MCBI Industry Day 01-28-26.pptx
PPTX presentation 14 MB Posted
- Solicitation number
- N4008526R0053
About this file
This file is an Industry Day presentation for the FY26 Marine Corps Barracks Repair by Replacement Initiative held on January 28, 2026. The presentation outlines a two-package Design-Build (DB) procurement strategy for Bachelor Enlisted Quarters (BEQ) construction and renovation across four Marine Corps installations. Package 1 encompasses Marine Corps Air Station (MCAS) Cherry Point with three new 3-4 story BEQ buildings containing 720 total 2+0 rooms (approximately 153,405 gross SF per building) and demolition of five existing structures. Package 2 includes four buildings at Marine Corps Base (MCB) Camp Lejeune (Hadnot Point and French Creek) and one building at MCAS New River, totaling 565 rooms across multiple buildings. All projects involve new construction, site improvements (roadways, parking, sidewalks, utilities), demolition of existing BEQs, and site amenities (covered picnic shelters, fire pits, equipment washdown areas, bicycle storage, and HIIT areas).
The procurement utilizes a two-phase Best Value Source Selection (BVSS) approach with a maximum of three firms advancing to Phase 2. Phase I RFP will be issued February 23, 2026, with proposals due April 14, 2026, evaluating technical approach, corporate experience, past performance, and safety. Phase II RFP will be released May 6, 2026, with proposals due July 14, 2026, evaluating technical solution, schedule, small business participation, and price. Contract award is anticipated September 30, 2026, with a 48-month performance period. The project cost range exceeds $500 million per package and is funded through Operations and Maintenance. The presentation identifies NAVFAC Mid-Atlantic as the contracting authority, with Clark Nexsen and Michael Baker as the joint venture design team.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Barracks Industry Day Roster.docx | DOCX document | |
| 2026 Barracks Repair by Replacement Industry Day Flyer - Updated.pdf | ||
| Attachment 1 - Registration Form.docx | DOCX document | |
| 2026 Barracks Repair by Replacement Industry Day Flyer.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FY26 Marine Corps Barracks – Repair by Replacement Jacksonville, NC
INDUSTRY DAY
28 January 2026 0900-1200
AGENDA
Time Action Presenter 0830 Attendee Check-In
| 0900 | Opening Remarks/Introductions | NAVFAC Contracting | |
| 0905 Ground Rules and Goals | NAVFAC Contracting | ||
| 0910 Program/Project Overview | NAVFAC PM/Design Team | ||
| 1045 Procurement Strategy | NAVFAC Contracting | ||
| 1100 | Questions | NAVFAC Contracting/Design Team | |
| 1200 | Adjourn |
INTRODUCTIONS
Kimberly Kahler; Chief of the Contracting Office, NAVFAC Mid-Atlantic Philip Cole; Contracting Officer, NAVFAC Mid-Atlantic Kurt Bezeau; Project Manager, NAVFAC Mid-Atlantic Katie Sakai; Project Manager, NAVFAC Mid-Atlantic Robert Huntoon; Design Production Coordinator, NAVFAC Mid-Atlantic
Brian Snyder, PE; Managing Principal, CN / MBI JV Lacey Craven, RA; Senior Project Manager, CN / MBI JV Kallyn Maddox, RA; Project Architect, CN / MBI JV Joe Blickenderfer, PE; Project Civil Engineer, CN / MBI JV Don Dasher, PE; Project Manager, CN / MBI JV
GROUND RULES
This meeting is informational and for planning purposes only.
This is not a Request For Proposal (RFP). Discussions today will not be evaluated in response to any future requests for proposals.
Do not provide the Government with proprietary information, trade secrets, or any other information deemed source selection sensitive, or information that you do not want disseminated to the public.
Effort that any contractor/entity expends on this effort is at its own time, risk, and expense.
Hold all questions until the end of the presentation.
Everything you see today is a DRAFT and is subject to change.
INDUSTRY DAY GOALS
Notify the Industry of the upcoming solicitations for the FY26 Marine Corps Barracks Repair by Replacement at multiple locations:
MCB Camp Lejune and MCAS New River MCAS Cherry Point
Inform Industry of the scope and possible construction challenges for the project.
