This is Amendment 0003 to a federal solicitation for contract N40085-27-R-9006, issued by NAVPAC Mid-Atlantic on November 20, 2026, with an effective date of November 13, 2026.

The amendment addresses a contractor question regarding commissioning requirements for NH100 Engine Control Unit Replacement on Project 27-0700. The government confirms that commissioning is strictly required and is governed by Section 3 and Section 4.b of the Scope of Work (SOW), along with NFPA 110, NFPA 99, UFC 4-510-01, and The Joint Commission standards. The Prime Contractor must hire an independent, verified Commissioning Agent (CxA) to direct, witness, and document comprehensive Functional Performance Testing (FPT) consisting of two stages: Stage 1 involves isolated load bank testing of each of three generators individually, verifying base engine parameters, ECU-to-engine control, ECU-to-switchgear communication, and full-capacity load bank testing to 910 kW at 0.8 power factor per NFPA 110 standards. Stage 2 involves integrated Emergency Power Supply System (EPSS) testing including black start and 10-second transfer simulation per NFPA 110 Level 1/Type 10 requirements, paralleling and load sharing verification using RussElectric switchgear PLCs, PLC monitoring and safety alarm verification, and retransfer and cooldown procedures. Closeout deliverables include the final signed NFPA 110 commissioning report, updated as-built wiring diagrams, operations and maintenance manuals, and staff training. The time and date for receipt of proposals remains unchanged, and acknowledgment of the amendment is required upon proposal submission.

View the file

Other files

File Type Posted
Amend 0002.pdf PDF
Amend 0001.pdf PDF
Combined DIV 01 specs small projects.pdf PDF
RFP 270700.pdf PDF
NH100 REPLACE ENGINE CONTROL UNITS ON 3 GENERATORS revised.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N40085-27-R-9006 Amendment 0003

CONTINUATION SHEET

1. QUESTION: Upon initial review of the contract documents, we are unable to locate a specification section addressing commissioning requirements for this project. The only reference to commissioning is in Section 01 78 23. Please clarify whether commissioning is required for this project. If so, please provide the applicable commissioning specifications, scope of work, and associated requirements.

ANSWER:

Yes, commissioning is strictly required for this project.

Because this project is a targeted controls upfit and repair of existing emergency generators, a standalone Division 01 commissioning specification section is not utilized; rather, commissioning is governed by Section 3 and Section 4.b of the Scope of Work (SOW), NFPA 110, NFPA 99, UFC 4-510-01, and The Joint Commission standards. (Note: Full NETA apparatus testing under UFGS 26 08 00 for new switchgear construction is not required, as existing medium/low-voltage breakers are not being replaced).

In accordance with Section 4.b of the SOW, the Prime Contractor shall hire an independent, verified Commissioning Agent (CxA) to direct, witness, and document a comprehensive Functional Performance Test (FPT) of each generator individually and the Emergency Power Supply System (EPSS) as a whole (3 generators and RussElectric paralleling switchgear), consisting of the following minimum requirements:

1. Individual Generator Functional Performance Testing (Stage 1 Isolated Load Bank Testing):

a. Verify Base Engine Parameters: Ensure each engine starts and comes up to rated frequency (60 Hz), voltage (480/277V), and speed (1800 RPM).

b. Verify ECU-to-Engine Control: Ensure the new MTU ECUs, pulse-controlled fuel injectors, harnesses, and Marathon DVR 2400 voltage regulators communicate properly with the prime mover and accurately control engine parameters.

c. Verify ECU-to-Switchgear Communication: Ensure the new ECUs communicate properly with the existing RussElectric PLC controls on the paralleling switchgear.

d. Full-Capacity Load Bank Test (NFPA 110): Utilize Contractor-furnished temporary exterior resistive/reactive load banks and temporary feeder cables to load-test each generator individually to full nameplate rating (910 kW / 0.8 PF) and verify stable voltage, frequency, and thermal performance prior to placing units onto the live hospital bus. (The Government will provide diesel fuel from the bulk storage system).

2. Integrated EPSS Functional Performance Testing (Stage 2 System & Building Load Testing):

a. Black Start & 10-Second Transfer Simulation: Simulate a loss of utility power (black start) and verify that the EPSS comes online, synchronizes, and Automatic Transfer

Switches (ATSs) transfer critical hospital loads within 10 seconds per NFPA 110 Level 1 / Type 10 requirements.

b. Paralleling & Load Sharing: Utilize load banks and/or coordinated dynamic building loads (operated by NMCCL FACMAN staff) to verify that the RussElectric paralleling switchgear PLCs properly command each generator, synchronize units onto the bus, and proportionally share load and execute load-shedding/load-adding sequences as designed.

c. PLC Monitoring & Safety Alarms: Verify that all RussElectric PLC monitoring, annunciation, and safety alarm/shutdown capabilities are functioning as intended (e.g., fuel levels, overspeed, high engine temperature, low oil pressure, voltage/frequency faults).

d. Retransfer & Cooldown: Upon simulated restoration of commercial utility power, verify that the ATSs smoothly retransfer load back to utility power and that the EPSS commands the generators to enter their programmed cooldown period prior to automatic shutdown.

3. Closeout Deliverables:

Upon completion of testing, the Commissioning Agent and Contractor shall provide the final signed NFPA 110 commissioning and functional test report, updated as-built wiring diagrams, O&M manuals per Section 01 78 23, and staff training in accordance with Section 4.b of the SOW.

2. All other terms and conditions remain unchanged.