Pricing Workbook_Exhibits A-F.xls
XLS spreadsheet 72 KB Posted
- Solicitation number
- N5523619R0010
About this file
This pricing workbook contains estimates for labor, materials, storage, transportation and tug services required under the Navy Expeditionary Combat Craft (NECC) Indefinite Delivery, Indefinite-Quantity (IDIQ) contract solicitation number N5523619R0010. The estimates are provided for each of the potential five base years of the contract and include approximately 48,532 manhours of labor and escalating estimates for materials and services each year, ranging from $10,122,454.72 for the first base year to $11,267,403.00 for the fifth base year. Offerors are instructed to include their material handling fee rates in highlighted cells. The solicitation is for NECC repairs and industrial support services and is issued by the Department of the Navy Naval Sea Systems Command. The total estimate provided across the five potential base years is $53,432,351.07.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N5523619R0010_0007.pdf | ||
| N5523619R0010_0006.pdf | ||
| N5523619R0010-0005.pdf | ||
| N5523619R0010-0004 - SIGNED.pdf | ||
| Pricing Workbook_Exhibits A-F_Rev3.xls | XLS spreadsheet | |
| N5523619R0010-0003 - SIGNED.pdf | ||
| Pricing Workbook_Exhibits A-F_Rev2.xls | XLS spreadsheet | |
| N5523619R0010_0002- signed.pdf | ||
| Pricing Workbook_Exhibits A-F_Rev1.xls | XLS spreadsheet | |
| N5523619R0001 Amendment 0001.pdf | ||
| Attachment-A.docx | DOCX document | |
| Attachment S2 - Request for Specification Clarification Form.doc | DOC document | |
| RFP N5523619R0010 NECC.pdf | ||
| Attachment J-1 Small Boat Listing NECC.docx | DOCX document | |
| Attachment S1 - Reference Information Sheet.docx | DOCX document | |
| Exhibit G - CDRLs.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NECC - BASE
| EXHIBIT A | Prime Contractor | |||||
| Supplies/Services | Est Qty | Unit | Unit | |||
| Price | Amount | |||||
| A001 | LABOR & MATERIALS | |||||
| LABOR | 48,532 | MH | $0.00 | |||
| MATERIALS | $ 9,122,454.72 | U.S. DOLLARS | $9,122,454.72 | |||
| A002 | Boat Storage / Lay day up to 50 feet | 50 | DAYS | $0.00 | ||
| A003 | Boat Storage / Lay day 50 feet to 78 feet or in length | 40 | DAYS | $0.00 | ||
| A004 | Boat Lift from water to blocks up to 50 feet | 40 | EA | $0.00 | ||
| A005 | Boat Lift from water to blocks from 50 feet to 78 feet in length and back to the water. | 40 | EA | $0.00 | ||
| A006 | Trailer/Haul boat/trailer from San Diego Naval Facilities area to Contractor's Facility, shorter than 30 ft. | 50 | EA | $0.00 | ||
| A007 | Trailer/Haul boat/trailer from Contractor's Facility to San Diego area Naval Facilities area, shorter than 30 ft. | 40 | EA | $0.00 | ||
| 0008 | Trailer/Haul boat/trailer from San Diego area Naval Facilities area to Contractor's Facility, 30 ft. to 50 ft. | 50 | EA | $0.00 | ||
| A009 | Trailer/Haul boat/trailer from Contractor's Facility to San Diego area Naval Facilities area, 30 ft o 50 ft. | 40 | EA | $0.00 | ||
| A010 | Provide Tug Services from San Diego Naval failities to Contractors facility for crafts 50 feet to 78 feet. | 40 | EA | $0.00 | ||
| A011 | Provide Tug Services from Contractors facility to San Diego Naval Failities to for crafts 50 feet to 78 feet. | 40 | EA | $0.00 | ||
| A012 | Contract Data Requirements (Form DD-1423) | NSP | ||||
| A013 | OVER AND ABOVE WORK - NECC, BASE YEAR | |||||
| LABOR | 12,500 | MH | $0.00 | |||
| OT LABOR | 11,250 | MH | $0.00 | |||
| MATERIALS | 1,000,000 | U.S. DOLLARS | $1,000,000.00 | |||
| Total Estimate for Base Year | $10,122,454.72 | |||||
| OFFEROR: Please be sure to include your Material Handling Fee Rate in the Yellow, Highlighted boxes. |
NECC - BASE 2
| EXHIBIT B | Prime Contractor | |||||
| Supplies/Services | Est Qty | Unit | Unit | |||
| Price | Amount | |||||
| B001 | LABOR & MATERIALS | |||||
| LABOR | 48,532 | MH | $0.00 | |||
| MATERIALS | $ 9,396,128.35 | U.S. DOLLARS | $9,396,128.35 | |||
| B002 | Boat Storage / Lay day up to 50 feet | 50 | DAYS | $0.00 | ||
| B003 | Boat Storage / Lay day 50 feet to 78 feet or in length | 40 | DAYS | $0.00 | ||
| B004 | Boat Lift from water to blocks up to 50 feet | 40 | EA | |||
| B005 | Boat Lift from water to blocks from 50 feet to 78 feet in length and back to the water. | |||||
| B006 | Trailer/Haul boat/trailer from San Diego Naval Facilities area to Contractor's Facility, shorter than 30 ft. | 50 | EA | $0.00 | ||
| B007 | Trailer/Haul boat/trailer from Contractor's Facility to San Diego area Naval Facilities area, shorter than 30 ft. | 40 | EA | $0.00 | ||
| B008 | Trailer/Haul boat/trailer from San Diego area Naval Facilities area to Contractor's Facility, 30 ft.to 50 ft. | 50 | EA | $0.00 | ||
| B009 | Trailer/Haul boat/trailer from Contractor's Facility to San Diego area Naval Facilities area, 30 ft o 50 ft. | 40 | EA | $0.00 | ||
| B010 | Provide Tug Services from San Diego Naval failities to Contractors facility for crafts 50 feet to 78 feet. | 40 | EA | $0.00 | ||
| B011 | Provide Tug Services from Contractors facility to San Diego Naval Failities to for crafts 50 feet to 78 feet. | 40 | EA | $0.00 | ||
| B012 | Contract Data Requirements (Form DD-1423) | NSP | ||||
| B013 | OVER AND ABOVE WORK - NECC, BASE YEAR 2 | |||||
| LABOR | 12,500 | MH | $0.00 | |||
| OT LABOR | 11,250 | MH | $0.00 | |||
| MATERIALS | 1,000,000 | U.S. DOLLARS | $1,000,000.00 | |||
| Total Estimate for Base Year 2 | $10,396,128.35 | |||||
| OFFEROR: Please be sure to include your Material Handling Fee Rate in the Yellow, Highlighted boxes. |
NECC - BASE 3
| EXHIBIT C | Prime Contractor | |||||
| Supplies/Services | Est Qty | Unit | Unit | |||
| Price | Amount | |||||
| C001 | LABOR & MATERIALS | |||||
| LABOR | 48,532 | MH | $0.00 | |||
| MATERIALS | 9,678,012 | U.S. DOLLARS | $9,678,012.00 | |||
| C002 | Boat Storage / Lay day up to 50 feet | 50 | DAYS | $0.00 | ||
| C003 | Boat Storage / Lay day 50 feet to 78 feet or in length | 40 | DAYS | $0.00 | ||
| C004 | Boat Lift from water to blocks up to 50 feet | 40 | EA | |||
| C005 | Boat Lift from water to blocks from 50 feet to 78 feet in length and back to the water. | |||||
| C006 | Trailer/Haul boat/trailer from San Diego Naval Facilities area to Contractor's Facility, shorter than 30 ft. | 50 | EA | $0.00 | ||
| C007 | Trailer/Haul boat/trailer from Contractor's Facility to San Diego area Naval Facilities area, shorter than 30 ft. | 40 | EA | $0.00 | ||
| C008 | Trailer/Haul boat/trailer from San Diego area Naval Facilities area to Contractor's Facility, 30 ft. to 50 ft. | 50 | EA | $0.00 | ||
| C009 | Trailer/Haul boat/trailer from Contractor's Facility to San Diego area Naval Facilities area, 30 ft o 50 ft. | 40 | EA | $0.00 | ||
| C010 | Provide Tug Services from San Diego Naval failities to Contractors facility for crafts 50 feet to 78 feet. | 40 | EA | $0.00 | ||
| C011 | Provide Tug Services from Contractors facility to San Diego Naval Failities to for crafts 50 feet to 78 feet. | 40 | EA | $0.00 | ||
| C012 | Contract Data Requirements (Form DD-1423) | NSP | ||||
| C013 | OVER AND ABOVE WORK - NECC, BASE YEAR 3 | |||||
| LABOR | 12,500 | MH | $0.00 | |||
| OT LABOR | 11,250 | MH | $0.00 | |||
| MATERIALS | 1,000,000 | U.S. DOLLARS | $1,000,000.00 | |||
| Total Estimate for Base Year 3 | $10,678,012.00 | |||||
| OFFEROR: Please be sure to include your Material Handling Fee Rate in the Yellow, Highlighted boxes. |
NECC - BASE 4
| EXHIBIT D | Prime Contractor | |||||
| Supplies/Services | Est Qty | Unit | Unit | |||
| Price | Amount | |||||
| D001 | LABOR & MATERIALS | |||||
| LABOR | 48,532 | MH | $0.00 | |||
| MATERIALS | 9,968,353 | U.S. DOLLARS | $9,968,353.00 | |||
