Amendment 0003.pdf

PDF 633 KB Posted

Attached to
Replace Pool Liner Combat Training Pool B289
Solicitation number
N400857064317
Issued by

View the file

Other files

File Type Posted
7064317 Amendment 0005.pdf PDF
Amendment 0004.pdf PDF
Amendment 0002.pdf PDF
Amendment 0001.pdf PDF
7064317 DrawingsAsOne.pdf PDF
RFP 7064317 B289 Replace Pool Liner Combat Training Pool.pdf PDF
7064317 SpecsAsOne.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NAVFAC

SPECIFICATIO N

7064317

B289 Replace Pool Liner

Combat Training Pool

MCAS Cherry Point, NC AMENDMENT

#0003

IMPORTANT

This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of the proposal.

If your proposal has been submitted prior to the receipt of this amendment, acknowledgement should be made by telegram, which should state whether the price contained in your proposal is to remain unchanged, is to be decreased by an amount, or is to be increased by an amount. The acknowledgement must be received prior to proposal opening time.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

1 3

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

0003 02/09/2021 7064317

6. ISSUED BY Code N40085 7. ADMINISTERED BY (If other than item 6.) Code

CG MCAS Cherry Point

FACILITIES, ROICC

B-163, CURTIS ROAD

PSC BOX 8006

CHERRY POINT, NC 28533

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION

B289 Replace Pool Liner Combat Training Pool

9B. DATED (SEE ITEM 11)

AMENDMENT MUST BE ACKNOWLEDGED WITH YOUR PROPOSAL 10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning 1 copy of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (if required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER: (specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return original to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

7064317 B289 Replace Pool Liner Combat Training Pool, Marine Corps Air Station Cherry Point, NC

This amendment is being issued to respond to pre-award RFIs and incorporate revised specifications as indicated on continuation sheet.

The deadline to submit pre-award RFIs remains 11 February 2021 by 0900.

The proposal due date of 23 February 2021 at 1200 local times remains UNCHANGED.

See Attached.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR (Same as Item 8) 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY

(Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.1-83) 0224-3(10-90)

PREVIOUS EDITION UNUSABLE Prescribed by GSA

CONTINUATION SHEET

PROJECT TABLE OF CONTENTS

SECTION 07 13 53, POOL LINER SYSTEM is deleted and 07 13 53, POOL LINER

SYSTEM dated 9 FEB 2021, as shown in the footer, is added to the

Project Table of Contents and accompanies this Amendment.

Amendment 0003 7064317 - B289 Replace Pool Liner Combat Training Pool

RFI Responses:

4. Spec Section 01 14 00, Paragraph 1.2a indicates that the Combat Training Pool must be ready for operation as approved by Contracting Officer by August 2, 2021. However, the Project RFP indicates that the Project CCD is 150 Days after Contract Task Order award. Will the Contract

Task Order Completion Date be 150 Days after award as specified in the Project RFP?

Response:

Submit Proposals in accordance with RFP, Specifications, Drawings, and all Amendments.

5. Will the remaining water in the pool be drained by the Government prior to the start of work and will the Government refill the pool after Project BOD?

Response:

See attached continuation sheet. See paragraphs 3.1 and 3.3.2 in Section 07 13 53 and Submit Proposals in accordance with RFP, Specifications, Drawings, and all Amendments.

Replace Pool Liner Combat Training Pool, B289 7064317

SECTION 07 13 53

POOL LINER SYSTEM

02/16

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D570 (1998; E 2010; R 2010) Standard Test Method for Water Absorption of Plastics

ASTM D751 (2006; R 2011) Coated Fabrics

ASTM D1004 (2013) Initial Tear Resistance of Plastic Film and Sheeting

ASTM D2136 (2002; R 2012) Coated Fabrics - Low-Temperature Bend Test

ASTM D4833/D4833M (2007; R 2020) Standard Test Method forIndex Puncture Resistance of Geomembranes and Related Products

1.2 SUBMITTALS

Government approval is required for all submittals. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Manufacturer's Standard Details

Pool Liner System

Accessories

Adhesives

SD-06 Test Reports

Pool Liner System

Field Quality Control documentation

SD-07 Certificates

Pool Liner System

Adhesives

Draft Special Warranties

SECTION 07 13 53 Page 1 REVISED 9 FEB 21

Final Special Warranties

Installer's Qualifications

SD-08 Manufacturer's Instructions

Adhesives

1.3 MANUFACTURER'S DETAILS

Submit manufacturer's standard details indicating methods of attachment and spacing, transition and termination details, and installation details. Include verification of existing conditions.

