Amend 0001.pdf

PDF 160 KB Posted

Attached to
Building 128 Grounds Improvements Federal contract opportunity
Solicitation number
N4008525R2650
Issued by
Department of the Navy Naval Facilities Engineering Command

About this file

This document is an Amendment (Amendment 0001) to Solicitation N40085-25-R-2650 for Building 128 Ground Improvements at Camp Lejeune. The amendment addresses several key contractor questions and updates the proposal submission deadline to 1400 on 22 April 2025.

The amendment provides clarifications about pond excavation, including permission to dewater the existing pond, requirements for restoring the water level, and disposal of pond spoils. Specifically, contractors can use the base landfill for surplus soil, provided the material is free of debris and contaminants. Notable requirements include screening soil to remove objects larger than 3 inches, coordinating with the Landfill Manager, and submitting photographic documentation and volume certification. The amendment also confirms there are no known hazardous soils and no geotechnical report was conducted for the project site.

View the file

Other files for this federal contract opportunity

Other files attached to Building 128 Grounds Improvements, newest first.
File Type Posted
N4008523B0029 Specs.pdf PDF
N4008523B0029 Dwgs.pdf PDF
RFP N40085-25-R-2650.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICIATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 11)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPIRATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

1 2

AMENDMENT NO. 0001 04/09/25 23-0029

N40085

NAVFAC Mid-Atlantic Resident Officer in Charge of Construction 1107 A Birch Street Camp Lejeune, NC 28547-2521

See Item 6

✘ N40085-25-R-2650

03/13/25

23-0029, Bldg 128 Ground Improvements

Amendment 0001, Answer Requests for information and change proposal due date

The time and date for receipt of proposals is changed to 1400, 22 April 2025.

This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of a proposal.

See Continuation Page(s)

N40085-25-R-2650 Amendment 0001

CONTINUATION SHEET

1. QUESTION: Can the existing pond be dewatered via the existing outlet structure in order to facilitate pond excavation to permitted design depths?

ANSWER: Yes, provided that dewatering activities do not release turbid water from the project site.

2. QUESTION: If pond dewatering is allowed, will the contractor be responsible for raising the water level to the previous pool elevation?

ANSWER: Yes the pond should be restored to design permanent pool elevation.

3. QUESTION: Is there any known hazardous or contaminated soils associated with the proposed pond excavation?

ANSWER: There are no known hazardous or contaminated soils associated with proposed pond excavation scope. If contaminants are suspected through odors or visual observation during construction activities, immediately stop work, call 911, and contact Environmental Compliance Branch (ECB) at 910-451-9641 for further instructions.

4. QUESTION: Can the pond spoils and sediment be taken to the base landfill?

ANSWER: Yes, provided that spoils are free of debris, are not contaminated, and meet the following directions:

Transport all surplus soil to the designated location on government property. No surplus material will leave government property without approval of installation Environmental Program Manager and the Contracting Officer.

• Area managed by PWD for use as daily cover:

• Base landfill, located on Piney Green Road, approximate coordinates

34°41'26.9"N 77°19'27.4"W.

• Contractor shall provide temporary silt fencing around designated stockpile areas as needed.

• Coordinate with Landfill Manager at (910) 451-8666. Landfill use letters will be provided so that deliveries can be tracked.

• This site operates Monday through Thursday between 0730 and 1500 and on

Friday between 0700 and 1400.

Contact POCs listed above 7 to 10 days in advance to coordinate delivery of material at the storage locations.

Prior to transportation to the designated location, screen all surplus soil to remove all objects greater than 3 inches and deleterious material. Deleterious material consists of organic debris such as roots, stumps, timber, and construction debris. Construction debris shall include, but is not limited to wood, plastic, glass, concrete, brick, and metal. Dispose of deleterious material and objects larger than 3 inches in accordance with Section 01 57 19 Temporary Environmental Controls.

Provide all plant, material, and labor for placement and management of the surplus material at the designated locations. Grade surplus material to a flat condition and slope to provide positive drainage daily. Submit the following verification documents to the Contracting Officer for review and approval:

1) Photographic documentation that surplus soil has been properly placed. Photograph will include time and date of image.

2) Certification statement indicating volume, in cubic yards (CY), of material delivered and confirming material is free of contaminants.

NOTE: Soil contaminated with debris or chemicals cannot be disposed at the stockpile location.

If contaminated soils are suspected or confirmed through presence of UXO, odors, or visual staining, affected soils must be properly tested, manifested, and disposed of in accordance with RCRA regulations. Contact Base EMD, ER Program Manager, for more information.

5. QUESTION: Is a geo-technical report available for this project/site?

ANSWER: No geotechnical investigation was not conducted for this project/site.

6. All other terms and conditions remain unchanged.