AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to incorporate Statement of Work ERRATA #1 as found in Section C Summary of Changes.
All other terms and conditions remain the same.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 50
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 22-Jan-2016
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4523A-16-R-0006
X 9B. DATED (SEE ITEM 11)
05-Jan-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
22-Jan-2016
CODE
PUGET SOUND NAVAL SHIPYARD CODE 400
1400 FARRAGUT
CONTRACTING CODE 440
BREMERTON WA 98314-5001
N4523A 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4523A-16-R-0006
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been modified:
STATEMENT OF WORK
Statement of Work Statement (SOW) ERRATA 1
1.0 General Requirements: This document invokes the requirements applicable to the docking and maintenance work to be performed on one each LCM (3). Work performed and accomplished shall be in accordance with the highest quality workmanship standards and practices commonly accepted in the commercial marine industry and the technical references listed herein. The Contractor is responsible for understanding and complying with all requirements specified herein. The requirements listed herein work in conjunction with the technical drawings and other references to describe the essential features, functions, and requirements of the work performed.
1.1 Vessel Characteristics:
MK 3 15 METER WORK BOAT 9207 Built by GULF COPPER MFR CORP.
Length: 50 FT Draft: 3 FT
Width: 14 FT – 5 IN Full Displacement: 41.4LT
Age: [ 22 YRS Light Load 22.5 LT
Hull Type: Steel
1.2 Scope Overview: Coordinate with the Contracting Officer, via the Contracting Officer’s Representative (COR) to deliver the vessel from Puget Sound Naval Shipyard Bremerton to the Contractor’s facility. Dock the vessel. Wash, and clean the exterior surfaces of the vessel upon docking. Remove existing fender material and pusher pads from hull, sweep blast and preserve. Replace damaged fender sections. Replace hull zinc anodes. Blast, inspect and preserve the Hull and void covers. Power Tool clean and spot preserve the Engine Room Bilge, Lazarette and Void areas. Replace Main Deck and Catwalk Non-Skid. Accomplish an Ultrasonic test (UT) measurement and visual inspection (VT) of the hull. Open, Clean, Pump, maintain clean and dry each tank/void. Inspect tanks/Voids for defects. Air-test each Tank/void and Skeg. Identify each Tank/Void. Accomplish a final closure inspection of each tank/void upon completion of all work. Install new tank gaskets and fasteners. Replace watertight door and hatch gaskets. Remove and repair propulsion shafting, shaft bearings, seals, rudder and propeller. Perform steering system inspection and repairs. Inspect hull docking drain plugs and Skeg drain plugs. Manufacture and install labels. Undock the vessel. Arrange and coordinate the delivery of the vessel back to the Government with the Contracting Officer via the COR.
1.3 Definitions: As used throughout this Specification, the following definitions and terms have meanings as indicated:
1.3.1 Unless otherwise stated, “as shown”, “as indicated”, “as detailed”, or other words of similar import refer to the contractual documents including reference documents and publications.
1.3.2 The words “as directed”, “as approved”, “when authorized” or words of similar import refer to the direction, requirements, permission, approval, or acceptance by the Contracting Officer.
1.3.3 The term “Objective Quality Evidence” (OQE) shall mean current, accurate, and complete objective documentation and information submitted together as a complete data package sufficient that a qualified and disinterested third party could analyze, evaluate, and formulate an opinion as to whether technical requirements were achieved.
1.3.4 Where “in accordance with Regulatory Body requirements” is stated, the industrial efforts shall be in accordance with the appropriate commercial regulatory body requirements unless otherwise authorized by the Government.
1.3.5 The term “Code 400 or C400”, as used in the Specifications, means Puget Sound Naval Shipyard and Intermediate Maintenance Facility (PSNS & IMF), Code 400, Northwest Regional Maintenance Center (NWRMC) Industry Management (IND MAN) Department, Contracting Officer and/or designated Contracting Officer’s Representative
(COR).
1.3.6 The term “marine” or “marine quality” means an item constructed of materials unaffected by moisture, sea spray, extremes in temperature or other hazards of the marine environment, and designed and constructed to perform its intended functions under marine operating conditions.
1.3.7 The term “herein” means the applicable section(s) of this Specification.
1.3.8 The term “NAVSEA” means the Naval Sea Systems Command, one of five system commands, responsible for engineering, building, supporting, and maintaining the Navy’s fleet of vessels.
1.4 Care of Vessel: The Contractor shall be responsible for the care of vessel equipment, materials, and components related to the work being performed. Each vessel shall be kept free of chips, shavings, refuse, dirt, scrap materials, welding slag, and other extraneous materials. Piping ends shall be covered with appropriate covers to prevent system contamination. Open areas in structure shall be covered to prevent water entry. Tanks and voids opened shall be clean, dry, and pass Government inspection prior to being closed. Do not operate or utilize existing, newly installed , or repaired shipboard equipment for or in the performance of the Contractor’s work effort.
Ship’s Force will accomplish such operation when required for test and checkout purposes. Appropriate temporary protective measures shall be taken to avoid wear and damage and to prevent corrosion and deterioration of the vessel. Water shall not be allowed to accumulate in the hull or structure during work performance. Vessel shall be maintained in a broom clean condition on a daily basis. Vessel shall be broom clean and with all preservation coatings fully cured prior to final delivery to the Government.