1.4 PRODUCT DATA

Include data for material descriptions, recommendations for product shelf life, and manufacturer's Safety Data Sheets (SDS) for adhesives.

1.5 DELIVERY, STORAGE, HANDLING, IDENTIFICATION

Deliver and store materials in accordance with manufacturer's printed instructions, out of the weather, in manufacturer's original packaging with brand name and product identification clearly marked. Keep materials wrapped and separated from off-gassing materials (such as drying paints and adhesives). Do not use materials that have visible moisture or biological growth. Do not permit unidentified materials in the work area or in the project. All materials provided are to be new and in unopened packaging.

1.6 SPECIAL WARRANTIES

1.6.1 Guarantee

Guarantee waterproofing membrane installation against failure due to leaks for a period of two years from the date of Beneficial Occupancy. Submit draft and final guarantees in accordance with Sections 01 78 00 CLOSEOUT SUBMITTALS and 01 78 23 OPERATION AND MAINTENANCE DATA.

1.6.2 Warranty

Provide manufacturer's material warranty for all system components for a period of ten years from the date of Beneficial Occupancy. Submit draft and final warranties in accordance with Sections 01 78 00 CLOSEOUT SUBMITTALS and 01 78 23 OPERATION AND MAINTENANCE DATA.

1.7 Installer's Qualifications

Pool liner material supplier and the PVC membrane manufacturer must have been engaged in the manufacture of PVC membranse for use in swimming pools for a minimum of ten years. Installer must submit a minimum of 15 pools of similar size and complexity.

SECTION 07 13 53 Page 2 REVISED 9 FEB 21

PART 2 PRODUCTS

2.1 MATERIALS

Provide materials that comply with applicable requirements cited below when tested in accordance with the referenced ASTM publications.

2.1.1 Stainless Steel

Class 301, 302, or 304. Satin finish for exposed surfaces and No. 4 finish for interior surfaces.

2.2 Pool Liner System

Provide a pool liner membrane consisting of polyvinyl chloride (PVC) flexible sheets fully UV stabilized and reinforced with a scrim consisting of a tightly woven polyester 9x9 threads per inch, 1,000 denier thread for maximum puncture resistance, not less than 60 mils minimum thickness (70 mil thickness with embossing). Provide 0.3 mil coating of factory-applied stain guard acrylic coating applied as a topcoat to reduce soiling in the field and to make the liner easier to clean. All pool liner system components must be from the same manufacturer. Material colors are as follows: Color of walls must be white or light blue as indictaed by the Contracting Officer. Floor must be light blue or white with stain guard acrylic topcoat protective coating and must be formulated using anti-fungal agents and manufactured specifically for use in the commercial swimming environment. An acrylic stand guard coating must be a factory applied top coating designed to make cleaning easier and to minimize soiling. The material must be applied with the nonskid/textured side out in the floor area and on all gutter and step areas to provide slip resistance. All welds must be accomplished with hot air welding. Solvent welding of PVC materials is not permitted. Double stick mylar tapes are not permitted. Seams must be tacked, a continuous air entrapment weld must be performed continuous on all welds, and then a minimum 3/4" wide weld must be installed. Burning of the material is not permitted.

Recycled products are not permitted.

Racing lanes, targets, marking strips, and depth indicators must be provided and are black in color. All markings must meed local, state, and federal pool codes.

