Landing Craft, Air Cushion (LCAC 78) Lift Fan, Emergent Repair.
Solicitation number
N5523619R0016
Issued by

About this file

RFP N5523619R0016

View the file

Other files

File Type Posted
Attachment_J-1.pdf PDF
N5523619R0016_0001.pdf PDF
Exhibit_A_Pricing_Workbook.xlsm XLSM spreadsheet
Attachment_J-1.pdf PDF
Exhibit_B_LCAC_78_CDRL.pdf PDF
Exhibit_C_LCAC_78_GFP_11APR2019.xlsx XLSX spreadsheet
Attachment_S1_-_Reference_Information_Sheet.docx DOCX document
Exhibit_A_Pricing_Workbook.xlsm XLSM spreadsheet
Attachment_S-2_-_Request_for_Specification_Clarification_Form.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CODE

(Hour)

PAGE(S)

until 02:00 PM local time 13 May 2019

X

A

X B

X C X D

EX

X

G

F 61 - 69

70 - 80

X H 81 - 85 melissa.borja@navy .mil

RATING PAGE OF PAGES

7. ISSUED BY

(Date)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)

Prescribed by GSA

FAR (48 CFR) 53.214(c)

DO-A3 1 85

(If other than Item 7)

15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO

AND

ADDRESS

SIGN OFFER (Type or print)

OF

OFFEROR

AMENDMENT NO. DATE

15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS

IS DIFFERENT FROM ABOVE - ENTER

SUCH ADDRESS IN SCHEDULE.

18. OFFER DATE

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 700)

2. CONTRACT NO.

N55236 8. ADDRESS OFFER TO

See Item 7

9. Sealed offers in original and 1 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in

CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and

NBSD, BLDG 77, ROOM 210

conditions contained in this solicitation.

10. FOR INFORMATION

CALL:

A. NAME (NO COLLECT CALLS)

MELISSA L BORJA 6195564706

11. TABLE OF CONTENTS

SOLICITATION/ CONTRACT FORM

SUPPLIES OR SERVICES AND PRICES/ COSTS

2 - 5

X I CONTRACT CLAUSES

DESCRIPTION/ SPECS./ WORK STATEMENT X

PACKAGING AND MARKING

6 - 31

J LIST OF ATTACHMENTS

INSPECTION AND ACCEPTANCE

DELIVERIES OR PERFORMANCE

33 - 35

36 - 37 X K

REPRESENTATIONS, CERTIFICATIONS AND

OTHER STATEMENTS OF OFFERORS

CONTRACT ADMINISTRATION DATA 38 - 47 X

SPECIAL CONTRACT REQUIREMENTS

OFFER (Must be fully completed by offeror) 48 - 49 X M

L INSTRS., CONDS., AND NOTICES TO OFFERORS

EVALUATION FACTORS FOR AWARD

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. DISCOUNT FOR PROMPT PAYMENT

(See Section I, Clause No. 52.232-8)

14. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments

AMENDMENT NO. DATE

to the SOLICITATION for offerors and related documents numbered and dated):

FACILITY

12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period

SOLICITATION, OFFER AND AWARD

X

(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)

PART I - THE SCHEDULE

26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE

EMAIL:TEL: (Signature of Contracting Officer)

CODE CODE

B. TELEPHONE (Include area code) C. E-MAIL ADDRESS

AWARD (To be completed by Government)

19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)

23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE

PART IV - REPRESENTATIO NS AND INSTRUCTIO NS

PART III - LIST O F DO CUMENTS, EXHIBITS AND O THER ATTACHMENTS

50 - 59

PART II - CO NTRACT CLAUSES

SOUTHWEST REGIONAL MAINTENANCE CENTER

CODE 410 3755 BRINSER STREET, STE 1

SAN DIEGO CA 92136

(619) 556-4708

(619) 556-2331FAX:

TEL:

FAX:

TEL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SOLICITATION

6. REQUISITION/PURCHASE NO.

N5523619R0016PR

5. DATE ISSUED

12 Apr 2019

4. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

[ X ]

3. SOLICITATION NO.

N5523619R0016

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES MAX

QUANTITY

UNIT UNIT PRICE MAX AMOUNT

CLIN

Number

1 Lot

LCAC 78 FY-19 EMERGENT REPAIRS

FFP

Prepare for and accomplish the Emergent Repairs on the LCAC 78 in accordance with the LCAC 78 Emergent Repairs and Work Item Nos. 243-11-001, 248-11-

001, 248-11-004, 248-11-005, 248-11-006, and 248-12-005 (Attachment J-1), as amended.

FOB: Destination

PURCHASE REQUEST NUMBER: N5523619R0016PR

PSC CD: J999

MAX

NET AMT

ITEM NO SUPPLIES/SERVICES MAX

QUANTITY

UNIT UNIT PRICE MAX AMOUNT

CLIN

Number

1 Lot

CONTRACT DATA REQUIREMENT LIST (CDRLS)

FFP

The data to be furnished hereunder shall be prepared and submitted in accordance with the CDRL, DD Form 1423, Exhibit B and attached hereto. The CDRLS form a part of the schedule of this solicitation. Not Separately Priced (NSP).

FOB: Destination

PURCHASE REQUEST NUMBER: N5523619R0016PR

PSC CD: J999

MAX

NET AMT

CLAUSES INCORPORATED BY FULL TEXT

B-227-H001 PROVISIONING TECHNICAL DOCUMENTATION – WITHHOLDING OF PAYMENT

(NAVSEA) (OCT 2018)

(a) For the purpose of paragraph (c) of the "Progress Payments" clause of this contract, if included, the requirement that the Contractor develop and deliver Provisioning Technical Documentation (PTD) is considered to be a "material requirement of this contract," and Contractor failure to make adequate progress in the development of PTD, or to deliver acceptable PTD on a timely basis, may result in reduction or suspension of Progress Payments as provided in said paragraph.

(b) The PTD is considered to be a part of the "Technical Data" specified to be delivered under this contract for the purposes of the "Technical Data--Withholding of Payment" (DFARS 252.227-7030) clause. The terms and conditions of the clause entitled "Limitation On Withholding of Payments (FAR 52.232-9), if included in this contract, shall not apply to withholding of payment for failure to make timely delivery of the PTD or delivery of deficient PTD.

(End of text)

RMC B-2-0002 PROGRESS PAYMENT RATES (SERMC) (JULY 2016)

The progress payment rate for this contract is 90 percent for large business and 95 percent for small business in accordance with 10 USC 2307(g).

NOTE B

FIXED SHIP REPAIR LABOR AND MATERIAL BURDEN RATES FOR GROWTH AND NEW WORK

SCHEDULE OF PRICES / RATES: SHIP REPAIR LABOR RATE (FULLY BURDENED)

1. The Contractor’s fully loaded ship repair labor rate will be used for negotiating growth and new work to be performed under this contract. The contractor agrees that the number of man hours included in its price proposal for contract modifications shall include only direct production man hours. For these purposes, direct production man-hours are for skilled labor at the journeyman level expended in direct production including but not limited to the following functions:

Abrasive cleaning/blasting

Fire Watch

Welding

Burning

Brazing

Carpentry

Machinists (inside and outside)

Electrical Work

Electronic Work

Engineering

Design Support

Lagging

Ship-fitting

Boiler-making

Painting

Sheet-metal Work

Pipefitting

Rigging

General Labor

Staging/Scaffolding

Diesel Mechanics

2. The fully burdened ship repair labor rate proposed by the contractor listed in paragraph 1 above shall include all costs associated with support functions (whether charged directly or indirectly by the offeror’s accounting systems) provided in support of the direct production man hour functions listed in paragraph 1 above. Support functions shall be considered to be included in the offeror’s fully burdened ship repair labor rate for direct production man hours.

Labor hours for the below support functions shall not be separately proposed in any circumstance, including in support of subcontractors. Support functions include, and are not limited to, those types listed below:

Testing

Quality Assurance

Execution Planning

Cleaning (except tank cleaning)

Supervision

Security

Surveying

Administration

Transportation

Purchasing Staff

Lofting

Other Indirect Support

Material Handling & Warehousing

Safety/Environmental

3. The fully burdened ship repair labor rate is a fixed hourly rate that includes all wages, overhead, all other indirect costs, general and administrative expenses, Facilities Capital Cost of Money (FCCOM), and profit. The fully burdened ship repair labor rate represents a blended rate including labor transferred between divisions, subsidiaries, or affiliates of the contractor under a common control.

4. Consumable materials are goods used in the ordinary course of work performance such as office supplies, paper, rags, vehicle or equipment fuel costs, cleaning chemicals, disposable tools, welding rods, paint buckets, paint brushes, protective clothing, etc. that are consumed/used in the process of repair and do not become an integral part of the repaired vessel. Consumable material shall be included in the contractor’s fully burdened ship repair labor rate and not separately priced.

5. Physical materials are goods that become an integral part of the repaired vessel in the course of the repair, such as equipment, replacement steel, pipes, paint, and fasteners. The material burden rates apply to physical materials but not to consumable materials. The material burden rate will be applied to the actual cost of the physical material.

Actual cost does not include handling charges, general and administrative cost, overhead, profit, or any other indirect cost.

6. For contract changes involving subcontractors, subcontractor quotes will be treated as Other Direct Costs (ODCs) and will be subject to the contract material burden rate shown in paragraph (7) below. Subcontractor quotes must be competitively acquired and submitted with the contractor’s Change Order Price Analysis (COPA) in response to a

Request for Contract Change (RCC) issued by the Contracting Officer. At no time will the proposed total to be performed by the prime contractor combined with subcontractor quote, material quote, and applicable burdens be allowed to cost more than it would have, had the prime contractor directly provided all material and labor. The proposed total pricing restriction addressed in the preceding sentence does not apply in any case where the work is required to be performed by Original Equipment Manufacturers (OEMs), Government directed subcontractors, Government authorized vendors, or any other work at the sole discretion of the Administrative Contracting Officer

(ACO). RCC’s that are for material only (no associated labor required within the RCC). RCCs shall not be subject to the Material Burden Rate.

7. The contract fixed fully burdened ship repair labor rate and material burden rate are shown below. These fixed rates shall be used for negotiating growth and new work during the entire availability regardless of how many labor hours and material dollars are procured and negotiated.

Fully Burdened Ship Repair Labor Rate *

Material Burden Rate *

*TO BE FILLED IN BY OFFEROR

Section C - Descriptions and Specifications

CONTRACT LINE ITEM DESCRIPTION

ITEM 0001 Prepare for and accomplish the Emergent Repairs on the LCAC 78 in accordance with the attached

LCAC 78 Emergent Repairs and Work Item Nos. 243-11-001, 248-11-001, 248-11-004, 248-11-005, 248-11-006, 248-12-005 (Attachment J-1) and as specified herein and in accordance with standard items, work item specifications, drawings, test procedures, and other detailed data provided by the Government listed in Section J.

ITEM 0002 Contract Data Requirements List (CDRL). See section J of this solicitation (Exhibit B).

(a) NAVSEA STANDARD ITEMS have been furnished to each MSRA and ABR contractor under separate cover for retention.

(b) The current NAVSEA standard items applicable to work items of this specification are listed in the Index of

Specifications, contained in Attachment J-1.

(c) Category I Standard Items are applicable to all items without further reference. Category II Standard Items are part of this specification when invoked and/or referenced in individual work items.

The Government will provide the following:

a. Work, Storage and Service Areas:

(1) Use of Hangar Bay and all associated services listed under paragraph (c) Utility Services herein as designated by Government, if available

(2) Area for Contractor supplied services, (T-Row)

(3) Area for Contractor administration trailer (T-Row)

(4) Contractor lay down area (T-Row)

(5) Contractor material receipt area (T-Row)

b. Employee Parking: Maximum of 25 passenger-size vehicle spaces. Location will be located at the North parking of the E4 and below parking area. One project manager vehicle can be parked beside the administration trailer and must be identified with a company logo.

c. Utility Services: Water, LP air, 440 VAC, and 110 VAC is located in the vicinity of all hangars.

d. Equipment Services:

(1) Mobile Gantry Crane (Travel Lift).

(2) Overhead Bridge Crane (Hangar Bay). Operated by qualified ACU-5 personnel only.

(2) A shipset of blocks installed for each craft in hanger bay, if required.

(3) Craft Fuel Services: All craft fuel and refueling services will be provided by ACU-5.

(4) Rest Room Facilities: The Government will designate an area for Contractor installation of portable restroom facilities. ACU-5 restroom facilities are not for contractor use.

(5) Work Break/Meal Facilities Area: The Government will designate an area for Contractor installation of work break/meal areas. The contractor shall not have access to ACU-5 shops, offices, restrooms, locker rooms, or any other facilities, unless authorized by Commanding Officer, ACU-5.

e. ACU-5 will provide craft refueling services, fly-over block installation, craft travel lift operation, overhead crane support and testing and trial support including craft operation during normal working hours, 0800 - 1500, Monday through Friday. ACU 5 will not be available to provide the services listed above on weekends, Federal Holidays, the week between Christmas and New Year's Day, and the week after New Year's Day unless agreed to by the

Commanding Officer, ACU 5. At least 48 hours prior to the need for ACU 5 to provide the services identified herein, the Contractor shall request the specific services, with all necessary details, from the authorized Government representative.

STATEMENT OF WORK

SCOPE OF WORK

1. GENERAL REQUIREMENTS

1.1 The Contractor under the direction of the Southwest Regional Maintenance Center (SWRMC) and as an independent Contractor and not as an agent of the Government, shall furnish the material, support electrical, crane, rigging, etc. and facilities, except those furnished by the Government under express provisions of this contract, and provide the management, technical, procurement, production, testing, and quality assurance necessary to prepare and accomplish the repair of the LCAC 78 FY-19 Emergent Repairs and Work Item Nos. 243-11-001, 248-11-001, 248-

11-004, 248-11-004, 248-11-005, 248-11-006, and 248-12-005 in accordance with the requirements stated in this

Section, the Work Item Specifications and Work Item Plans, Drawings, and Other References, the Delivery

Schedule, and all other terms and conditions set forth in this contract. Category I NAVSEA FY19 Chg 5 Standard

Items identified under Attachment J-1 are applicable to all items without further reference. Category II

NAVSEAFY19 Chg 5 Standard Items are applicable when invoked and/or referenced in individual work items specified in Attachment J-1. See Exhibit B for applicable Contract Data Requirement List (CDRL).

1.1.1 Wherever the term “SUPERVISOR” is used in this solicitation/award, it also means “SWRMC Project

Manager” or “SWRMC Shipbuilding Specialist.”

NAVSEA Standard items may be found at:

http://www.navsea.navy.mil/Home/RMC/CNRMC/OurPrograms/SSRAC/NSI.aspx

1.2 The Contractor shall accomplish planning and scheduling to ensure a rational, integrated and timely plan for receipt, storage and installation of Government Furnished Material as identified in Work Item Specifications, and for accomplishment of production work.

1.3 The Contractor shall provide an integrated milestone plan for the availability. These milestones will include a schedule of key events necessary to meet the contract delivery dates. A critical path analysis and a milestone schedule shall be used to measure schedule accomplishment of the functions and elements required to successfully complete the repair of LCAC 78 FY-19 Emergent Repairs within the availability dates herein.

1.4 INTEGRATED PRODUCTION SCHEDULE DEVELOPMENT, UPDATE, AND REVIEWS –

1.4.1 The contractor shall develop a report listing for each Work Item of the Job Order, the Work Item number, Work Item title, scheduled start date, scheduled completion date, actual start date, and the percentage complete. The report shall address changes to the Key Events and Milestones list and major problems of Work Items, to include negative float, and proposed corrective action. The report shall reflect the addition, deletion, or modification of

Work Items. Completed Work Items need not be addressed.

1.4.2 The contractor shall participate in review conferences at the 25, 50, and 75 percent points in the availability.

Data from the most recent submission in accordance with paragraph 3.7.1 of Standard Item 009-60 will be used at the review conferences. Review conferences will be held within two days of the Weekly Progress Meeting or, subject to SWRMC LCAC Project Manager approval, may be held simultaneously with the Weekly Progress

Meeting. The conferences will be scheduled at a time and place mutually agreeable to all parties.

1.4.3 The contractor shall:

http://www.navsea.navy.mil/Home/RMC/CNRMC/OurPrograms/SSRAC/NSI.aspx

1.4.3.1 Be prepared to discuss planned production manning versus actual production manning by total, trades, and subcontractors.

1.4.3.2 Identify known factors that may affect Key Events, Milestones and the contract completion. Provide recommended courses of action to resolve problem areas.

1.4.3.3 Provide the Supervisor or designated individual with the status of open and inspect reports and be prepared to discuss possible impact of growth work in these items at the 25 percent review conference.

1.4.3.4 Provide Supervisor or designated individual the with the following information for the 50 percent review conference:

1.4.3.5 A machinery reinstallation plan showing projected dates for installing the equipment on the foundation, hook-up of the equipment, and operational tests of the equipment.

1.4.3.6 A valve status list showing projected completion and reinstallation dates.

1.4.3.7 A list of items required for the next Key Event and Production Completion Date (PCD) that are not complete. Annotate those items on the list that may be in jeopardy of completing by the next Key Event and PCD.

1.5 Wherever the term “Job Order” is used in this solicitation/award, it also means “Contract.”

1.6 The Contractor shall report and recommend corrective action during contract performance for those deficiencies discovered which are not covered by the Work Item Specifications. As found conditions including needed repairs and corrective actions will be submitted to the Government in the form of a Condition Found Report (CFR). The

CFR shall be in accordance with that set forth in Standard Item 009-01.

1.7 The Navy may send a site inspection team to perform an inspection of the contractor's facility prior to arrival of the vessel

1.8 GOVERNMENT FURNISHED MATERIAL: Government Furnished Material (GFM) cited in the solicitation will be delivered to the contractor at the Government facility. The successful offeror is to coordinate delivery, accountability, storage and transportation of Government Furnished Material with the Project Manager. Government property permanently removed from a vessel that requires a SWRMC Code 400 Property Administrator's disposition instructions shall be properly prepared for shipment and be delivered as directed by the Property Administrator.

GFM will be listed in paragraph 5 of the Work Item(s) and in Exhibit C.

1.9 QUALITY ASSURANCE

1.9.1 QUALITY ASSURANCE PROGRAM - The Contractor shall provide and maintain a quality assurance program acceptable to the Government, and shall perform or have performed the inspections and tests pursuant to that program to substantiate that the material and workmanship provided pursuant to the job order conform to the drawings, specifications, job orders, and contract requirements listed herein. The Contractor's quality assurance program shall be in accordance with that set forth in Standard Item 009-04. In addition to its rights under DFARS

252.217-7005 “Inspection and Manner of Doing Work”, the Government shall have the right to deem work or material furnished by the Contractor to be incomplete and not in accordance with the requirements of the job order by reason of the Contractor's failure to comply with the requirements of its quality assurance program and, as such, the Contractor shall not be entitled to progress payments for said work and material.

1.10 IDENTIFICATION OF CONDITION FOUND - In accordance with the requirements of NAVSEA Standard

Item 009-01, the contractor shall identify needed repairs and recommend corrective action during contract performance for work/deficiencies discovered which are not covered by the existing work package. For conditions to impact the critical path(s) /controlling item(s), the contractor shall notify the government via electronic media within 24-hours of discovery. This initial notification need not include all content required for a Condition Found

Report (CFR), but must include a description of the condition/deficiency and an estimated timeframe for the offeror's professional recommendation for resolution, which shall not exceed five (5) working days as specified below. Recommended repairs and corrective actions shall be submitted to the Government in the form of a CFR

(intended to represent the "Work Request" described in DFARS 252.217-7028 “Over and Above Work”).

1.10.1 CONDITION FOUND NOTIFICATION TO GOVERNMENT

CFRs shall be submitted via email (dj.brandt@navy.mil) within five (5) working days of discovery of the condition

(or 24 hours for conditions impacting critical paths).

At a minimum, the CFR will include the following:

(1) Identify contract, ship, and hull number

(2) Serialized by CFR number

(3) Identification of the applicable Work Item number

(4) Date requirement was discovered

(5) Description of the work requirement

(6) Specific location of the work

(7) Recommendation for corrective action

(8) Recommendation for the appropriate/best time to accomplish the work (i.e. during current availability with or without schedule change, future CNO, or Continuous Maintenance Availability). Provide supporting rationale for the recommendation, such as cost efficiencies, availability of work force, availability of material, premium expenditures, etc.

(9) Identification of related changes, if any, to the internal milestones and production and contract completion dates.

1.10.2 GOVERNMENT REVIEW AND RESPONSE TO CFR

The Maintenance Team will review the CFR. If the CFR is inadequate or incomplete, it will be rejected with time continuing to accrue (relative to five (5) working day requirement/24 hour requirement). As appropriate, the

Government and contractor will need to meet, conduct ship checks, and/or discuss the recommendation for corrective action further to determine the full scope of work required prior to final approval of the CFR. The contractor's accuracy reflected in the CFRs submitted may be evaluated in CPARS and utilized for past performance ratings on future requirements.

1.11 REQUEST FOR CONTRACT CHANGE (RCC)

In the event a growth requirement or new work is validated and fully scoped, the Government may generate a

Request for Contract Change (RCC) which the ACO may request a firm fixed price proposal from the contractor.

The contractor shall provide all Change Order Price Analysis (COPA) proposals to the ACO in response to RCCs within seven (7) calendar days. A contractor’s COPA shall remain valid for a minimum of fourteen (14) calendar days, unless otherwise specified on an individual RCC by the ACO; if another timeline is specified by the

Government on an individual RCC, the contractor’s COPA shall remain valid for that amount of time. A COPA addressing a change to the FFP contract shall include at a minimum:

a. Labor hours to be performed by the Prime Contractor __________

b. Subcontractor Quote (if applicable) * $__________

c. Material Quote (if applicable)** $__________

d. Mark-up (if applicable) $__________

*Subcontractor quotes shall include labor hours, labor rate, material (part number, description, unit cost, quantity, total cost, and vendor quotes for each line item), and tiered subcontractor quotes (if applicable).

