Attachment S-3 - Past Performance Questionnaire

View the file

Other files

File Type Posted
AMEND_03.pdf PDF
N55236-16-R-0020_Amendment_2.pdf PDF
S2_-_Management_&_Technical_Experience.docx DOCX document
Amen_1_Non-Complex_Solicitation.pdf PDF
S3_-_Past_Perf_Questionnaire.docx DOCX document
N55236-16-R-0020_SOLICITATION.docx DOCX document
Section_J_-_Exhibits_A B _ _C.zip ZIP file
J1-_Labor_and_Material_Price_Sheet_KTR_non-Complex.xlsx XLSX spreadsheet
Section_J_-_Attachements_S2 _S3_and_S4.zip ZIP file
CDRLB7.pdf PDF
A011.pdf PDF
J1-_Labor_and_Material_Price_Sheet_KTR_non-Complex.xlsx XLSX spreadsheet
A001.pdf PDF
A006.pdf PDF
A012_.pdf PDF
A009.pdf PDF
S-4_Pre-Proposal_Information_Form.docx DOCX document
A003.pdf PDF
S-4_Pre-Proposal_Information_Form.docx DOCX document
CDRLB1.pdf PDF
A008.pdf PDF
CDRLB8.pdf PDF
CDRLB9.pdf PDF
CDRLC2.pdf PDF
A007.pdf PDF
CDRLB6.pdf PDF
CDRLB5.pdf PDF
CDRLC1.pdf PDF
A014.pdf PDF
A002.pdf PDF
S2_-_Management_&_Technical_Experience.docx DOCX document
A005.pdf PDF
CDRLB3.pdf PDF
J1-_Labor_and_Material_Price_Sheet_KTR_non-Complex.xlsx XLSX spreadsheet
CDRLB4.pdf PDF
CDRLB2.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment S-3

PAST PERFORMANCE QUESTIONNAIRE

Instructions to Offeror: The Offeror shall complete PARTS I, II and III of this questionnaire. The Offeror shall then provide a copy of the partially completed questionnaire to the points of contact it identifies in PART II a. and instruct them to complete PART IV of the questionnaire and forward the questionnaire, by the proposal due date, to:

SOUTHWEST REGIONAL MAINTENANCE CENTER

ATTN: SWRMC 410B Joaquin Alvarez), CONTRACT SPECIALIST SWRMC 3755 Brinser Street, Suite 1 San Diego, CA 92136

SOLICITATION NUMBER: N55236-16-R-0020

DO NOT OPEN IN MAIL ROOM

Or email to: Joaquin Alvarez, SWRMC 410B , joaquin.alvarez@navy.mil

THE GOVERNMENT WILL ONLY EVALUATE A PAST PERFORMANCE QUESTIONNAIRE IF PARTS I, II, III AND IV HAVE BEEN COMPLETED AND SUBMITTED TO THE ABOVE ADDRESS. ALL PARTS OF THE PAST PERFORMANCE QUESTIONNAIRE SHOULD BE SUBMITTED TO THE ADDRESS ABOVE BY THE PROPOSAL DUE DATE. FAILURE OF THE CUSTOMER TO SUBMIT THE PAST PERFORMANCE QUESTIONAIRE TO THE NAVAL SEA SYSTEMS COMMAND, AS ADDRESSED ABOVE, WITHIN THE REQUESTED TIMEFRAME MAY RESULT IN THE INABILITY OF THE GOVERNMENT TO EVALUATE THAT PAST PERFORMANCE QUESTIONNAIRE. IN THE EVENT THAT A QUESTIONNAIRE IS SUBMITTED AFTER THE SOURCE SELECTION EVALUATION BOARD (SSEB) HAS COMPLETED ITS PAST PERFORMANCE EVALUATION THEN THAT PARTICULAR QUESTIONNAIRE WILL NOT BE EVALUATED. ALL PAST PERFORMANCE INFORMATION SUBMITTED BY THE OFFEROR SHALL BE PROVIDED TO THE GOVERNMENT USING THE PAST PERFORMANCE QUESTIONAIRE.

The Offeror may submit up to five (5) questionnaires. PARTS I, II, and III of any questionnaire shall not exceed three (3) pages. The Offeror shall also submit the last (in the case of a completed contract) or latest (in the case of an on-going contract) Cost Performance Report (CPR) for each cost-type contract questionnaire with their proposal. FAILURE TO SUBMIT A CPR FOR EACH APPLICABLE CONTRACT MAY RESULT IN THE OFFEROR’S PROPOSAL BEING DEEMED UNACCEPTABLE AND MAY THEREFORE NOT BE CONSIDERED FOR AWARD.

PART I: Title of Past Performance Effort and Identification of Performing Activity

a. Assign a tracking number to this questionnaire; e.g. Number 1 of 5 questionnaires prepared.

b. Provide an Offeror point of contact and phone number for the administrative handling of this questionnaire.

c. Provide a contract number and short title that encompasses the work that was performed.

d. Provide the company name, address, zip code, technical and management points of contact, and phone number of the performing activity.

