Availability Milestone _012-24_ VBSS 11MRX1101 and 1102 Rev 3.1.docx

DOCX document 29 KB Posted

Attached to
Preservation, Hull, Mechanical, and Electrical/Electronic Repairs - VBSS 11MRX1101 and 11MRX1102
Solicitation number
N5523624R0009
Issued by

About this file

This document is an Availability Milestone schedule for the preservation, hull, mechanical, and electrical/electronic repairs of two Visit, Board, Search, and Seizure (VBSS) boats, 11MRX1101 and 11MRX1102, to be performed by a contractor. The work is scheduled from October 2024 to June 2025, with key milestones including arrival, preliminary inspection, production schedule submission, condition found reports, material procurement, and conferences at 25%, 50%, and 75% completion. The work will be performed at a contractor facility within 50 miles of the 32nd Street Naval Base in San Diego. The applicable NAICS code is 336611 Ship Building and Repairing. A sources sought notice has been issued under Solicitation Number N5523624R0009, with responses due by September 16, 2024. This is not a request for proposal, and the government will not compensate for any responses received. The work will be awarded to a small business concern along the West Coast.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Availability Milestone Ship/Craft HIN: VBSS 11MRX1101 & 1102

A. Milestones/Key Events: 270 242 248 days Availability Rev 3

Event
Scheduled Date
Start Availability (Execution)
07 Oct 2024
Receive Craft by contractor Not Later Than (NLT)
09 Oct 2024
Arrival Conference NLT
16 Oct 2024
Preliminary Inspection NLT.
15 Oct 2024

Submit Production Schedule NLT Submit Weekly Production Reports to Supervisor NLT 18 Oct 2024

Submit Condition Found Reports/Long Lead Time Materials (LLTM) NLT 20% of availability. NLT Submit Condition Found Report for identified additional materials and/or work requirement that will result of change of work requirement to be accomplish. NLT Submit Commercially Furnish Materials (CFM) NLT.

Submit Electrical Disconnect report NLT.

26 Nov 2024

Conduct 25% Conference NLT 25 percent of milestone of craft completion will be recognized all LLTM has been identified and submitted to SUPERVISOR NLT.

Submit the requirements for paint and preservation to SUPERVISOR NLT.

Trailer inspection NLT Sponson repairs NLT 08 Dec 2024

Conduct 50% Conference NLT 50 percent of milestone of craft completion will be recognized upon the completion of all structural repairs.

Engine repairs accomplished NLT.

DYNO Complete NLT.

Fuel Bladder Pressure test NLT.

12 Feb 2025

Conduct 75% Conference NLT 75 percent of milestone of craft completion will be recognized upon the completion of all preservation requirements.

Surface Preservation NLT.

16 Apr 2025

Production Completion Date.

Production work requirements in its entirety shall be completed on this date.

23 May 2025

SOW requirements Government and Contractor joint verification of completion..
27 May 2025
Preliminary Waterborne/Bay Trials (Contractor)/Correction of Discrepancies NLT.
3-4 June 2025
Final Inspection/Waterborne Trials/Bay Trials NLT
9-10 June 2025
Craft Delivery NLT.
12 June 2025

NOTES:

If any milestone is not accomplished by the date listed, and the failure to accomplish any such milestone event does not arise from a cause beyond the control and without fault or negligence of the Contractor, such failure may be deemed to constitute a failure to perform this contract in accordance with its terms within the meaning of the clause of this contract entitled “Default-Fixed-Price Supply and Service”.

Holidays:

Columbus DayOct. 14, 2024
Veteran's DayNov. 11, 2024
ThanksgivingNov. 28, 2024
ChristmasDec. 25, 2024
New Year's DayJan. 1, 2025
M. L. King DayJan. 20, 2025
President's DayFeb. 17, 2025
Memorial DayMay. 26, 2025

File details come from the government source that posted it. Updated .