1.5 Workmanship: Workmanship provided by Contractor employees shall be consistent with the highest standards of commercial marine practices and regulatory bodies. The Government reserves the right to accept or reject material and workmanship nonconformance. Noncompliance with Contractor’s quality control processes will influence past performance rating provided on contract evaluation.
Plating and structural member cuts shall be neatly and accurately made with edges cleaned and prepared for welding. Sharp edges shall be ground smooth to avoid injury to personnel. Equipment, machinery and associated support systems shall not leak oil, water or other type of fluids. Machinery and equipment shall be protected against weather hazards. Machinery, equipment and electrical cables shall be protected against accidental movement or shifting in exposed locations.
1.5.1 At the time of delivery, work performed shall meet the performance requirements specified. In the event that deficiencies are discovered during the Warranty period, an opportunity will be afforded the Contractor to witness, inspect and comment on such deficiencies. Materials and articles used for work performed shall be of commercial marine quality, conforming to the requirements of the Regulatory Bodies listed herein, unless specified to be otherwise.
1.5.2 The decision that an area is inaccessible shall be determined by inspection and agreed to by the COR prior to proceeding with the requirements of the SOW.
1.6 Arrival Conference: The Government will arrange an arrival conference with the Contractor at a Code 400 facility after contract award and prior to start of production work. The Contractor shall submit the following information 5 working days after contract award:
1.6.1 List of all subcontractors with extent of work to be accomplished by each subcontractor.
1.6.2 List of manufacturer’s Technical Representatives to be provided per the particular specification requirement.
1.6.3 List of Contractor’s NFPA Marine Chemist certifying gas-free conditions for this project and a list identifying Contractor employees designated as “Competent Persons” in accordance with 29 CFR 1915.7, including date trained.
1.6.4 Welder Qualification List, with name, type of qualification(s) and date of last qualification test for each qualification and a list of qualified silver brazers.
1.6.5 Material Safety Data Sheets (MSDS) for all materials to be used by the Contractor to accomplish the requirements of this contract.
1.6.6 List of key Contractor personnel with names, positions, telephone, and fax numbers, e-mail addresses and emergency contact information.
1.6.7 Copy of the Contractor’s Inspection and Quality Control System with copies of all related forms, reports, and other supporting documentation.
1.6.8 Copy of Contractor’s Property Administration Program for Government Furnished Equipment (GFE) or Material (GFM) including copies of all related forms and reports.
1.6.8.1 The Contractor’s Property Administration Program shall be accepted and approved for adequacy only by the Code 400 Property Administrator, Sandie Betts, at (360) 476-4205.
1.6.9 Copy of Contractor’s Environmental Protection and Hazardous Waste Management Plan, including Risk Management/Mitigation plans specific to this contract.
1.6.10 Copy of required federal, state and local environmental notifications and permits for performance of the work (or a schedule of when they will be obtained).
1.6.11 Contractor’s production performance and material ordering schedules.
1.7 Corrective Action Request (CAR): The Contractor is solely responsible for implementation of the Inspection and Quality Control System submitted in 1.6.7.
Government observer(s) will monitor production work performed at any time or at any facility where work is ongoing. If, during the performance of work, the Government observer(s) witness work that fails to meet the specifications or would lead to an unsatisfactory end product the observer will alert the Contracting Officer and advise the Contractor of the deficiency. If the deficient work is not corrected within a reasonable amount of time (determined by the Contracting Officer’s Representative) the Contractor will be issued a Corrective Action Request (CAR) and shall respond in writing within 48 hours of CAR receipt to the Contracting Officer concerning the corrective action taken to remedy the issue and prevent future occurrences.
1.8 Progress Meetings: Weekly progress meetings shall be held at the Contractor’s facility near the vessel. The day and time of the meeting shall be set by the COR upon consultation with the Contractor. A review of percentage completion for each work item shall be conducted including the Contractor’s assessment of schedule adherence.
Production schedule, corrective action reports, material lead times and other issues shall be discussed.
1.9 Interferences: Contractor pricing offered shall include removal and re-installation of all interferences associated with performance of the required work. The fact that interference is not shown on a plan or specifically identified in the specification item is not justification for a contract change. A physical check of each work site prior to bid submittal is strongly encouraged.
1.10 Safety Requirements: Comply with the requirements of 29 CFR Part 1915, 29 CFR 1910, and 29 CFR Part 1926, state and local laws, rules, and ordinances during contract performance and as follows:
1.10.1 General: Contractor shall be responsible for the compliance of the above requirements by all subcontractor personnel performing work related to this contract. In cases of conflict between the above regulations, the stricter of the requirements shall take precedence.
1.10.2 Accidents and Injuries: Report injuries to Contractor and subcontractor employees immediately to the COR. A written report of the incident shall be submitted within 24 hours of investigation completion. Written report shall include narratives of the circumstances leading up to and including the injury and any actions (immediate and contemplated) taken to mitigate future reoccurrences of injuries.
