Answers to Offeror Questions (continued) 03 July 2014
25 Q Please define the interface requirements to operate the GFE ASPU Dry test motor and dyno:
1) Water flow based on a 45 degree Fahrenheit inlet temperature
a) GPM into Dyne
i) Expected heat losses required to dissipate
b) GPM into Motor
i) Expected heat losses required to dissipate
2) Weight of GFE
a) Is there equal floor loading?
3) Foot print of GFE
4) Electrical Service Requirements
a) Voltages
b) Phases
c) Current draw
d) Number of circuits
5) Alternate sources of energy required a). Compressed Air?
A 1. Water flow based on a 45 degree Fahrenheit inlet temperature ‐60 Ton
Chiller @ 120 Gallons per minute (GPM)
a. GPM into Dyne ‐
37 Gallons per minute (GPM)
b. GPM into Motor
Variable Gallons per minute (GPM) based on heat load.
c. GPM into Motor controller
20 Gallons per minute (GPM)
2. Weight of GFE
25,000 lbs
a. Is there equal floor loading? No
3. Foot print of GFE ‐ 20 Foot Conex box
4. Electrical Service Requirements ‐ 220 VAC, 90 AMP & 120 VAC 12.5 amp
5. Alternate sources of energy required a). Compressed Air? 90 PSI air
26 Q Please clarify standard reference:
Paragraph states “MIL‐STD‐454B ; should this reference be MIL‐HDBK‐454 Rev
B as stated in paragraph 2.1.2 (d) of NAVSEA Drawing No 8516387.
If reference MIL‐HDBK‐454 Rev B is the correct standard, then “requirement
55” should be “Guideline 55” in paragraph 5.2.5.12 of NAVSEA Drawing No.
8516387.
If reference MIL‐HDBK‐454 Rev B is the correct standard, should the Document
8516387 take precedence over Item 2 of Forward MIL‐HDBK‐454 Rev B?
Suggest adding reference to paragraph to paragraph 4.6.4 of NAVSEA Drawing
No. 8516387.
A Yes Paragraph states “MIL‐STD‐454B ; should this reference be MIL‐HDBK‐454
Rev B as stated in paragraph 2.1.2 (d) of NAVSEA Drawing No 8516387.
Yes “requirement 55” should be “Guideline 55”
Document 8516387 take precedence over MIL‐HDBK‐454 Rev B
See updated Paragraph below:
5.2.5.12 Enclosure
The drive enclosure shall meet the specification of paragraph 4.6.4 and the requirements of Guideline 55 of MIL‐HDBK‐454 Rev B. Additionally, one enclosed drive shall be tested as specified in MIL‐STD‐108E.
27 Q Please clarify if the GFE item 1 (ASPU Dry test motor) and item 2 (Dyno) are delivered assembled. Will vender be required to assemble item 1 and item 2 to make them functional for test?
Will the Purchaser supply any needed instruction on the use of the GFE if
Vendor decides to use GFE?
A GFE item 1 (ASPU Dry test motor) and item 2 (Dyno) are delivered assembled in one 20 foot Conex box
Yes PSNS will provide a general operational instruction with the GFE item.