state, and local codes shall be followed including but not limited to Unified Facility Criteria found at https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc
• Ensuring that all work is tested to be complete and useable
• Ensuring dust and noise levels are kept to a minimum with daily cleanup.
1.2 SUBMITTALS
Submit three copies of the following for approval by the Contracting Officer within 7 calendar days after award.
1.2.1 Statements
a. Safety Data Sheet (SDS),
b. Statement of Nonuse of Ozone Depleting Substances (ODS),
c. Accident Prevention Plan including Activity Hazard Analysis,
d. Work Schedule,
e. Bonds and insurance.
f. Name, SSN, and Citizenship of each on site worker, and
g. Standard drawings in ACAD LT 2012 and PDF.
https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc
1.3 PERIOD OF PERFORMANCE
The Contractor shall be required to complete all work, ready for use, not later than 2 February 2027.
1.4 DEFINITIONS
Where "as shown", "as indicated", "as detailed", or words of similar import are used, it shall be understood that reference to the drawings/sketches accompanying this specification is made unless stated otherwise. Where "as directed", "as permitted", "approved", "acceptance", or words of similar import are used, it shall be understood that the direction, requirements, permission, approval, or acceptance of the Contracting Officer is intended unless stated otherwise. As used herein, "provided" shall be understood to mean "provided complete in place in a completely usable condition", that is "furnished and installed". As used herein "secure" shall be understood to mean "marked by solidity, firmness, and stability, especially in design or construction".
1.5 SAFETY REQUIREMENTS
In performing the contract, the Contractor shall provide for protecting the lives and health of employees and other persons and for preventing damage to property, materials, supplies and equipment in accordance with the latest revision of the U.S. Army Corps of Engineers "Safety and Health Requirements Manuals" (EM 385-1-1) and "Occupational Safety and Health Standards" (29 CFR 1910). Prior to commencement of the work, the Contractor shall meet in conference with representatives of the Contracting Officer to discuss and develop mutual understandings relative to the administration of safety. All OSHA work standards shall be followed including but not limited to Lockout/Tagout procedures. Electrical Safety Code and OSHA 1910 subchapter S shall be specifically followed. Prior to commencement of the work, the contractor shall meet in conference with representatives of the Contracting Officer to discuss and develop a mutual understand relative to the administration of safety. Power shall not be deenergized without at least 2 weeks’ prior approval of the Contracting Officer. No live electrical work shall be permitted.
PART 2 PRODUCTS
Use only Contracting Officer approved parts or materials.
PART 3 EXECUTION
3.1 STATION REGULATIONS
The Contractor and his employees and subcontractors shall become familiar with and obey all applicable Federal, State, local and station regulations, including fire, safety, traffic, and security regulations. No employee of the Contractor shall be admitted to the work site without satisfactory proof of United States citizenship. Some work areas may require an escort and/or a security clearance for access.
3.1.1 Working Hours
Work hours will be coordinated with the Contracting Officer. No power disruptions are allowable during normal working hours. The Contractor will work together with the Contract Surveillance Representative for access into restricted spaces. Contracting Officer shall approve working hours prior to commencement of work. Regular working hours shall consist of an 8-hour period established by the Contracting Officer between 6 a.m. and 6 p.m., Monday through Friday, excluding Government holidays.
-- End of Scope of Work --
| 1 GENERAL INFORMATION: |
| Detailed Project Description |
| 1.2 SUBMITTALS |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |