Amendment 0002 7483016.pdf

PDF 379 KB Posted

Attached to
MCAS-Cherry Point: Generator and ATS Replacement, AirOps, Building 1695
Solicitation number
N400857483016
Issued by

About this file

This is Amendment #0002 to solicitation 7483016 for Generator and ATS Replacement at AirOps Building 1695, Marine Corps Air Station Cherry Point, North Carolina, issued by NAVFAC FEAD Cherry Point on August 7, 2025. The amendment confirms that the proposal due date remains unchanged at August 29, 2025 at 12:00 PM local time and must be acknowledged by offerors to avoid rejection of their proposals.

The primary change in this amendment updates the bond requirements, mandating that bid bonds are required per Federal Acquisition Regulation (FAR) 52.228-1, and specifying that an electronic copy of the bid bond must be submitted with the proposal. Failure to include the electronic bid bond will result in the proposal being deemed nonresponsive and removed from consideration. All other contract terms and conditions remain unchanged. Offerors who have already submitted proposals must acknowledge this amendment by telegram, stating whether their proposed price remains the same, increases, or decreases, with acknowledgment required before the proposal opening time.

View the file

Other files

File Type Posted
Amendment 0003 7483016.pdf PDF
7483016 Revised 8.15.25.pdf PDF
Amendment 0001 7483016.pdf PDF
7483016 RFP.pdf PDF
7483016 Final Specs.pdf PDF
1695 Gen Pic1.jpg JPG image
B1695.png PNG image
1695 Gen Pic2.jpg JPG image

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

7483016 Generator and ATS Replacement, AirOps, Building 1695

MCAS Cherry Point, NC AMENDMENT

#0002

IMPORTANT

This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of the proposal.

If your proposal has been submitted prior to the receipt of this amendment, acknowledgement should be made by telegram, which should state whether the price contained in your proposal is to remain unchanged, is to be decreased by an amount, or is to be increased by an amount. The acknowledgement must be received prior to proposal opening time.

NAVFAC

SPECIFICATION

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

1 2

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

0002 08/07/2025

6. ISSUED BY Code N40085 7. ADMINISTERED BY (If other than item 6.) Code

FEAD CHERRY POINT

PSC BOX 8006

CHERRY POINT, NC 28533

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION

9B. DATED (SEE ITEM 11)

AMENDMENT MUST BE ACKNOWLEDGED WITH YOUR PROPOSAL 10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning 1 copy of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (if required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER: (specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return original to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

7483016 Generator and ATS Replacement, AirOps Building 1695, Marine Corps Air Station Cherry Point, NC

The proposal due date of August 29, 2025 at 12:00 PM local time REMAINS unchanged.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR (Same as Item 8) 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY

(Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.1-83) 0224-3(10-90)

PREVIOUS EDITION UNUSABLE Prescribed by GSA

Project 7483016 Generator and ATS Replacement, AirOps

7483016

Generator and ATS Replacement, AirOps Building 1695 Amendment 0002

MCAS Cherry Point, North Carolina Project No. 7483016

Block 14. DESCRIPTION OF AMENDMENT (cont.)

A. This amendment updates the Bond Requirements paragraph provided in the original Request for

Proposal to the following:

B. Bond Requirements: Bid bonds are required in accordance with Federal Acquisition Regulation

(FAR) 52.228-1. An electronic copy of your bid bond must be submitted with your proposal.

Failure to submit an electronic copy of your bid bond with your proposal will result in your proposal being deemed nonresponsive and your proposal removed from consideration.

C. All other contract terms and conditions remain unchanged.

Blank Page

File details come from the government source that posted it. Updated .