2.2.1 PVC Membrane Performance Requirements

a. Overall thickness: .059 inches minimum (60 mil)

b. Tensile strength, ASTM D751: MD > 165 ppi; TD > 156 ppi minimum

c. Elongation at break, ASTM D751: MD < 0.22%; TD < 0.10%

d. Tear resistance, ASTM D1004: 25 lbf

e. Puncture Resistance, ASTM D4833/D4833M : 100

f. Cold Flex Resistance, ASTM D2136: Pass -50C; 1/8" Mandrel

g. Water Absorption, ASTM D570: 0.5 percent maximum

SECTION 07 13 53 Page 3 REVISED 9 FEB 21

2.2.2 Felt Underlayment

Provide an underlayment of 10.5 oz felt fully adhered the entire pool with adhesive that is compatible with the felt and PVC membrane and that meets the manufacturers recommendations.

Spray or roll on an anti-microbial product fully compatible with the PVC membrane under the felt underlayment to discourage microbial groth under the pool liner system.

2.2.3 Adhesives

a. Adhesive for felt underlayment as recommended by manufacturer.

b. Adhesive for pool liner must be recommended by the manufacturer, not be weakened when exposed to water immersion and must be fully compatible for bonding to the PVC material and felt underlayment.

2.2.4 Accessories

2.2.4.1 Terminations

Provide PVC coated stainless steel metal terminations. PVC Coated galvanized steel is not permitted

2.2.4.2 Flanges

Flanges must be constructed of Type I Exterior Grade Hard PVC sheet and custom fabricated, radiused and drilled for use at all membrane penetrations. PVC foam based or foam core compression flanges are not permitted.

2.2.4.3 Expansion Joint Covers

6 inches wide Stainless Steel 25 gauge plate installed over all active expansion joints and working cracks.

PART 3 EXECUTION

3.1 VERIFICATION OF CONDITIONS

The government will remove any water in the pool before work begins.

Before starting the work, verify surfaces that must be waterproofed are in satisfactory condition. Notify the Contracting Officer of defects or conditions anticipated to prevent a satisfactory application. Do not start application until defects and conditions have been corrected.

3.2 SURFACE PREPARATION

Ensure surfaces to receive treatment are clean, dry, smooth, and free from deleterious materials and projections. Cut off high spots or grind smooth. Finish top surfaces of projecting masonry or concrete ledges below grade, except footings, to a steep bevel with Portland cement mortar. Thouroughly clean surfaces to receive covering before applying pool liner system to remove dust and foreign matter. Cure concrete by a method compatible with the waterproofing system. All working cracks, expansion joints, or voids must be isolated from the 10.5 ounce felt layer above by the installation of rigid stainless steel strips.

SECTION 07 13 53 Page 4 REVISED 9 FEB 21

3.3 APPLICATION

3.3.1 General Installation Requirements

Install pool liner system in accordance with manufacturer's printed installation instructions. Ensure the surface to receive membrane is clean, smooth and dry without surface irregularities; correct deficiencies prior to installation. Avoid wrinkles and buckles in applying membrane and joint reinforcement.

3.3.2 Pool Liner Membrane (PVC)

Consult with membrane manufacturer prior to grid application. Install 12 inches wide sub-membrane containment grid as required by manufacturer.

Provide the containment grid at intervals across the width and length of the substrate, at the base of all transitions, walls, penetrations, and at the perimeter of each substrate section. Fully adhere strips to the concrete in a full bedding of manufacturer approved adhesive. Weld adjacent sheets in accordance with manufacturer's instructions. Hot-air weld all side and end joints.

3.4 FIELD QUALITY CONTROL

Notify the Contracting Officer 5 working days prior to date of performing tests. Fill pool after pool liner system has been installed. Coordinate with the Contracting Officer for water source. Test pool liner system for 24 hours. Do not add water after start of 24 hour period. Accurately measure water level at beginning and end of 24 hour period. If water level falls, remove water and inspect pool liner system. Make repairs or replacement as directed, and repeat test. Do not proceed with work that conceals membrane waterproofing before receiving approval and acceptance of the Contracting Officer.

-- End of Section --

SECTION 07 13 53 Page 5 REVISED 9 FEB 21

12825943 REV2.pdf
Sheets and Views
A-501