N5523622R0015PR
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
REF: Commercial Industrial Services (CIS) Pumps and Motors Repair – AMENDMENT 0001 The purpose of this amendment is to answ er vendors' questions See Summary of Changes.
All other terms and conditions remain unchanged.
Note: Amendment 0001 must be acknow ledged w ith submission of proposal.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 15-Aug-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N5523622R0015
X 9B. DATED (SEE ITEM 11)
08-Aug-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
15-Aug-2022
CODE
SOUTHWEST REGIONAL MAINTENANCE CENTER
CODE 410B 3755 BRINSER STREET, STE 1
SAN DIEGO CA 92136
N55236 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL: 619-556-4706 michael.t.luu.civ@us.navy.mil
N5523622R0015
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
(End of Summary of Changes)
The following items are applicable to this modification:
AMENDMENT 0001
QUESTION #1
Contractor Question: Items A016, A017, A018, A019, A020, A021 all specify to “remove existing and install new”, is the contractor required to include the new pump/motor or removing and installing GFM?
Government Answer: The Contractor shall procure and install a new pump/motor in accordance with ELINs A016, A017, A018, A019, A020, and A021 if the existing is deemed beyond repair. The Government may provide a new pump/motor to the Contractor if the damaged existing pump/motor if one is available and the Contractor cannot obtain a new pump/motor to support the contract performance dates.
QUESTION #2
Contractor Question: If access cuts or removals of soft patches are required for the removal and installation of a pump or motor, will those be captured A026 over and above? Or is contractor to assume that all require an access cut IAW 009-05?
Government Answer: The Government does not intend to overhaul/repair any pump/motor that will not go through the existing rigging routes (WTD, WTH, Escape trunk, access trunks, or passageway). Onboard shipcheck between the Government, Contractor and Ships Force shall identify the dimension of the motors/pumps slated for repair/overhaul. During the onboard shipcheck, the Government and the Contractor will identify the primary and alternate rigging route. Access cuts will be invoked in a specific Delivery Orders if the traditional rigging route will not be supported by the pump/motor dimensions. In this instance, the Government shall inform the Contractor that 009-005 shall be invoked in its entirety. The Contractor shall follow the requirements of NAVSEA Standard Item009-005 in its entirety when invoked and shall use ELIN A026AA and A026AB for estimating purposes.