Solicit private sector input to help shape the project procurement.
CLARK NEXSEN / MICHAEL BAKER JOINT VENTURE
PROJECT PRESENTATION
Marine Corps Barracks Initiative Repair by Replacement
FY 26 DB RFP
Norfolk Naval Station MCBI – FY26 Repair by Replacement
PROJECT OVERVIEW
Repair by Replacement projects at 4 locations:
MCB Camp Lejeune – Hadnot Point MCB Camp Lejeune – French Creek MCAS New River MCAS Cherry Point
DB RFP ORGANIZATION
DB RFP with Standard Design Approach:
Part 2 General Requirements Per Installation specific requirements Part 3 Project Program “A” Standard Requirements - Standard requirement for all projects “B” Site Supplement – Unique to each project site Part 4 Performance Technical Specifications (PTS) Reference WBDG.org Part 5 Prescriptive Specifications Standard requirement for all projects Part 6 Attachments Unique to each project site No bridging / concept documents
PROJECT DESCRIPTION
The function of the Marine Corps 2+0 room Bachelor Housing quarters is to provide unaccompanied military personnel with adequate, comfortable housing.
The USMC standard 2+0 room layout shown must be used.
GFGI Furniture Package Terminal Air Conditioner (PTAC) or Heat Pumps (PTHP) as specified in Part 5 Prescriptive Specification
Comply with UFC 4-721-01, FC 4-721-10N, and installation specific BEAP for standard requirements (provided in Part 6).
PROJECT DESCRIPTION
Each BEQ will contain standard common areas, to include:
Multi-Purpose Room with Quiet Room Laundry (GFGI Equipment) Centralized Kitchen (GFGI Equipment) Marine Corps Exchange (MCX24) (GFGI Equipment) Duty Desk Duty Bunk Admin Office Intended adjacencies and access between ground floor entry, circulation, and common areas should be as shown.
PROJECT DESCRIPTION
Intended layout and sizing for the MCX24 (GFGI Equipment).
PROJECT OBJECTIVES – HADNOT POINT
New Construction 3 story BEQs to contain 300 total 2+0 rooms 2 buildings of (150) 2+0 rooms each Approx. 97,799 gross SF per building
Site Improvements Roadways, parking areas, and fire lanes Sidewalks with site lighting Concrete dumpster pads with enclosures
Demolition BEQs HP51, HP53, HP55, and HP57
Site Amenities Covered picnic shelter areas equipped with tables and barbecues Fire pits Equipment washdown and drying areas Bicycle storage Seating areas High-intensity interval training (HIIT) areas
PROJECT LOCATION – HADNOT POINT
New BEQ Site Demo Sites
PROJECT LOCATION – DEMO SITES
HP 57
HP 55
HP 53
HP 51
PROJECT LOCATION – HADNOT POINT BEQ SITE
Re-route existing water maximizing buildable area Existing sewer tie-in Re-route existing sewer maximizing buildable area Maintain access to existing operational facility Re-route existing storm sewer maximizing buildable area Note: Utility line markings are for information purposes only.
Site limits G Street Holcomb Blvd
PROJECT PHASING – HADNOT POINT
PHASE 1:
Construct BEQs & site amenities
Allow 120 days for GFGI FF&E & Occupancy by Residents
PHASE 2:
Demo 4x BEQs -HP51, HP53, HP55, & HP57
PROJECT OBJECTIVES – FRENCH CREEK
New Construction 3 story BEQ to contain 85 total 2+0 rooms 1 building Approx. 57,854 gross SF
Site Improvements Roadways, parking areas, and fire lanes Sidewalks with site lighting Concrete dumpster pads with enclosures
Demolition
BEQ 1340
Fire pits Equipment washdown and drying areas Bicycle storage
PROJECT LOCATION – FRENCH CREEK
Demo Site
PROJECT LOCATION – DEMO SITE
BLDG 1340
PROJECT LOCATION – FRENCH CREEK BEQ SITE
Tie to existing sanitary sewer main Note: Utility line markings are for information purposes only.