1.10.3 Scaffolding: PSNS & IMF has established additional standards above the OSHA minimum requirements when PSNS & IMF personnel are required to access or work from any scaffolding and associated ladders. These additional requirements are hereby invoked and are applicable to Contractor assembled scaffolding and ladders at any location where PSNS & IMF personnel administer the contract. Scaffolds and ladders shall meet the requirements of 29 CFR 1910.27, 29 CFR 1910.28 and as follows:
1.10.3.1 Install a swinging gate guardrail at the entrance to each scaffold ladder access opening(s) and each through-platform access opening(s).
1.10.3.1.1 Install standard railing around the non-access sides and a swinging gate guardrail on the entrance side of through-platform access openings.
1.10.3.1.2 Install standard toe-boards around all scaffold floor openings, except at the entrance to the swinging gate guardrail, on all exposed sides of through-platform access openings.
1.10.3.2 Install each ascending ladder section with a landing platform and with each ladder section platform in an offset position from the previous or adjacent ladder section for heights above 21 feet. Position each ladder perpendicular to each landing or work platform to the greatest extent practicable.
1.10.3.3 Install commercial scaffolding that is configured and designed by a qualified person when OSHA, ANSI, and manufacturers’ designed guidelines exist.
Construct, load, and maintain scaffolding in accordance with the qualified person’s design.
1.10.3.4 Develop detailed engineered drawings and specifications for scaffolds when OSHA, ANSI, or manufacturers’ designed guidelines do not exist, such as for “hanging scaffolding”. Drawings and specifications shall be designed by a registered professional engineer and meet the following:
1.10.3.4.1 Maintain on the jobsite a copy of the detailed
engineering drawings and specifications showing the sizes and spacing of members and the calculations developed for the engineered design(s).
1.10.3.4.2 Construct, load, and maintain scaffolding in
accordance with the registered professional engineer’s design.
1.10.3.5 Install a commercially available scaffold tag system on all scaffolds. The tagging system, as a minimum, shall be prominently attached to the scaffold structure, consist of green colored “Okay to Use” tag(s), red colored “Danger” tag(s), and accomplish the following:
1.10.3.5.1 Ensure that only qualified Competent Person’s
apply tags;
1.10.3.5.2 Ensure that any scaffolds not properly tagged shall not be used;
1.10.3.5.3 Apply all tags on the scaffold structure as close as practicable to each ladder access and/or entry point;
1.10.3.5.4 Apply a red tag to indicate to users that the
scaffold is being dismantled, is not yet completely erected, or for some reason is unsafe for use;
1.10.3.5.5 Apply a green tag to indicate to users that the
scaffold is safe for use and is compliant with all OSHA regulations and other applicable requirements;
1.10.3.5.6 Ensure green tags contain the following
information as a minimum: the location of the scaffolding structure; a unique reference number to identify each separate scaffolding structure, if necessary; the date the scaffolding structure was first erected; the name(s) of the scaffold builder(s); the load rating of the scaffold structure; and the Competent Person’s printed name and signature.
1.11 Hot Work/Welding: Prior to performance of any hot work/welding on the vessel, certify a safe atmosphere exists in and around the work area before starting any work that may produce the heat of ignition, sparks or flame. Accomplish necessary steps in order to make the area safe for hot work. A copy of the gas free certification shall be posted at the work site for the entire period that personnel entry into and around the work area is required.
1.11.1 All welding equipment and materials shall comply with the applicable requirements of American National Standards Institute/American Welding Society (ANSI/AWS) D1.1, Structural Welding Code, Steel and American Bureau of Shipping (ABS) requirements. Welding shall be sequenced to keep the thermal expansion of structures to a minimum.
1.11.2 Perform visual, radiographic, ultrasonic, magnetic particle or dye penetrant inspection of welds, to determine conformance, in accordance with the requirements of American Society for Testing and Materials (ASTM) International. All welds shall be 100 percent visually inspected. All boundary integrity welds shall be 100 percent visually inspected and tested to the appropriate nondestructive testing method.
All defects shall be repaired in accordance with approved procedures. All welders shall be certified by the Contractor’s AWS welding qualification program.
1.11.3 Submit one legible drawing or sketch of each proposed access cut and a list of each proposed bolted/riveted access removal to the COR and GDO (Government Docking Observer) 3 working days prior to making any cut or removing any bolted/riveted access. Submittals are not required where access cuts are authorized per a NAVSEA approved drawing. Drawing or sketch shall contain, as a minimum, the following:
1.11.3.1 Describe the temporary access closure or enclosure.
1.11.3.2 Develop a plan and elevation view specifying the location of the access by deck, frame, and distance from the center line or deck edge including measurement and location of adjacent penetrations, bulkheads, framing, welds, and riveted joints within 12-inches of the proposed cuts.
1.11.3.3 Identify the location and number of previous cuts visible in each plate and the cutback of existing welds.
1.11.3.4 Identify structural reinforcement required to prevent distortion of the vessels structure.
1.11.3.5 Identify the thickness and type of material of plating and structural members to be cut. Identify the source or document/drawing number identifying the material requirements, if possible.
1.11.3.6 Identify by positive methods any structural member, interference, and compartment boundary(s) on the opposite side of the proposed access cut or bolted/riveted access.
