The document provided contains the Government's responses to five questions related to a Request for Comment (RFC) for the Maintenance, Repair, and Preservation of YT-808 ROH solicitation. The key details are:
The solicitation is for a firm-fixed-price contract to perform maintenance, repair, and preservation on the YT-808 Harbor Tug, which has the following characteristics: 90 FT length, 38 FT width, 16 FT draft, 494 LT displacement, 438 L Tons Light Load, 4 years old, and steel hull. The work will take place at a contractor facility located in the Puget Sound, WA region, defined as the West Coast of the continental US from Olympia, WA to Bellingham, WA. The period of performance is scheduled for 19 December 2024 to 18 March 2025. This is a 100% Small Business set-aside under NAICS code 336611, with a size standard of 1,300 employees. The Government will transport the vessel to the contractor's facility, and upon completion, the Government will take custody of the vessel.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Government Responses to RFC 01-05 N4523A24R1068 YT-808 ROH
01) Question: What is the docking plan and general arrangement?
Response: Docking plan drawing (8774050 Rev 2) is listed in the original SOW and included in the drawings package. REV 5 of the General Arrangement (8775054 Rev 5) was not included in the SOW.
Amendment 0001 addresses this change and includes and updated SOW to include Errata 1.
02) Question: What is the hull type?
Response: The hull is steel. See section 1.1 on the SOW.
03) Question: Would the Government consider expanding the area of performance to include the Vancouver region?
Response: No as the YT-808 is not able to go in the open ocean.
04) Question: Will another opportunity for a ship check be available before bids are due?
Response: Amendment 0002 is to add another ship check date. The vessel will be available for another ship check on August 27.
05) Question: Would the Government consider adjusting the period of performance to commence in March 2025, rather than conclude in March 2025?
Response: The Government is unable to accommodate adjustment of period of performance.