24-0702 WARNING SIGN AND CAUTION BUOY INSTALLATION - SUBMITTAL REGISTER.pdf

PDF 46 KB Posted

Attached to
Warning Sign and Buoy Installation
Solicitation number
N4008524R2783
Issued by

About this file

This document is a Submittal Register for Contract No. a2e6a0fe93834d9ca70e2318b90ebf08. It lists the various submittals required under this contract, including administrative documents (e.g. accident prevention plan, schedule, contacts), technical submittals (e.g. crane work plans, equipment delivery schedule), and closeout documents (e.g. DD1354 form, submittal register). The key products or services required under this contract appear to be related to the installation of warning signs and caution buoys. The contract is being issued by the Naval Facilities Engineering Command, and only contractors on the approved General Requirements cover page may submit proposals. No other specific details about the contract opportunity, such as pricing terms, set asides, or incumbents, are provided in this document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT NO.

CONTRACTOR

SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A

C

T

I

O

N

C

O

D

E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A

C

T

I

O

N

C

O

D

E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

01 20 00

1.3

01 30 00

1.4.1

01 31 50

1.2

01 32 16

1.2

1.3

01 33 00

1.4.1

1.6.1

01 35 29

1.9

1.10

1.9.1

1.9.1

1.7.1.4

1.14

1.14.1

1.14.3

1.14.4

1.14.5

1.11

Crane Reports

SD-07 CERTIFICATES

Confined Space Entry Permit

Approving Authority Contractor

Schedule Dates

SD-11 CLOSEOUT SUBMITTALS

Interim DD1354, Transfer & Acceptance

SD-11 CLOSEOUT SUBMITTALS

Submittal Register

Complete Submittal Package

TITLE AND LOCATION

Lighting Inverter Replacement G644

Schedule of Prices

List of Contact Personnel

Construction Schedule of Military Real Property (If Applicable)

A

C

T

I

V

I

T

Y

N

O

T

R

A

N

S

M

I

T

T

A

L

N

O

(d)

Contractor

Action

DESCRIPTION

ITEM SUBMITTED

(Enter Contractor Name Here)

Crane Work Plan (If Applicable)

Activity Hazard Analysis (AHA)

SD-06 TEST REPORTS

SD-01 PRECONSTRUCTION SUBMITTALS

23-0401

SD-01 PRECONSTRUCTION SUBMITTALS

Accident Prevention Plan (APP)

SD-01 PRECONSTRUCTION SUBMITTALS

Equipment Delivery Schedule

SD-01 PRECONSTRUCTION SUBMITTALS

SUBMITTAL REGISTER

P

A

R

A

G

R

A

P

H

N

O

S

P

E

C

S

E

C

T

C

L

A

S

S

I

F

I

C

A

T

I

O

N

G

O

V

T

O

R

A

E

R

E

V

W

R

Crane Critical Lift Plan (If Applicable)

Crane Operators (If Applicable)

Reports

Accident Reports

Monthly Exposure Reports

Regulatory Citations and Violations

1.14.6

1.14.7

01 45 10

1.6

01 50 00

1.6.2.1

2.1

3.1

1.3

01 57 19

1.6.1

1.6.4

1.7.2

1.7

1.7

PAGE 1 OF _

Third Party Certification of Barge-

Mounted Movile Cranes

SD-11 CLOSEOUT SUBMITTALS

Qaulity Control Plan (QC Plan)

Certificate of Compliance

Backflow Tester Certification (If Applicable)

Backflow Preventer Tests (If Applicable)

SD-01 PRECONSTRUCTION SUBMITTALS

Traffic Control Plan (If Applicable)

SUBMITTAL FORM, JAN 96 PREVIOUS EDITION OBSOLETE

MSDS for Class I ODS Waivered Product

SD-01 PRECONSTRUCTION SUBMITTALS

Permit for Storm Water Discharge (If applicable)

Environmental Protection Plan

Preconstruction Survey

Notice of Intent (If applicable)

SD-03 PRODUCT DATA

Backflow Preventers (If Applicable)

Backflow Preventers Certificate (If Applicable)

SD-06 TEST REPORTS

SD-07 CERTIFICATES

File details come from the government source that posted it. Updated .