Synopsis Amendment 0003.pdf
PDF 133 KB Posted
- Solicitation number
- N4008524R2674
About this file
This document is an amendment to a synopsis for an Indefinite Delivery/Indefinite Quantity (IDIQ) contract for architect-engineer (A-E) services for mechanical, electrical, and plumbing (MEP) projects primarily located in the Marine Corps Area of Responsibility (AOR). The amendment provides responses to pre-proposal inquiries, confirms the SF330 submission due date, and maintains the deadline for receipt of pre-proposal inquiries. The contract will be a total small business set-aside with a NAICS code of 541330, Engineering Services, and a size standard of $25.5 million. The contract is estimated to have a $60 million ceiling over 5 years, with a $5,000 guaranteed minimum. Typical task orders are expected to range from $50,000 to $500,000, with resulting construction costs of $500,000 to $5 million. The contract will require A-E services such as design, studies, and construction support for a variety of facility types and MEP systems. Key evaluation criteria include specialized experience, professional qualifications, past performance, quality control, program management, and volume of prior DOD work.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N40085-24-R-2674 INDEFINITE QUANTITY/INDEFINITE DELIVERY CONTRACT FOR
ARCHITECT-ENGINEER SERVICES FOR MECHANICAL, ELECTRICAL, AND
PLUMBING IN SUPPORT OF PROJECTS PRIMARILY LOCATED IN THE MARINE
CORPS AREA OF RESPONSIBILITY
AMENDMENT 0003 – 13 SEPTEMBER 2024
The purpose of this amendment is to provide:
I. Pre-Proposal Inquiry (PPI) responses
II. The SF330 Submission Due Date of 23 September 2024 NLT 2:00 PM EDT remains unchanged.
III. PPI Deadline remains unchanged.
I. Pre-Proposal Inquiry Responses
Question 16. Please confirm if the "ATTACHMENT D - PROJECT INFORMATION FORM" is to replace the SF330, PART I, SECTION F, Project Page in our submission to the
Government. (Reference: Pre-Proposal Inquiry Responses, Question/Response #14) –
Response: As stated in Amendment 0002, Question 14 response, “your firm MAY complete this form for each project to provide ADDITIONAL clarity pertaining to completion dates.”
Attachment D DOES NOT replace SF330, PART I, SECTION F. SF330 PART I, SECTION F is required per the Synopsis.
II. The SF330 submission due date of Monday, 23 September 2024 NLT 2:00 PM EDT remains unchanged.
III. The deadline receipt of PPIs from Offerors is Friday, 13 September 2024 NLT 2:00PM
EDT. Responses to RFI’s received after this time may not receive a response.
-End of Amendment-
File details come from the government source that posted it. Updated .