** Material quote shall include the part number, description, unit cost, quantities, total cost, and vendor quotes for each line item.

Note 1: Labor hours for both prime and subcontract shall be provided broken down by trade and labor mix.

Note 2: The required documentation must accompany the COPA for the COPA to be considered submitted to the

ACO.

If circumstances arise where the contractor is unable to submit a COPA within seven (7) calendar days, the contractor shall notify the ACO in writing of the specific circumstances and provide a revised date in which a COPA proposal will be submitted. Additional time needed to complete a COPA may be granted solely at the discretion of the ACO. The new timeframe granted, solely at the discretion of the ACO, may differ from the contractor’s request, but shall be met by the contractor.

1.12 ORGANIZATION CHART AND EMPLOYEE ROSTER:

1.12.1 EMPLOYEE ROSTER: After receipt of award and prior to starting work aboard the vessel, the contractor must submit a list of employees who will work aboard ship to the Commanding Officer of the ship via the SWRMC

Security Office. The list should be on company letterhead, include each employee's name and security clearance when required, and bear the signature of a company official.

2. LOCATION: Camp Pendleton, CA, ACU-5.

3. SCHEDULE: LCAC 78/FY-19 Emergent Repairs must be delivered, mission-ready, no later than 02 AUG 2019.

3.1: MILESTONES

3.1.1 If any milestone event is not accomplished by the date provided, and the failure to accomplish any such milestone event does not arise from a cause beyond the control and without fault or negligence of the Contractor, such failure may be deemed to constitute a failure to perform this contract in accordance with its terms within the meaning of subparagraph (a)(1)(ii) of the clause of this contract entitled "DEFAULT” (DFARS 252.217-7009).

3.1.2 The Contractor shall schedule the performance of all items in the LCAC 78 FY-19 Emergent Repairs work package, including work items included as both Base and Option items (if applicable), so as to permit up to a 25% scope increase to be performed as "Additional Requirements" (including growth and new work). The Government will track the contract scope increase by calculating the increase in labor hours of growth and new work as a percentage against labor hours proposed in the basic work package. The contractor agrees that these Additional Requirements, if ordered, shall be performed concurrently with the aforementioned work items, during the contract period of performance, without impacting, accelerating, or causing delay or disruption to the work required by the aforementioned work items, to any other Government contract, or to any other work in progress for the Government.

The "Additional Requirements," if required, shall be ordered during the contract period of performance, as may be modified, on the following schedule:

• No more than 75% of the hours or material following the 25% schedule point the availability (as measured in days between the “Start Availability” and “End of Availability”).

• No more than 50% of the hours or material following the 50% schedule point the availability (as measured in days between the “Start Availability” and “End of Availability”).

• No more than 25% of the hours or material following the 75% schedule point the availability (as measured in days between the “Start Availability” and “End of Availability”).

3.2. DELAYS / DISRUPTIONS: The contractor shall coordinate the work effort with the SWRMC LCAC Project

Manager on a daily basis to prevent changing situations from causing delays and disruptions. Disruption due to minor delays in obtaining access to spaces and operation of equipment are to be expected. A minor delay is defined as eight (8) hours or less. These disruptions are considered normal rather than unusual occurrences during the performance of tasks ordered under this contract. If, during contract performance, delays greater than those indicated above are encountered, the Contractor shall immediately verbally notify the Project Manager and Contracting

Officer, followed by a written statement within twenty-four (24) hours after occurrence of delay, stating time of impact, reason for delay, duration of impact, number of people affected, action taken to properly schedule the work, action taken to minimize impact, and the names of the Government person(s) contacted.

4. SAFETY:

4.1 SAFETY INSPECTOR / FIRE MARSHALL: In addition to the safety standards provided in the specifications, the contractor is responsible for providing an experienced Safety Inspector/Fire Marshall who will accomplish daily inspections for the duration of the availability of the Contractor's entire work area on the ship, together with the

Contracting Office’s Safety Representative. This Inspector or Fire Marshall shall not be one of the Contractor's supervisors or superintendents normally assigned to the ship and shall be identified in the contractor’s approved

Safety Plan.

4.2 PERSONAL PROTECTIVE EQUIPMENT: Whenever work is performed aboard U.S. Naval Ships or vessels at piers or dry docks of a Naval Shipyard or Naval Station, Contractor employees (including management personnel) shall have and use at all times the following personal protective equipment:

(a) Protective hard hats that meet the following specifications:

(1) Protective helmets purchased after July 5, 1994 shall comply with ANSI Z89.1-1986, "American National

Standard for Personnel Protection-Protective Headwear for Industrial Workers-Requirements," or shall be demonstrated to be equally effective.

(2) Protective helmets purchased before July 5, 1994 shall comply with ANSI Standard "American National

Standard Safety requirements for Industrial Head Protection," Z89.1-1969, or shall be demonstrated by the employer to be equally effective. [Ref. 29 CFR 1910.135 Head Protection]

(b) Approved type Plano or prescription glasses meeting the following specifications:

(1) Protective eye and face devices purchased after July 5, 1994 shall comply with ANSI standard Z87.1-1989, "American National Standard Practice for Occupational and Educational Eye and Face Protection", or shall be demonstrated by the employer to be equally effective.