PART II: Customer Information

a. Provide the customer name, address, zip code and phone number for the following individuals:

Contracting Officer Name:

Program Manager Name:

b. Provide the Contract Number.

c. Identify the type of Contract.

d. Identify the Period of Performance.

e. Summarize the scope of work and the responsibilities of the Contractor.

f. Explain the status of the contract.

g. Explain the relevancy to the complex emergent, scheduled, continuous maintenance, modernization, and repair requirements for Surface Combatant (CG and DDG) / Amphibious (LPD, LSD, LHA, and LHD) class ships.

h. Provide the DUNS number and CAGE code of the Offeror to enable the Government to conduct accurate searches in the PPIRS database.

PART III: Contractor’s Self-Assessment

It is incumbent upon the Offeror to explain the relevance of the data provided to complex emergent, scheduled, continuous maintenance, modernization, and repair requirements for Surface Combatant (CG and DDG) / Amphibious (LPD, LSD, LHA, and LHD) class ships.

a. Explain the schedule performance (award date, the contractually required delivery date(s), the actual delivery date(s) and explanations for differences in actual and contractually required delivery dates).

b. Explain the technical performance (explain in detail any performance shortcomings or customer dissatisfaction, such as CPARS evaluations.)

c. Explain the cost/price at award, the cost/price at completion or in the case of on-going efforts, and the estimated cost/price at completion. Provide an explanation for any differences in the cost/price at award and the cost/price at completion. Provide an explanation for any overruns and a summary of all CPRs.

d. Explain in detail any significant subcontracting/teaming required to successfully perform the contract.

PART IV: Customer Satisfaction

The following is to be completed by the offices of the cognizant Contracting Officer and Program Manager. For the areas identified below, please use the following ratings:

a. Exceptional: Performance meets contractual requirements and exceeds many to the Government's benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.

b. Very Good: Performance meets contractual requirements and exceeds some to the Government's benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor was effective.

c. Satisfactory: Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

d. Marginal: Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented.

e. Unsatisfactory: Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains a serious problem(s) for which the contractor's corrective actions appear or were ineffective.

f. Not Applicable (N/A): Please indicate if performance is Not Applicable in the comments section of each assessment elements.

Assessment Elements: Please select/circle the appropriate performance assessment value for each item on the questionnaire and provide supporting narrative.

a. Cost Control: Rate the contractor’s effectiveness in forecasting, managing, and controlling cost (including reporting and analyzing variances) and ability to deliver at the agreed-to cost/price. Provide reasons for changes to the contract value (e.g., scope changes, overrun/underrun, Government-imposed schedule changes).

Exceptional
Very Good
Satisfactory
Marginal
Unsatisfactory

Comments:

b. Schedule: Rate the contractor’s ability to deliver according to the agreed-to schedule. What were the causes of any schedule variances?

Exceptional
Very Good
Satisfactory
Marginal
Unsatisfactory

c. Technical Performance: Ability to overcome technical challenges by applying sound engineering principles, complete required engineering analyses, and develop adequate technical reports and plans.

Exceptional
Very Good
Satisfactory
Marginal
Unsatisfactory

d. Quality: Rate the contractor’s ability to provide a product or service that met your required level of quality.

Assess the contractors conformance to contract requirements, specifications, and standards of good workmanship (e.g., commonly accepted technical, professional, environmental, or safety and health standards.)

Exceptional
Very Good
Satisfactory
Marginal
Unsatisfactory

e. Subcontract Management: Rate the contractor’s ability to meet the goals of the subcontracting plan, to include the ability to timely award and manage subcontracts. Please describe the offerors success in meeting planned goals and/or efforts made to overcome goal deficiencies and challenges as well as the offeror’s ability to successfully manage and integrate subcontractors.

Exceptional
Very Good
Satisfactory
Marginal
Unsatisfactory

f. Business Relations: Rate the contractor’s ability to integrate and coordinate all activities needed to execute the contract, specifically the timeliness, completeness, quality of problem resolution, corrective action plans, the contractor’s history of reasonable and cooperative behavior, customer satisfaction, and ability to submit accurate invoices in a timely manner.

Exceptional
Very Good
Satisfactory
Marginal
Unsatisfactory

g. Management of Key Personnel: Assess the contractor’s performance in selecting, retaining, supporting, and replacing, - when necessary – key personnel.

Exceptional
Very Good
Satisfactory
Marginal
Unsatisfactory

h. Evaluate conditional, provisional, or late delivery in which consideration was provided back to the Government.

Exceptional
Very Good
Satisfactory
Marginal
Unsatisfactory

i. Recommendation: To what extent would you recommend this contractor for additional contracts? Rate on the scale: 5 = Yes, definitely; 4 = Yes, likely; 3 = Maybe, 2 = No, not likely; 1 = No, not ever; 0 = N/A.

5
4
3
2
1
0

Comments:

Comments from: [ ] Contracting Office and [ ] Program Office

Reviewing Activity:

Name/Title of reviewer:

Phone number:

Signature/Date

Concur by:

Name/Title:

Signature/Date