REQUEST FOR CLARIFICATION
N4523A18R0002
Attachment J-3
DATE OF REQUEST: 10-23-17 QUESTION NO: 2
REQUIREMENT: YC-800 and 804
REQUISITION NO.: N4523A18R0002
ITEM NO: 3.5
TITLE: Main deck repairs
PSNS&IMF CONTRACTS POC & PHONE:
See POCs listed on RFP.
PARA. NO: 3.5.1 – 3.5.4 PAGE NO: CONTRACTOR:
PLANNER’S NAME: ATTACH. NO: CONTRACTOR POC & PHONE:
CONTRACTOR QUESTION: (ONE QUESTION PER PAGE)
In reference to YC-800, can you supply a drawing that shows the main deck fittings?
DO NOT WRITE BELOW THIS LINE
SPEC CHG: No DWG/REF CHG: No RQMTS CHG: No MAT'L CHG: No
TECHNICAL REVIEW: SERIAL NO:
No additional drawings available. Ship check can provide more details. Ship check date is 01 NOV 2017 at Naval Base Kitsap (Bremerton); Pier “Delta”, 0830 to 1130.
ALL RFCs MUST BE RECEIVED NO LATER THAN 2:00 P.M. (PST), 6 November 2017.