1.11.3.7 Furnish a copy of the weld procedure or identify the
Government approved weld procedure number on/with the drawing or sketch.
1.11.3.8 Furnish all drawing titles, numbers, and technical
documentation used to accomplish the requirements of 1.11.3.
1.12 Threaded Fasteners: Except as otherwise specified herein, or on the drawings listed, threaded fasteners shall be in accordance with applicable ASTM standards.
Coarse thread series shall be used unless the component’s design indicates a necessity to use fine thread series. Hole diameters for mounting bolts shall not exceed the diameters produced using standard size drill bits. Brass and cadmium plated fasteners are prohibited. Where drawings specify the use of brass fasteners on a fuel or fuel oil tank, CRES 304 fasteners shall be substituted in lieu of brass. Consult the requirements of MIL-STD-777 and Naval Ships’ Technical Manual (NSTM) Chapter 075 (S9086-CJ- STM-010) for guidance in instances where there is a question as to the material to be utilized.
1.12.1 Threads on externally threaded fasteners, after being installed and tightened, shall protrude a minimum of 2 threads to a maximum of 5 threads beyond the top of the nut with the exception of minimum thread protrusion for self-locking (plastic insert) nut installations. For those installations, bolt or stud end minimum thread protrusion shall be flush with the face of the nut. For self-locking nuts, the bolt or stud end shall protrude a maximum of 5 threads beyond the top of the nut after the nut is tightened.
1.12.2 Clean, chase, and tap exposed threaded areas of each fastener and threaded socket.
1.12.3 Tighten threaded fasteners in the sequence, patterns, and the torque values, when not otherwise specified, using the requirements of Section 4, paragraph 075-4.1 through 075-4.6.2 of NSTM Chapter 075 for guidance.
1.13 Environmental and Hazardous Waste Management: Comply with all federal, state, and local laws, codes, regulations, acts, ordinances, and rules for Environmental Protection and Hazardous Waste Management / Disposal, including obtaining required licenses, generator identification number, and permits. Designate One employee responsible for Environmental and Hazardous Waste Management. Provide copies of all hazardous waste manifest forms, signed by the owner or operator of the disposal facility to the COR within 30 days of project completion. All contract, manifests, invoices, and other documents related to the removal, storage, handling, transportation or disposal of hazardous waste shall bear a generator identification number issued to the Contractor pursuant to applicable law. Provide a report to the COR identifying type, amount, and disposal cost of waste that was removed as part of the required performance of this contract. The report shall include the chemical analysis method used to identify the waste and state whether the waste was hazardous (with generator identification number) or non-hazardous. Take actions to mitigate creation of hazardous waste by recycling and other available methods. All hazardous waste generated by work under this contract is anticipated to be Contractor generated and shall be the responsibility of the Contractor. Estimated hazardous waste associated with work required in these Specifications is listed below:
Product Amount
Techtyl # 894 (cold) or 435 (hot) Rust Preventive Compound
200 gallons
Cleaning Solvents 50 gallons
Paint (enamel, latex, epoxy, thinners, oil based, rubber, non-skid, lacquer, varnishes, removers)
100 gallons
Rags (contaminated with a known source) 100 pounds
Blast Media and paint chips possibly contaminated with heavy metals and other contaminants
20,000 pounds
Tank water possibly contaminated with heavy metals and other contaminants
600 gallons
Solids possibly contaminated with heavy metals and other contaminants
100 pounds
Hazardous waste generated during the actual performance of the work may vary in type or amount from the waste listed above. The above is an estimate of the amount of waste anticipated to be generated; not an estimate of the amount of work in generating that waste.
1.13.1 The Contractor shall ensure that their cost proposal for the work proposed herein includes reasonable compensation for all anticipated cost of managing and disposing of the wastes listed above, and/or created or generated in the execution of the delivery order issued, in accordance with the requirements of 42 USC 6901-6992 Rev 1996, 49 USC 5103, 10 USC 7311 Rev 1/22/02. The Contractor shall include a 5-way break down of the anticipated costs associated with this effort in their offer.
Pursuant to the requirements of Paragraph (b) of 10 USC 7311 Rev 1/22/02, total cost greater or less than the above dollar amount when authorized by the Contracting Officer will be the subject of an equitable adjustment.
1.13.2 Consider marine coatings to contain heavy metals (e.g. lead, chromium, cadmium), hexavalent chromium, crystalline silica, and/or other toxic or hazardous substances until laboratory analysis establishes otherwise. Comply with all procedures and precautions required for employee protection, sampling, removal, and disposal.
1.13.3 Consider insulation, lagging, and mastics to be asbestos-containing material (ACM) until it can be established by laboratory analysis, or other reliable method(s), that the material does not contain asbestos. Ensure compliance with the requirements of 29 CFR 1915.1001.
1.13.4 Consider materials, debris, and/or residue associated with ventilation systems to contain toxic/hazardous substances including but not limited to cadmium, chromium, and PCB’s until laboratory analysis establishes otherwise.
1.14 Materials: All Contractor furnished materials (CFM) installed shall be new.
Materials shall be as indicated on the listed drawings, publications or as specified in this Specification, unless noted otherwise. The use of asbestos, polychlorinated biphenyl (PCB), magnesium, cadmium, or mercury in any materials is prohibited.