Site limits
Tie to existing water main Existing operational facility to remain Existing permitted SWM facility. Do not disturb.
ConnerStreet Gonzalez Blvd H M Smith Blvd
PROJECT PHASING – FRENCH CREEK
Construct BEQ & site amenities
Demo 1x BEQ Bldg 1340
PROJECT OBJECTIVES – NEW RIVER
New Construction 3-4 story BEQ to contain 180 total 2+0 rooms 1 building Approx. 116,235 gross SF
Site Improvements Roadways, parking areas, and fire lanes Sidewalks with site lighting Concrete dumpster pads with enclosures
Demolition AS4024 (New River HIIT Center) BEQ AS4200, support building AS4201
Fire pits Equipment washdown and drying areas Bicycle storage
PROJECT LOCATION – DEMO SITE
BLDG AS4200
PROJECT LOCATION – NEW RIVER BEQ SITE
Site limits
Existing storm water ditch Tie to existing water main Tie to existing sewer main Demo BLDG AS4024 Existing electrical line and sanitary sewer. Do not disturb.
Existing storm water canal to regional infiltration basin (SW 8210702) Limit tree disturbance.
Campbell Street Schmidt Street Canal Street
PROJECT PHASING – NEW RIVER
Demo AS4024 HIIT Center
Construct BEQ & site amenities
PHASE 3:
Demo 1x BEQ Bldg AS4200 & Support Bldg AS4201
PROJECT OBJECTIVES – CHERRY POINT
New Construction 3-4 story BEQs to contain 720 total 2+0 rooms 3 buildings of (240) 2+0 rooms each Approx. 153,405 gross SF per building
Site Improvements Roadways, parking areas, and fire lanes Sidewalks with site lighting Concrete dumpster pads with enclosures
Demolition BEQs 4312, 4201, 4199, 4294, 4295
Fire pits Equipment washdown and drying areas Bicycle storage
PROJECT LOCATION – CHERRY POINT
Demo Site
PROJECT LOCATION – DEMO
BLDG 4312
BLDG 4201
BLDG 4199
BLDG 4294
BLDG 4295
PROJECT LOCATION – BEQ SITE
Site limits
Replace existing sanitary sewer main and tie laterals to new line Tie laterals to existing water main Remove existing steam lines throughout the site E Street
PROJECT PHASING – CHERRY POINT
Demo 4x BEQs Bldgs – 4312, 4199, 4201 & 4294
Reroute/ Replace existing sanitary sewer
PHASE 3: Construct BEQs & site amenities
PHASE 4: Demo 1x BEQ 4295
Procurement Strategy Two-Phase Design-Build Procurements (2 separate packages):
– Best Value Source Selection (BVSS) using Trade-Off Procedures.
– Phase 1 Evaluation: Technical Approach, Corporate Experience, Past Performance and Safety.
– Phase 2: Technical Solution, Schedule, Small Business Participation and Price.
– A maximum of 3 of the most highly qualified firms will be selected to participate in Phase 2.
Note: Dates and acquisition strategy are still in refinement, and subject to change. Source selection evaluation factors will be specifically defined in each solicitation.
Procurement Timeline Issue Phase I Request for Proposal (RFP) – 23 Feb 26 Phase I Proposals due – 14 April 26 Phase II Proposal RFP – 6 May 26 Phase II Proposals due – 14 July 26 Contract Award – 30 September 26
Contract Duration – 48 months
Funding – Operations and Maintenance
Note: The due date for the Phase II Proposals will likely be staggered between the two packages allowing firms to focus on submitting one proposal at a time.
ANY QUESTIONS?
Any additional questions can be submitted in writing to: brittany.n.cristelli.civ@us.navy.mil and Philip.j.cole.civ@us.navy.mil image2.jpeg image3.png image4.jpeg image5.png image6.png image7.png image8.png image9.png image10.jpeg image11.jpeg image12.png image13.png image14.png image15.jpeg image16.png image17.png image18.png image19.jpeg image20.png image21.png image22.jpeg image23.png image24.jpeg image25.png image26.png image27.jpeg image28.png image1.jpeg