| D002 | Boat Storage / Lay day up to 50 feet | 50 | DAYS | $0.00 | ||
| D003 | Boat Storage / Lay day 50 feet to 78 feet or in length | 40 | DAYS | $0.00 | ||
| D004 | Boat Lift from water to blocks up to 50 feet | 40 | EA | |||
| D005 | Boat Lift from water to blocks from 50 feet to 78 feet in length and back to the water. | |||||
| D006 | Trailer/Haul boat/trailer from San Diego Naval Facilities area to Contractor's Facility, shorter than 30 ft. | 50 | EA | $0.00 | ||
| D007 | Trailer/Haul boat/trailer from Contractor's Facility to San Diego area Naval Facilities area, shorter than 30 ft. | 40 | EA | $0.00 | ||
| D008 | Trailer/Haul boat/trailer from San Diego area Naval Facilities area to Contractor's Facility, 30 ft. to 50 ft. | 50 | EA | $0.00 | ||
| D009 | Trailer/Haul boat/trailer from Contractor's Facility to San Diego area Naval Facilities area, 30 ft o 50 ft. | 40 | EA | $0.00 | ||
| D010 | Provide Tug Services from San Diego Naval failities to Contractors facility for crafts 50 feet to 78 feet. | 40 | EA | $0.00 | ||
| D011 | Provide Tug Services from Contractors facility to San Diego Naval Failities to for crafts 50 feet to 78 feet. | 40 | EA | $0.00 | ||
| D012 | Contract Data Requirements (Form DD-1423) | NSP | ||||
| D013 | OVER AND ABOVE WORK - NECC, BASE YEAR 4 | |||||
| LABOR | 12,500 | MH | $0.00 | |||
| OT LABOR | 11,250 | MH | $0.00 | |||
| MATERIALS | 1,000,000 | U.S. DOLLARS | $1,000,000.00 | |||
| Total Estimate for Base Year 4 | $10,968,353.00 | |||||
| OFFEROR: Please be sure to include your Material Handling Fee Rate in the Yellow, Highlighted boxes. |
NECC - BASE 5
| EXHIBIT E | Prime Contractor | |||||
| Supplies/Services | Est Qty | Unit | Unit | |||
| Price | Amount | |||||
| E001 | LABOR & MATERIALS | |||||
| LABOR | 48,532 | MH | $0.00 | |||
| MATERIALS | 10,267,403 | U.S. DOLLARS | $10,267,403.00 | |||
| E002 | Boat Storage / Lay day up to 50 feet | 50 | DAYS | $0.00 | ||
| E003 | Boat Storage / Lay day 50 feet to 78 feet or in length | 40 | DAYS | $0.00 | ||
| E004 | Boat Lift from water to blocks up to 50 feet | 40 | EA | $0.00 | ||
| E005 | Boat Lift from water to blocks from 50 feet to 78 feet in length and back to the water. | 40 | EA | $0.00 | ||
| E006 | Trailer/Haul boat/trailer from San Diego Naval Facilities area to Contractor's Facility, shorter than 30 ft. | 50 | EA | $0.00 | ||
| E007 | Trailer/Haul boat/trailer from Contractor's Facility to San Diego area Naval Facilities area, shorter than 30 ft. | 40 | EA | $0.00 | ||
| E008 | Trailer/Haul boat/trailer from San Diego area Naval Facilities area to Contractor's Facility, 30 ft. to 50 ft. | 50 | EA | $0.00 | ||
| E009 | Trailer/Haul boat/trailer from Contractor's Facility to San Diego area Naval Facilities area, 30 ft o 50 ft. | 40 | EA | $0.00 | ||
| E010 | Provide Tug Services from San Diego Naval failities to Contractors facility for crafts 50 feet to 78 feet. | 40 | EA | $0.00 | ||
| E011 | Provide Tug Services from Contractors facility to San Diego Naval Failities to for crafts 50 feet to 78 feet. | 40 | EA | $0.00 | ||
| E012 | Contract Data Requirements (Form DD-1423) | NSP | ||||
| E013 | OVER AND ABOVE WORK - NECC, BASE YEAR 5 | |||||
| LABOR | 12,500 | MH | $0.00 | |||
| OT LABOR | 11,250 | MH | $0.00 | |||
| MATERIALS | 1,000,000 | U.S. DOLLARS | $1,000,000.00 | |||
| Total Estimate for Base Year 5 | $11,267,403.00 | |||||
| OFFEROR: Please be sure to include your Material Handling Fee Rate in the Yellow, Highlighted boxes. |
SUMMARY
| EXHIBIT F | ||
| SUMMARY | ||
| NECC | BASE YEAR | $ 10,122,454.72 |
| NECC | BASE YEAR 2 | $ 10,396,128.35 |
| NECC | BASE YEAR 3 | $ 10,678,012.00 |
| NECC | BASE YEAR 4 | $ 10,968,353.00 |
| NECC | BASE YEAR 5 | $ 11,267,403.00 |
| TOTAL | $ 53,432,351.07 |
File details come from the government source that posted it. Updated .