This is Amendment #0004 to NAVFAC Specification 7263360 for renovating the break room and entrance at Building 159 DLA at MCAS Cherry Point, NC. The amendment provides responses to pre-award RFIs and includes a revised drawing (12912581 A-102) dated January 31, 2025.

The amendment addresses contractor questions about existing break room furnishings, including 6' tall multi-tier personal lockers, tables, chairs, and other items. It also addresses work in an active restroom requiring removal and reinstallation of a water closet and toilet enclosure. For all RFI responses, contractors are directed to refer to the revised drawing 12912581 and submit proposals in accordance with the RFP, specifications, drawings and all amendments. Key dates remain unchanged: pre-award RFI deadline is February 10, 2025 at 9:00 AM, and proposals are due February 20, 2025 at 12:00 PM local time. The amendment must be acknowledged when submitting proposals, with any price changes noted if proposals were already submitted.

View the file

Other files

File Type Posted
7263360 Amendment 0006.pdf PDF
7263360 Amendment 0005.pdf PDF
7263360 Amendment 0003.pdf PDF
7263360 Amendment 0002.pdf PDF
7263360 Amendment 0001 - Updated.pdf PDF
RFP 7263360 - Updated.pdf PDF
7263360 Amendment 0001.pdf PDF
7263360 DrawingsAsOne SIGNED.pdf PDF
RFP 7263360.pdf PDF
7263360 SpecsAsOne SIGNED.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NAVFAC

SPECIFICATION

7263360 Renovate Break Room and

Entrance, B159 DLA

MCAS Cherry Point, NC

AMENDMENT #0004

IMPORTANT

This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of the proposal.

If your proposal has been submitted prior to the receipt of this amendment, acknowledgement should be made by telegram, which should state whether the price contained in your proposal is to remain unchanged, is to be decreased by an amount, or is to be increased by an amount. The acknowledgement must be received prior to proposal opening time.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

1 2

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

0004 1/31/2025 7263360

6. ISSUED BY Code N40085 7. ADMINISTERED BY (If other than item 6.) Code CG MCAS Cherry Point

FACILITIES, ROICC

B-163, CURTIS ROAD

PSC BOX 8006

CHERRY POINT, NC 28533

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION

Renovate Break Room and Entrance, B159

DLA

9B. DATED (SEE ITEM 11)

AMENDMENT MUST BE ACKNOWLEDGED WITH YOUR PROPOSAL 10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning 1 copy of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (if required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER: (specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return original to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

7263360 Renovate Break Room and Entrance, B159 DLA, Marine Corps Air Station Cherry Point, NC

Amendment 0004 is being issued to answer pre-award RFI’s.

The deadline to submit pre-award RFI’s REMAINS 10 February 2025 at 9:00 AM.

The proposal due date of 20 February 2025 at 12:00 PM local time REMAINS unchanged.

See Attached.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR (Same as Item 8) 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY

(Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.1-83) 0224-3(10-90)

PREVIOUS EDITION UNUSABLE Prescribed by GSA

Amendment 0004 7263360 Renovate Break Room and Entrance, B159 DLA

MULTI-RFI Responses:

1. During the Prebid site visit it was observed that an approx. 6’ tall run of multi-tier personal lockers are located along the west wall of the Break Room. This feature is not identified on the drawings or addressed by specification guidance. Will it be removed prior to the start of work by others (i.e. not in contract)?

Response:

See drawing 12912581 revised 1/31/25. Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

2. If contractor is required to breakdown, store and reinstall the lockers, it is requested that product data be provided. Is a suitable storage area within B159 available? If not, please advise where a storage container can be placed outside the building.

Response:

Drawings and all amendments.

3. Like above, the Break Room is also filled with tables and chairs and misc. items. Will these item be removed prior to the start of work by others (i.e. not in contract)?

Response:

Drawings and all amendments. Also a continuation sheet must be provided.

4. During the Prebid site visit it was observed the work indicated by Demolition Keynote 7 and Construction Keynote 5 on Drawing A-102 is in an active restroom and will require the removal, storage and reinstallation of a water closet and toilet enclosure. The nature of the work will require the restroom to be out of service for most of the construction. Please confirm the location observed during the site visit was correct and that the impact on Building’s operation is acceptable (loss of toilet facility).

Response:

Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

Subj: AMENDMENT TO WO 7263360 RENOVATE BREAK ROOM AND ENTRANCE, MCAS CHERRY

POINT NC

CONTINUATION SHEET

DOCUMENT 00 01 15

1.2 CONTRACT DRAWINGS

The following drawings are revised as of 31 JAN 2025:

NAVFAC DWG NO. TITLE

12912581 A-102 DEMOLITION & CONSTRUCTION FLOOR PLANS

These drawings accompany this Amendment.