25R0067 AMENDMENT_0002.pdf

PDF 244 KB Posted

Attached to
REPLACE PAD MOUNTED TRANSFORMER, BUILDING 530, NAS OCEANA, VA BEACH, VA
Solicitation number
N4008525R0067
Issued by

About this file

This document is a Standard Form 30 Amendment of Solicitation/Modification of Contract for Solicitation N40085-25-R-0067, issued by NAVFAC (Naval Facilities Engineering & Acquisition Division) Mid-Atlantic. The amendment is for a project to replace a pad mounted transformer at Building 530, Naval Air Station (NAS) Oceana in Virginia Beach, Virginia. The primary purpose of the amendment is to provide PPI (Probable Pricing Information) Responses and extend the proposal due date from 11 August 2025 at 2:00PM EDT to 14 August 2025 at 2:00PM EDT. An Adobe PDF PPI spreadsheet with NAVFAC's response has been posted on SAM.gov for potential bidders to review.

View the file

Other files

File Type Posted
PPI Spreadsheet_NAVFAC Response.pdf PDF
25R0067 AMENDMENT_0003.pdf PDF
25R0067 AMENDMENT_0001.pdf PDF
PROVISION 52.204-24.pdf PDF
BASE ACCESS INSTRUCTION.pdf PDF
1832302_B530 NASO REPLACE PAD MOUNTED TRANSFORMER_FINAL DBRFP_SIGNED.pdf PDF
PPI Spreadsheet.xlsx XLSX spreadsheet
BLANK SPONSOR VERIFICATION SPREADSHEET.xls XLS spreadsheet
SECNAV 5512.pdf PDF
WAGE DETERMINATION.txt TXT text file
N400852R0067 GENERAL REQUIREMENTS .pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

J

PAGE OF PAGES

1 2

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. P ROJECT NO.(If applicable)

6. ISSUED BY CODE N4008 7. ADMINISTERED BY (If other than item 6) CODE

See Item 6

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X 9A. AMENDMENT OF SOLICITATION NO.

X 9B. DATED (SEE ITEM 11)

10A. MOD. OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICAT IONS OF CONT RACTS/ORDERS.

IT MODIFIES T HE CONT RACT /ORDER NO. AS DESCRIBED IN ITEM 14.

A. T HIS CHANGE ORDER IS ISSUED PURSUANT T O: (Specify authority) THE CHANGES SET FORT H IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONT RACT /ORDER IS MODIFIED TO REFLECT THE ADMINIST RAT IVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO T HE AUT HORIT Y OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORT ANT : Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT /MODIFICAT ION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

TEL: EMAIL:

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

BY

(Signature of Contracting Officer)

16C. DATE SIGNED

EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

30-105-04 ST ANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

0002 11-Aug-2025 ACQR6087172

N40085-25-R-0067

08-Jul-2025

SOLICITATION N40085-25-R-0067, REPLACE PAD MOUNTED TRANSFORMER, BUILDING 530, NAS OCEANA, VIRGINIA BEACH, VIRGINIA

The purpose of this amendment is to provide the PPI Responses and extend the proposal due date.

***Receipt of Proposal due date is 14 August 2025 at 2:00PM EDT.***

SEE CONTINUATION PAGE.

11-Aug-2025

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

(End of Summary of Changes)

N40085-25-R-0067

SOLICITATION N40085-25-R-0067, REPLACE PAD MOUNTED TRANSFORMER, BUILDING 530, NAS

OCEANA, VIRGINIA BEACH, VIRGINIA

The purpose of this amendment is to provide the PPI Responses and extend the Proposal due date.

Attachment:

1) Adobe PDF - PPI Spreadsheet_NAVFAC Response

The Attachment has been posted on SAM.gov.

Proposal due date has changed:

FROM:

11 August 2025 at 2:00PM

TO:

14 August 2025 at 2:00PM

Page Section Para. Dwg #

The breakers appear to be the service entrance and main distribution equipment for the building. UFC requires a main circuit breaker for service equipment. UFC also requires 15% empty space and 15% spare capacity (ampacity) for all panelboards, switchboards, etc. Does a load study need to be performed to size the panelboard or will historic load information (meter data) be provided to properly size the new equipment?

Historical load information is not available.

Follow the guidance provided in UFC 3-501-

01, Design Analysis and Documentation. For paragraph 3-2.2.2, only the calculations necessary for the new equipment.

UFC 3-520-01 3-2.2 requires a switchboard for service equipment when over 1200-amps. I don’t think there is a manufacturer that makes a panelboard over 1200-amps. Please confirm that a new exterior mounted switchboard should be provided as the new main service and distribution equipment.

Yes, if a panelboard is not available, an exterior mounted switchboard would be acceptable.

3 RFP PART 3

SEC

G4010

RFP Part 3, G4010, states: “Provide and install new transformer with a secondary compartment with panelboard and new circuit breakers on new concrete equipment pad.” Designer notes under UFGS Section 26 12 19, 2.2.1.3 state:

“Installation of circuit breakers in the secondary compartment is not recognized by IEEE standards, and limits accessibility by covering lugs, gages, and accessories.

Do not use.” Please confirm that new “panelboard” (or other main service and distribution equipment) will need to be installed outside of the secondary compartment of the new transformer.

Yes, secondary distribution equipment can be installed outside of the secondary compartement.

Please confirm the impedance of the existing transformer.

See Part 6 Photos of the RFP for transformer label plate information (page 171 of 210).

Project Title: REPLACE PAD MOUNTED TRANSFORMER, B530, NASO Solicitation / RFP#: N4008525R0067 - PPI Cut Off Date: 25JULY2025

Amend No.GOVERNMENT RESPONSEPPI No. Offeror Date Submitted

REFERENCE QUESTION

New service transformer, new main circuit breaker and new distribution circuit breakers will all affect detailed arc flash labels. Please confirm whether or not the activity has an arc flash risk assessment program that would require updated are flash labels in accordance with UFC 3-560- 01 1-12.3.

Activity does not have an arc flash risk assessment program.

New service transformer will affect the available fault current at every point in the electrical system unless the impedance of the existing transformer is matched.

Please confirm that a complete short circuit analysis is required unless existing impedance is matched.

Follow the guidance provided in UFC 3-501- 01 for short Circuit Analysis applicable to new equipment.

NEC 2023 620.62 requires selective coordination of elevator disconnect

OCPDs with all supply side OCPDs where more than one elevator is supplied by the same source. Please confirm whether or not the existing elevator disconnect supplies more than one elevator.

The building has one elevator.

RFP Part 3, G4010, states: “Provide and install new secondary conductors from the secondary compartment to ACC-1 and to the elevator motor control panel.”

If the new service entrance equipment is the new “panelboard” supplying MDPs and Chiller, each of these other disconnects would be considered another service. NEC 2023 230.2 allows multiple services for a single building in certain circumstances. It doesn’t appear this building falls under one of those circumstances. Please confirm whether of not the new service equipment (probably switchboard not panelboard) should be sized to supply ACC-1 and the elevator.

Our interpretation is that this building falls under NEC Article 230.2 (B)(1) and (3)(3) and can have multiple services. That aside, the intent of the RFP is to have the switchboard sized to include ACC-1 and the elevator.

Will civil/topo survey be required as part of the design package?

A civil/topo survey is not required to be part of the design package. Determine existing grade elevations as required to place the concrete slab such that the top of slab elevation meets the requirements of the RFP.

~Response by Jason Picano

10 Are building/site CAD files available? Building/site CAD files are not available.

Sheet1

File details come from the government source that posted it. Updated .