1.15 Label Plates: Label plates installed in locations exposed to the weather shall be CRES and shall be prepared by the “Metal-Photo” process and sealed to exclude moisture between the plate and the mounting surface. Label plates shall be installed to assure maximum visibility. Label plates shall be attached with CRES screws or adhesive, using drawing S2803-980209 Rev L for guidance. Where adhesive is used, surface preparation shall be in strict accordance with the adhesive manufacturer’s instructions. Test label plates shall be attached on or adjacent to all equipment or components tested without interference to equipment or component operation. The label shall identify the equipment or component, the test load, the dynamic and static load (if applicable), the rated load, the date of testing, and the activity performing the test, using the layout format of drawing S2803-980209 Rev L for guidance.
1.16 Availability Requirements: All written and electronic correspondence with the Government, however addressed, shall be submitted to the Contracting Officer via the COR. In general, for subjects related to payments, separate letters shall be submitted to the Government for each subject concerning changes or delivery. Company “authorized representatives” shall sign all Contractor correspondence. Furnish the Contracting Officer with a listing of names, titles, and telephone numbers of these authorized representatives, including emergency contact numbers at the Arrival Conference and when Contractor employees change.
1.16.1 Prepare and keep current schedules necessary for the purpose of establishing an orderly and systematic accomplishment of production work and material ordering. Provide two legible copies, One in hard copy and One in approved transferrable media to the COR.
1.16.1.1 All schedules and reports shall be submitted no later than
12:00 P.M. each Tuesday.
1.16.2 Document Contractor “conditions found” and inspection discrepancies on
FIGURE A, included as part of this specification. Duplicate and complete the form to notify the Contracting Officer of problems and provide Contractor recommended corrective action. Items whereby the contractor recommends corrective action, affecting costs or schedule, shall be accompanied by the contractor’s proposed costs and schedule impact. Provide sufficient information to enable the Contracting Officer to make a determination if contract modification is required. Provide all inspection results including detailed measurements, photographs, sketches, and other means to accurately detail the inspection results using FIGURE A, with attachments as necessary.
1.16.3 Provide separately metered electrical service equipment capable of supplying, monitoring, and measuring electrical usage for the industrial service type work specified in this SOW for the entire availability. It is estimated that a cumulative 200,000 KWH of electrical usage will be used for the entire availability.
1.16.3.1 Total KWH greater or less than the quantities listed in 1.16.3, when authorized by the Contracting Officer, will be the subject of an equitable adjustment.
1.16.3.2 Submit one legible copy, in approved transferrable media, of a final industrial service electrical usage report for the vessel to the COR.
1.16.4 Arrange for and transport the vessel from the Government facility at Puget Sound Naval Shipyard at Bremerton, WA to the Contractor's repair facility. Upon completion of all work, coordinate redelivery of the vessel to the Government facility at Puget Sound Naval Shipyard at Bremerton, WA. Provide all materials, labor, and insurance bonds necessary for the safe transport of the vessel to and from the Contractor's facility and for the period that the vessel is located at the Contractor's repair facility and as follows:
1.16.5 Provide Quantity (One EA) parking space, located within 1/4 mile of the vessel from 2 days prior to availability start to 2 days after availability completion for use by the COR.
1.16.5.1 Designate parking space with a sign stating "SUPSHIP
PARKING ONLY".
1.17 Integrated Logistic Support: Submit original copies of manufacturer supplied operating instructions, warranty information, service manuals and other supporting documents for all new equipment and parts to the COR, for items supplied by the Contractor.
1.18 Gas Free: Provide certified Marine Chemist, Certified Industrial Hygienist (CIH) services, and Shipyard Competent Person services as required by 29 CFR 1915 and as follows:
1.18.1 Submit one legible copy, in approved transferrable media, of a listing of the Contractor’s designated Shipyard Competent Persons, including Contractor certification that the Competent Persons’ training has been completed within the past year to the COR.
1.18.1.1 Provide the COR an updated roster each time Shipyard Competent Persons are added, deleted, or retrained.
1.18.2 Maintain certifications for the duration of the time that work is being accomplished, employees require access and prior to hot work being accomplished on each vessel.
1.18.3 Post, update, and maintain gas free certificates at each access entry to the area certified.
1.18.4 Consolidate and maintain the Contractor’s current confined space entry/gas free certification processes into a single and comprehensive document as part of a confined space entry/gas free certification program.
1.18.4.1 Submit one legible copy, in approved transferrable media, of any changes to the Contractor’s confined space entry/gas free certification program to the COR, after initial submission.
1.19 General Requirements for Testing: Test all Contractor affected equipment, systems and subsystems for compliance with this SOW and Commercial Marine standards and practices. Demonstrate workmanship, alignment, strength, rigidity, water tightness, functionality, and suitability for the purpose intended.
1.19.1 Prepare and submit a Test and Inspection Plan for each Test and Inspection required by this SOW, containing paragraph number or listed applicable reference requiring Tests and Inspections; identification of each component/system;
description of each Test and Inspection; accept/reject criteria; date scheduled;
Government notifications; date completed; and each Test and Inspection result.