(2) Protective eye and face devices purchased before July 5, 1994 shall comply with ANSI "USA standard for

Occupational and Educational Eye and Face Protection", Z87.1-1968, or shall be demonstrated by the employer to be equally effective. [Ref. 29 CRF 1910.133 Protective eye and face devices.]

(c) Safety toe shoes, with built-in protective toe box that meet the following specifications:

(1) Protective footwear purchased after July 5, 1994 shall comply with ANSI Standard Z41-1991, "American

National Standard for Personal Protection-Protective Footwear", or shall be demonstrated by the employer to be equally effective.

(2) Protective footwear purchased before July 5, 1994 shall comply with the ANSI standard "USA Standard for

Men's Safety Toe Footwear", Z41.1 1967, or shall be demonstrated by the employer to be equally effective [Ref. 29

CFR 1910.136 Protective eye and face devices.]

4.3 BLACK OXIDE COATED THREADED FASTENERS (BOCTFs): Due to safety concerns, use of BOCTFs is not authorized when installing or replacing threaded fasteners in the accomplishment of any work required by any

Work Item in this contract.

4.4 Force Protection Condition - The Navy is currently in force protection condition Alpha. The contactor shall fully comply with the requirements of NAVSEA Standard items 009-72(Physical Security at a Private contractor facility:

accomplish), to include armed water borne security. Any costs associated with delays, disruptions, or security precautions associated with this force protection condition level shall be included in your proposal. Contractors will not receive additional compensation for delays, disruptions, or security precautions associated with this force protection condition level.

4.5. Preservation Requirements: In accordance with NAVSEA Standard Items 009-32 (Cleaning and Painting

Requirements). The contractor shall consider marine coatings and abrasive blasting media to contain heavy metals

(e.g., beryllium, cadmium) chromium, or lead, hexavalent chromium, crystalline silica and/or other toxic or hazardous substances).

5. OTHER REQUIREMENTS

5.1 USE/POSSESSION OF PERSONAL ELECTRONIC DEVICES (PED'S) - The possession and use of portable electronic devices (PED's) within the confines of any naval vessel, or in the contractor's facility where equipment removed from the vessel is being worked, is strictly controlled. Cellular phones with digital imaging capabilities are strictly prohibited. PED's may not be connected to any Navy-owned or controlled network. PED's may not be used to store or process any digital information associated with the conduct of the contract without written authorization from the Naval Supervising Activity (NSA). PED's include:

• mobile computing devices such as personal digital assistants (PDA's);

• hand-held or laptop computers;

• mobile telephone devices such as data-enabled cellular telephones;

• two-way pagers, including those with e-mail capability;

• analog and digital sound recorders; and

• digital cameras, including cellular phones with digital imaging capabilities.

5.2 NON SMOKING POLICY - For bidding purposes, contractors are advised that in light of the Navy's policy regarding smoke-free facilities, the entire vessel, topside and below decks, is to be considered a "No Smoking Area" unless otherwise indicated by shipboard policy.

5.3. CITIZENSHIP REQUIREMENTS - The contractor shall comply with the Department of Defense Industrial

Security Manual (DoD 5220.22), and any revisions to that manual as of the Bid Opening Date prescribed, for verification of all U. S. Citizens. Prospective offerors shall refer all questions pertaining to the above to NSA, Security Manager. The DoD Industrial Security Manual can be found at:

http://www.dtic.mil/whs/directives/corres/pdf/522022_vol3_2014.pdf

6. MISCELLANEOUS

6.1 All references to technical volume(s) includes the Contractor’s non-price proposal.

C-202-H001 ADDITIONAL DEFINITIONS–BASIC (NAVSEA) (OCT 2018)

(a) Department - means the Department of the Navy.

(b) Commander, Naval Sea Systems Command - means the Commander of the Naval Sea Systems Command of the

Department of the Navy or his duly appointed successor.

(c) References to The Federal Acquisition Regulation (FAR) - All references to the FAR in this contract shall be deemed to also reference the appropriate sections of the Defense FAR Supplement (DFARS), unless clearly indicated otherwise.

(d) National Stock Numbers - Whenever the term Federal Item Identification Number and its acronym FIIN or the term Federal Stock Number and its acronym FSN appear in the contract, order or their cited specifications and standards, the terms and acronyms shall be interpreted as National Item Identification Number (NIIN) and National

Stock Number (NSN) respectively which shall be defined as follows:

http://www.dtic.mil/whs/directives/corres/pdf/522022_vol3_2014.pdf

(1) National Item Identification Number (NIIN). The number assigned to each approved Item

Identification under the Federal Cataloging Program. It consists of nine numeric characters, the first two of which are the National Codification Bureau (NCB) Code. The remaining positions consist of a seven digit non-significant number.

(2) National Stock Number (NSN). The National Stock Number (NSN) for an item of supply consists of the applicable four-position Federal Supply Class (FSC) plus the applicable nine-position NIIN assigned to the item of supply.

C-211-H001 ACCESS TO THE VESSEL(S) (NAVSEA) (OCT 2018)

Officers, employees and associates of other prime Contractors with the Government and their subcontractors, shall, as authorized by the Supervisor, have, at all reasonable times, admission to the plant, access to the vessel(s) where and as required, and be permitted, within the plant and on the vessel(s) required, to perform and fulfill their respective obligations to the Government. The Contractor shall make reasonable arrangements with the Government or Contractors of the Government, as shall have been identified and authorized by the Supervisor to be given admission to the plant and access to the vessel(s) for office space, work areas, storage or shop areas, or other facilities and services, necessary for the performance of the respective responsibilities involved, and reasonable to their performance.

