Bidder’s Questions (Part 2)
N50054-21-Q-0079
USS Laboon Pre-SRA Offload
7. Q: Will we need any equipment on the ship, or will crane and forklift be set-up on dock or pier?
A: Pier only
8. Q: Are we expected to be available to offload on their schedule for this entire period of time, or are we in charge of the schedule as long as it is completed within this timeframe?
A: Yes, the work will need to be coordinated with the ship as they are working with NAVFAC for the transportation of some of the material. The timeframe has been established for accomplishment- to allow for this schedule integration to occur as required.
9. Q: What is heaviest load to be lifted? (Items 3.1 and 3.2 weights are not listed)
A: There will be no lift greater than 7,000 lbs.
10. Q: Are there manufacturer recommended rigging points on the equipment to be lifted?
A: Yes, there are specific lift points for the antennas and directors. Government personnel will assist with that compliance.