1.19.1.1 Fully integrate the Test and Inspection Plan with the Contractor’s production schedule.
1.19.1.2 Provide the number of tests and inspections for a given system, component, or installation required to demonstrate required satisfactory performance. This section specifies tests to be performed in support of the work performed.
1.19.2 Provide a detailed description of preoperational checks to be conducted, operations to be performed, and the parameters to be satisfied. Furnish data sheets which provide spaces for recording the quantitative values measured during the test, for each test procedure. Specify the minimum and maximum allowable tolerance limits for each measured value. Furnish signature sheets for fill-in by the person conducting the test, the Government witness present, and the date of the test. Block diagrams, simplified schematics or diagrams may be used to clarify the procedure or test method.
Include a comment sheet to record significant events and observations by either the Government witness or Contractor.
1.19.3 Provide materials, supplies, utilities, equipment, instrumentation, services and personnel to accomplish each test. Incorporate safety precautions into each test procedure. Prepare all test documentation during the development and implementation of the acceptance test.
1.19.3.1 Whenever Government and/or Ships Force support is required for the operation of vessel equipment and/or systems, a minimum of 2 workday’s prior notification of the operational/test support requirement shall be provided to the COR.
1.19.3.2 Tests and equipment/systems operation requiring Government and/or Ship’s Force operational support shall be scheduled for accomplishment during normal day shift working hours, as much as practicable.
1.19.3.3 Provide a minimum of 3 workdays prior notification to the COR for tests and equipment/system operations requiring Government and/or Ships Force operational support for work being performed on weekends, after normal dayshift working hours, and immediately before and/or after Federal holidays.
1.19.3.4 The COR or his representative shall witness each test, unless authorization is received to proceed from the COR without a Government witness. A minimum of 4 hours prior notification to the COR is required prior to conducting tests.
Adjustments of equipment are not to be made during acceptance testing. The COR may countersign the acceptance test report, however the Government’s signature does not constitute approval or concurrence in any aspect of the testing, other than the presence of the Government at the test.
1.19.4 Perform tests using the applicable test procedure for systems and subsystems. Demonstrate compliance with the Specification requirements by satisfactory completion of the test. Complete all work prior to initial testing of that particular system or subsystem and in a timeframe sufficient to allow for correction of deficiencies prior to dock trials, sea trials, or other applicable milestones established in these specifications. Perform any grooming or dry run testing prior to the scheduled acceptance test.
1.19.4.1 Stop the test if the equipment, system, or subsystem tested fails to satisfy the acceptance criteria of the established test procedure. Determine the cause and correct.
1.19.5 Document the overall test results and findings in relation to the technical specification requirements. Provide a complete copy of the test procedure, with filled in data sheets, and detailed analysis of the raw data to the COR upon completion of each test.
1.20 Condition Found / Inspection Discrepancy Report (CFR/IDR): Utilize Figure A to communicate to the Contracting Officer concerning all conditions found, discrepancies noted, and other information requiring formal documentation. Provide the Contractor’s recommendation for corrective action and include Contractor’s estimated pricing (man hours and materials) to correct the condition found. The Government will review and respond to the submitted report. Additional repairs related to the found condition will be tasked if determined necessary by the Government. In the event difficulty is encountered in meeting requirements or difficulty is anticipated in complying with the contract schedule dates, immediately notify the Contracting Officer via verbal communication with the COR. Provide the COR a written report stating pertinent details as to why requirements cannot be met the following work day. Receipt of this notification by the Government is not to be construed as a waiver of the requirements, delivery schedule, or waiver of rights or remedies provided by law or under this contract, or any other requirements in the SOW relating to jeopardy of contract schedule dates.
Submission of this report does not authorize the Contractor to perform additional work not covered by the contract or authorized by the Contracting Officer.
1.20.1 When work does not require a report, and one is determined to be necessary in order to produce a reliable or complete repair, submit one legible copy, in approved transferrable media, of a report with supporting data as early as possible in the contract period to the Contracting Officer, via the COR. The goal is to have required work completed within the original contract period.
1.20.2 For required reports that could result in a change in work to be accomplished or additional material to be procured, complete the preliminary documentation and submit one legible copy, in approved transferrable media, of the required report in a time frame to allow the Contracting Officer, via the COR, to initiate early action, but no later than the first 20 percent of the scheduled availability.
1.20.3 Drydock related inspection reports shall be submitted no later than the first 20 percent of the scheduled docking period. Drydock related reports which contain readings (final, thickness, etc.) clearances, alignments, test results, or other such data for work that has to be completed prior to pre-flood/undocking, shall be submitted to the Contracting Officer, via the COR, within 24 hours after recording the data but no later than 72 hours prior to pre-flood/undocking, whichever occurs first.