C-211-H004 HEAVY WEATHER PLAN (NAVSEA) (OCT 2018)

(a) In order to ensure that Naval vessel(s), material and Government property are protected during destructive weather such as gales, storms, hurricanes, high winds, heavy snow, ice and high water, the Contractor is required to have a written Heavy Weather Plan (HWP) which assigns responsibilities and prescribes actions to be taken on the approach of and during heavy weather conditions as delineated in NAVSEA Standard Item (SI) 009-69 dated 18 November 2016. A copy of Standard Item (SI) 009-69 can be obtained from via the internet by going to:

http://www.navsea.navy.mil/Home/RMC/CNRMC/OurPrograms/SSRAC/NSI/ and selecting the NAVSEA Standard

Items (NSI) tab then select the applicable FY standard item link and then select SI 009-69. In accordance with SI 009-

69, the Contractor shall furnish to the cognizant Regional Maintenance Center (RMC), a copy of such HWP, and shall make such changes in the plan as the RMC considers necessary and reasonable to protect and care for vessel(s), material and Government property.

(b) In the event the RMC directs the Contractor to implement the HWP pursuant to SI 009-69 the Contractor may submit to the Contracting Officer a request for reimbursement for costs resulting from such actions together with any documentation that the Contracting Officer may reasonably require. The Government shall reimburse the Contractor for all reasonable, allowable and allocable costs resulting from the Contractor's implementation of the HWP based on such

Government direction.

http://www.navsea.navy.mil/Home/RMC/CNRMC/OurPrograms/SSRAC/NSI/

C-211-H008 QUALIFICATION OF CONTRACTOR NON-DESTRUCTIVE TESTING (NDT) PERSONNEL

(a) The Contractor and any Non-destructive Testing (NDT) subcontractor shall utilize for the performance of required NDT, only Level I, II and III personnel currently certified in accordance with NAVSEA Technical

Publication T9074-AS-GIB-010/271, Revision 1 of 11 September 2014. Documentation pertaining to the qualification and certification of NDT personnel shall be made available to the Contracting Officer for review upon request.

(b) These requirements do not apply with respect to nuclear propulsion plant systems and other matters under the technical cognizance of the Office of Navy Nuclear Propulsion (NAVSEA 08). Because of health and safety considerations, such matters will continue to be handled as directed by NAVSEA 08.

C-211-H016 SPECIFICATIONS AND STANDARDS (NAVSEA) (OCT 2018)

(a) Definitions.

(i) A "zero-tier reference" is a specification, standard, or drawing that is cited in the contract (including its attachments).

(ii) A "first-tier reference" is either: (1) a specification, standard, or drawing cited in a zero-tier reference, or (2) a specification cited in a first-tier drawing.

(b) Requirements. All zero-tier and first-tier references, as defined above, are mandatory for use. All lower tier references shall be used for guidance only unless specifically identified below.

None

C-211-H017 UPDATING SPECIFICATIONS AND STANDARDS (NAVSEA) (DEC 2018)

The contractor may request that this contract be updated to include the current version of the applicable specification or standard if the update does not affect the form, fit or function of any deliverable item or increase the cost/price of the item to the Government. The contractor should submit update requests to the Procuring Contracting Officer with copies to the Administrative Contracting Officer and cognizant program office representative for approval. The contractor shall perform the contract in accordance with the existing specifications and standards until notified of approval/disapproval of its request to update by the Procuring Contracting Officer. Any approved alternate specifications or standards will be incorporated into the contract.

C-211-H018 APPROVAL BY THE GOVERNMENT (NAVSEA) (JAN 2019)

Approval by the Government as required under this contract and applicable specifications shall not relieve the

Contractor of its obligation to comply with the specifications and with all other requirements of the contract, nor shall it impose upon the Government any liability it would not have had in the absence of such approval.

C-211-H020 PROTECTION OF THE VESSEL (NAVSEA) (MAR 2019)

(a) The Contractor shall exercise reasonable care, as agreed upon with the Supervisor, to protect the vessel from fire, and shall maintain a system of inspection over the activities of its welders, burners, riveters, painters, pipe fitters, and similar workers, and of its subcontractors, particularly where such activities are undertaken in the vicinity of the vessel's magazines, fuel oil tanks, or store rooms containing inflammable materials. All ammunition, fuel oil, motor fuels, and cleaning fluids shall have been off-loaded and the tanks cleaned, except as may be mutually agreed upon between the Contractor and the Supervisor prior to work on the vessel by the Contractor. Fire hose lines shall be maintained by the Contractor ready for immediate use on the vessel at all times while the vessel is berthed alongside the Contractor's pier or in dry dock. All tanks under alteration or repair shall be cleaned, washed, and steamed out or otherwise made safe to the extent necessary, and the Contractor shall furnish the vessel's Gas Free

Officer and the Supervisor with a "Gas Chemists' Certificate" before any hot work is done. The Contractor shall maintain a fire watch aboard the vessel in areas where the Contractor is working. All other fire watches aboard the vessel shall be the responsibility of the Government.

(b) Except as otherwise provided in contractually invoked technical specifications or NAVSEA furnished directives, while the vessel is at the Contractor's plant and when the temperature becomes as low as thirty-five degrees Fahrenheit, the Contractor shall assist the Government when requested in keeping all pipe-lines, fixtures, traps, tanks, and other receptacles on the vessel drained to avoid damage from freezing, or if this is not practicable, the vessel shall be kept heated to prevent such damage. The vessel's stern tube and propeller hubs shall be protected by the Contractor from frost damage by applied heat through the use of a salamander or other proper means.

