Availability Milestone _012-24_ VBSS 11MRX1101 and 1102 Rev 3.1.docx
DOCX document 29 KB Posted
- Attached to
- Preservation, Hull, Mechanical, and Electrical/Electronic Repairs - VBSS 11MRX1101 and 11MRX1102
- Solicitation number
- N5523624R0009
About this file
This document is an Availability Milestone schedule for the preservation, hull, mechanical, and electrical/electronic repairs of two Visit, Board, Search, and Seizure (VBSS) boats, 11MRX1101 and 11MRX1102, to be performed by a contractor. The work is scheduled from October 2024 to June 2025, with key milestones including arrival, preliminary inspection, production schedule submission, condition found reports, material procurement, and conferences at 25%, 50%, and 75% completion. The work will be performed at a contractor facility within 50 miles of the 32nd Street Naval Base in San Diego. The applicable NAICS code is 336611 Ship Building and Repairing. A sources sought notice has been issued under Solicitation Number N5523624R0009, with responses due by September 16, 2024. This is not a request for proposal, and the government will not compensate for any responses received. The work will be awarded to a small business concern along the West Coast.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| NSW VBSS 11MRX1101 and 11MRX1102 FINAL.docx | DOCX document | |
| Availability Milestone _012-24_ VBSS 11MRX1101 1102 REV 3.docx | DOCX document | |
| Attachment-A_012-24_ VBSS 11MRX1101and 1102.docx | DOCX document | |
| Attachment-B None Applicable SSI _012-24_ VBSS 11MRX1101 and 1102.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Availability Milestone Ship/Craft HIN: VBSS 11MRX1101 & 1102
A. Milestones/Key Events: 270 242 248 days Availability Rev 3
| Event |
| Scheduled Date |
| Start Availability (Execution) |
| 07 Oct 2024 |
| Receive Craft by contractor Not Later Than (NLT) |
| 09 Oct 2024 |
| Arrival Conference NLT |
| 16 Oct 2024 |
| Preliminary Inspection NLT. |
| 15 Oct 2024 |
Submit Production Schedule NLT Submit Weekly Production Reports to Supervisor NLT 18 Oct 2024
Submit Condition Found Reports/Long Lead Time Materials (LLTM) NLT 20% of availability. NLT Submit Condition Found Report for identified additional materials and/or work requirement that will result of change of work requirement to be accomplish. NLT Submit Commercially Furnish Materials (CFM) NLT.
Submit Electrical Disconnect report NLT.
26 Nov 2024
Conduct 25% Conference NLT 25 percent of milestone of craft completion will be recognized all LLTM has been identified and submitted to SUPERVISOR NLT.
Submit the requirements for paint and preservation to SUPERVISOR NLT.
Trailer inspection NLT Sponson repairs NLT 08 Dec 2024
Conduct 50% Conference NLT 50 percent of milestone of craft completion will be recognized upon the completion of all structural repairs.
Engine repairs accomplished NLT.
DYNO Complete NLT.
Fuel Bladder Pressure test NLT.
12 Feb 2025
Conduct 75% Conference NLT 75 percent of milestone of craft completion will be recognized upon the completion of all preservation requirements.
Surface Preservation NLT.
16 Apr 2025
Production Completion Date.
Production work requirements in its entirety shall be completed on this date.
23 May 2025
| SOW requirements Government and Contractor joint verification of completion.. |
| 27 May 2025 |
| Preliminary Waterborne/Bay Trials (Contractor)/Correction of Discrepancies NLT. |
| 3-4 June 2025 |
| Final Inspection/Waterborne Trials/Bay Trials NLT |
| 9-10 June 2025 |
| Craft Delivery NLT. |
| 12 June 2025 |
NOTES:
If any milestone is not accomplished by the date listed, and the failure to accomplish any such milestone event does not arise from a cause beyond the control and without fault or negligence of the Contractor, such failure may be deemed to constitute a failure to perform this contract in accordance with its terms within the meaning of the clause of this contract entitled “Default-Fixed-Price Supply and Service”.
Holidays:
| Columbus Day | Oct. 14, 2024 |
| Veteran's Day | Nov. 11, 2024 |
| Thanksgiving | Nov. 28, 2024 |
| Christmas | Dec. 25, 2024 |
| New Year's Day | Jan. 1, 2025 |
| M. L. King Day | Jan. 20, 2025 |
| President's Day | Feb. 17, 2025 |
| Memorial Day | May. 26, 2025 |
File details come from the government source that posted it. Updated .