FIGURE A - CONDITION FOUND/INSPECTION DISCREPANCY
REPORT
CFR Number________ Date: ______________
From:________________________________ (Contractor Authorized Representative) To: PSNS & IMF, NWRMC IND MAN, C400, Contracting Officer Via: PSNS & IMF, NWRMC IND MAN, C400, Contracting Officer’s
Representative (COR)
Vessel: LCM (3) WB 9207
Section of Contract Affected:
Description:
Impact:
Recommended Action:
C400 Response:
Signature of C400 Representative Date
Page ___ of ____
2.0 REFERENCES: All references shall be of the latest issue and/or revision or as indicated in the Consolidated List of References. It is incumbent on the Contractor to maintain current commercial specifications and be thoroughly familiar with Federal, State and Local laws, regulations and ordinances. Contractor is prohibited from using Government provided technical information for any purpose other than that contemplated by the specifications. Contractor is prohibited from further use, release, or disclosure of this information. References provided on CD-ROM, including any information contained thereon, must be destroyed in accordance with the instructions included on the CD-ROM label, at completion of the contract. After award, for those Contractors in receipt of a CD-ROM and not awarded a delivery order, the CD-ROM including any information contained thereon, shall be destroyed in accordance with the instructions included on the CD-ROM label.
2.1 Order of Precedence: Unless otherwise noted within this specification, hierarchy, priority, or order of precedence of requirements shall be as follows:
2.1.1 Specification Definite Item
2.1.2 Specification General Requirement
2.1.3 Military/Navy Drawings
2.1.4 Military/Navy Technical Manuals
2.1.5 Commercial Drawings
2.1.6 Commercial Technical Manuals
2.1.7 Commercial or Industrial Standards
2.1.8 Commercial Practices
2.2 Discrepancies: Drawing, technical reference, or other discrepancies associated with this specification shall be reported using the Request for Specification Clarification form, during proposal, or the “Condition Found / Inspection Discrepancy Report” form (FIGURE A) during delivery order period of performance.
CONSOLIDATED LIST OF REFERENCES
The following publication and drawing requirements are applicable to this SOW:
Publication Number Title
1) 29 CFR 1910 Occupational Safety and Health Standards
2) 29 CFR 1915 Occupational Safety and Health Standards for Shipyard Employment
3) 29 CFR 1926 Safety and Health Regulations for Construction
4) 10 USC 7311 Repair or Maintenance of Naval Vessels:
Handling of Hazardous Waste
5) 15 USC 2601, et seq. Toxic Substances Control Act
6) 33 USC 1251 to 1387 Federal Water Pollution Control Act
7) 33 USC 1342 National Pollutant Discharge Elimination
System
8) 33 USC 2701 to 2761 Oil Pollution Control Act of 1990
CONSOLIDATED LIST OF REFERENCES
The following publication and drawing requirements are applicable to this SOW:
Publication Number Title
9) 42 USC 6901 to 6992 Resource Conservation and Recovery Act of
10) 42 USC 7401, et seq. Clean Air Act
11) 49 USC 5103 Hazardous Materials Transportation
Authorization Act of 1994
12) ANSI/AWS D1.1 Structural Welding Code, Steel
13) ASTM A167, AISI 304L, AISI
316L Plate and Sheet Steel Standards
14) ASTM A1011 Grade, 30, 36 or
Plate (1/8 inch or greater)
15) ASTM A131 Bars and Shapes
16) ASTM A53, A106 Grade B, Steel Pipes
17) ASTM F718 Standards for Shipbuilders and Marine
Paints and Coating Product/Procedure Data Sheet
18) ASTM F940
ASTM F 1321-92 Standard Guide for Conducting a Stability Test
19) ASTM NDT References E709-01 - Magnetic Particle Examination E164-03 - Ultrasonic Examination E165–02 - Liquid Penetrant Examination
20) SSPC Painting Manual, Volume
Good Painting Practice
21) SSPC Painting Manual, Volume
Systems and Specifications
22) SSPC Manual 05-03 Surface Preparation Specifications and
Practices
23) T9074-AS-GIB-010/271 Requirements for Nondestructive Testing Methods
24) MIL-STD-777 Schedule of Piping, Valves, Fittings and Associated Piping Components for Naval Surface Ships
25) NSTM Chapter 997 Docking Instructions and Routine Work in Dry Dock
26) S9086-CH-STM-010/CH 074
VOL 1
Welding and Allied Processes
27) S9086-CJ-STM-010 NSTM, Chapter 075, Fasteners
28) S9086-HM-STM-010/CH243 Propulsion Shafting
29) S9086-HN-STM-010/CH244 Propulsion Bearing and Seals
30) S9086-HP- STM-010/CH245 Propellers and Propulsor
31) S2803-98020 Rev L Labels
32) S2804-921819 Rev C Distinguishing Figures for Miscellaneous Vessels
33) S9086-C-6-STM-010 Weights and Stability Testing
34) S9008-C1-BIB-010 15-Meter Work Boat MK3, FY92
ERRATA1 35) SK15MWB9207 Fender Drawing
Drawing Number Title
1) 101-6893066 Rev A General Arrangement Inboard and Out Board
2) 101-6893067 Rev B Hull Construction and Details
3) 101-6893068 Rev A Pilot House Construction and Details
4) 101-6893069 Rev A Miscellaneous Details
5) 101-6893078 Rev A Lines and Offsets
6) 201-6893070 Rev A Machinery Arrangement and Details
7) 201-6893071 Rev C Steering System and Engine Controls
8) 501-6893073 Rev D Piping System Diagram and Details
9) 601-6893074 Rev B Hoisting Arrangement and Details
10) 601-6893075 Rev A Pusher Pads
11) 803-921865 Rev R Cathodic Protection Hull Zinc Anodes
12) S570K Assembly Instructions (Checks & Tests) and Production Tests, Marine Transmission MG- 506/MG-506-1/MG-506A Twin Disc Inc. Spec Sheet
3.0 WORK REQUIREMENTS:
3.1 DOCKING AND UNDOCKING THE VESSEL: Accomplish the following to safely dock and undock the vessel as follows:
3.1.1 Personnel and equipment: Furnish qualified and experienced personnel, facilities, and the necessary equipment to safely dock and undock the vessel, including:
3.1.1.1 A Dock Master currently qualified and certified by the Contractor and accepted by the Government Docking Observer (GDO);
3.1.1.2 Supporting employees to accomplish the docking and undocking evolutions;
3.1.1.3 Tugs, pilots, and divers required for the complete transfer, docking, and undocking of each vessel. At the docking conference, the GDO will review and approve the number and size of the tugs to be used.