(c) The work shall, whenever practicable, be performed in such manner as not to interfere with the work performed by military personnel attached to the vessel, and provisions shall be made so that personnel assigned shall have access to the vessel at all times, it being understood that such personnel will not unduly interfere with the work of the Contractor's workmen.

(d) The Contractor shall at all times keep the site of the work on the vessel free from accumulation of waste material or rubbish caused by its employees, or the work performed by the Contractor in accordance with this contract, and at the completion of such work shall remove all rubbish from and about the site of the work, and shall leave the work in its immediate vicinity "broom clean", unless more exactly specified by the Supervisor.

(End of Text)

C-215-H002 CONTRACTOR PROPOSAL (NAVSEA) (OCT 2018)

(a) Performance of this contract by the Contractor shall be conducted and performed in accordance with the detailed obligations to which the Contractor committed itself in Proposal dated in response to Solicitation No.

N5523619R0016.

(b) The technical volume(s) of the Contractor's proposal is(are) hereby incorporated by reference and made subject to the "Order of Precedence" (FAR 52.215-8) clause of this contract. Under the "Order of Precedence" clause, the technical volume(s) of the Contractor's proposal referenced herein is (are) hereby designated as item (f) of the clause, following

"the specifications" in the order of precedence.

C-217-H005 GROWTH AND NEW WORK (NAVSEA) (JAN 2019)

(a) The Contractor is required to notify the Contracting Officer via email regarding growth and new work within 30 days of discovery:

(1) of any apparent errors or omissions in the contract (SF 33, specifications, drawings, etc.); and,

(2) of any/all conflicts between the contract package and actual conditions observed during ship check(s) and/or contract execution.

(b) Growth work is synonymous with over and above work, which is described in DFARS 252.217-7028, Over and

Above Work and it provides the process for adjudication.

(c) New work is distinguished from over and above work and is outside the scope of the competitively procured requirement. New work will be approved in accordance with FAR Part 6 and associated policies and procedures.

(d) The Government will NOT negotiate modifications to increase the contract price to address errors or omissions to the contract package which were reasonably apparent to the contractor prior to proposal submission.

C-222-H001 ACCESS TO THE VESSELS BY NON-U.S. CITIZENS (NAVSEA) (OCT 2018)

(a) No person not known to be a U.S. citizen shall be eligible for access to naval vessels, work sites and adjacent areas when said vessels are under construction, conversion, overhaul, or repair, except upon a finding by

COMNAVSEA or his designated representative that such access should be permitted in the best interest of the

United States. The Contractor shall establish procedures to comply with this requirement and NAVSEAINST

5510.3 (series).

(b) If the Contractor desires to employ non-U.S. citizens in the performance of work under this contract or agreement that requires access as specified in paragraph (a) of this requirement, approval must be obtained prior to access for each contract or agreement where such access is required. To request such approval for non-U.S. citizens of friendly countries, the Contractor shall submit to the cognizant Contract Administration Office (CAO), an Access

Control Plan (ACP) which shall contain as a minimum, the following information:

(1) Badge or Pass oriented identification, access, and movement control system for non-U.S. citizen employees with the badge or pass to be worn or displayed on outer garments at all times while on the Contractor's facilities and when performing work aboard ship.

(i) Badges must be of such design and appearance that permits easy recognition to facilitate quick and positive identification.

(ii) Access authorization and limitations for the bearer must be clearly established and in accordance with applicable security regulations and instructions.

(iii) A control system, which provides rigid accountability procedures for handling lost, damaged, forgotten or no longer required badges, must be established.

(iv) A badge or pass check must be performed at all points of entry to the Contractor's facilities or by a site supervisor for work performed on vessels outside the Contractor's plant.

(2) Contractor's plan for ascertaining citizenship and for screening employees for security risk.

(3) Data reflecting the number, nationality, and positions held by non-U.S. citizen employees, including procedures to update data as non-U.S. citizen employee data changes, and pass to cognizant CAO.

(4) Contractor's plan for ensuring subcontractor compliance with the provisions of the Contractor's ACP.

(5) These conditions and controls are intended to serve as guidelines representing the minimum requirements of an acceptable ACP. They are not meant to restrict the Contractor in any way from imposing additional controls necessary to tailor these requirements to a specific facility.

(c) To request approval for non-U.S. citizens of hostile and/or communist-controlled countries (listed in Department of Defense Industrial Security Manual, DOD 5220.22-M or available from cognizant CAO), Contractor shall include in the ACP the following employee data: name, place of birth, citizenship (if different from place of birth), date of entry to U.S., extenuating circumstances (if any) concerning immigration to U.S., number of years employed by

Contractor, position, and stated intent concerning U.S. citizenship. COMNAVSEA or his designated representative will make individual determinations for desirability of access for the above group. Approval of ACP's for access of non-U.S. citizens of friendly countries will not be delayed for approval of non-U.S. citizens of hostile communist-controlled countries. Until approval is received, Contractor must deny access to vessels for employees who are non-

U.S. citizens of hostile and/or communist-controlled countries.

(d) The Contractor shall fully comply with approved ACPs. Noncompliance by the Contractor or subcontractor serves to cancel any authorization previously granted, in which case the Contractor shall be precluded from the continued use of non-U.S. citizens on this contract or agreement until such time as the compliance with an approved

ACP is demonstrated and upon a determination by the CAO that the Government's interests are protected. Further, the Government reserves the right to cancel previously granted authority when such cancellation is determined to be in the Government's best interest. Use of non-U.S.