3.1.2 Docking Procedure: Submit a docking procedure to the GDO 5 working days prior to dry docking, which shall include the following:
3.1.2.1 Operating practices;
3.1.2.2 Safety and security plans;
3.1.2.3 Special precautions or actions required by the characteristics of the dock, marine railway, or other docking methods;
3.1.2.4 Pumping/flooding schedule;
3.1.2.5 Specific list, trim, and stability requirements.
3.1.3 Blocking Plan: Develop and submit to the GDO for review and approval a blocking plan to set and align the docking blocks in accordance with the requirements of NSTM Chapter 997, using drawings 101-6893066 Rev A, 101-6893067 Rev B, 101- 6893069 Rev A, and 101-6893078 Rev A for guidance.
3.1.3.1 Submit the docking plan in the form of a scaled drawing including:
block size, block spacing, and location of vessel with respect to the blocks at landing.
Position blocking to ensure that equipment on the surface of or protruding from the hull will not be damaged.
3.1.3.2 Determine the docking clearances utilizing references for guidance and the minimum clearance between the side of the vessel (including fixed projections) and permanent dock structure (such as catwalks, crane rails, etc.). Minimum clearance shall be 12 inches for bringing the vessel into or out of dock and performing any work inside the dock. Ensure hull openings are not obstructed. Ensure a 40-inch minimum clearance between the keel and dock floor for vessels with more than 12 inches of dead rise and a 60-inch minimum clearance between the keel and dock floor for vessels with less than 12 inches of dead rise.
3.1.3.3 The blocking plan shall be accompanied by a written request for approval to the GDO a minimum of 5 working days prior to the scheduled docking date.
The use of haul, fixed, or fitted blocks shall be clearly stated.
3.1.3.4 The use of universal docking blocks is prohibited.
3.1.3.5 Submit supporting data substantiating that:
3.1.3.5.1 The block loading pressures are limited to a maximum of 20 long tons per square foot;
3.1.3.5.2 The number, distance from centerline, and square
footage of the side blocks per side is sufficient to resist overturning moments; and
3.1.3.5.3 At least 90 percent of blocks land on longitudinal
strength members or main transverse bulkheads.
3.1.4 Crib and Brace Blocking: Ensure that crib and brace blocking are in accordance with the requirements of NSTM Chapter 997, using the drawing applicable to the docking facility. Keel block height must be a minimum of 40 inches between the keel and dock floor for vessels with more than 12 inches of dead rise and a minimum of 60 inches between the keel and dock floor for vessels with less than 12 inches of dead rise.
3.1.4.1 The aspect ratio for un-cribbed keel blocks shall not exceed 2.0 where the aspect ratio is defined as the height divided by the horizontal dimension for the longitudinal and transverse direction, each checked separately.
3.1.4.2 Side blocks with a longitudinal dimension less than 24 inches shall be longitudinally braced or cribbed when their height as measured from the base to the highest corner of the soft cap exceeds 3 times the longitudinal dimension. Bracing shall be by an approved method.
3.1.4.3 Blocking shall be constructed of hardwood or composite hardwood/concrete and soft caps, with at least 2 inches of soft cap thickness. Blocking material construction requirements are as follows:
3.1.4.3.1 The term “hardwood”, for the purposes of this contract, includes White Oak, California Laurel, Oregon Myrtle, Iron Wood, Blue Gum, American Rock Elm, or preserved Red Oak. The normal lifespan for hardwood blocking is about 10 years.
3.1.4.3.2 Woods acceptable for use as soft caps are Douglas Fir, Tamarack, Long Leaf Pine, or Hemlock.
3.1.4.3.3 Composite blocking showing evidence of spalling and cracks or chipped and damaged concrete is not acceptable.
3.1.4.4 Blocking showing evidence of excessive crushing, warping, cracking, checking, rotting, or damage from dogging, loss of contact at edges caused by cracking or unequal shrinkage or deterioration to an extent no longer being capable of supporting a prescribed load over full bearing areas is not acceptable and shall be replaced.
3.1.5 Setting and Alignment of Docking Blocks: Furnish, set, record, and align the blocks in accordance with the Government approved Contractor blocking plan and in accordance with the requirements of NSTM Chapter 997.