This document is Amendment 0001 to Solicitation N4008524R2620 for the replacement of the fire alarm system in Building 536, a Bachelors Enlisted Quarters (BEQ), at Naval Air Station Oceana in Virginia Beach, Virginia.

The amendment provides answers to pre-proposal inquiries, adds a Site Visit Attachment, and makes technical changes to the scope of work. The key details include:

  • No CAD drawings for the building are available
  • The firestopping system installation and testing must occur within the same construction phasing and sequencing as the fire alarm system
  • The contractor must coordinate with the existing NASO fire protection maintenance contractor for any required fire protection related outages
  • The fire alarm system must be an analog/addressable, voice evacuation combination fire alarm mass notification system
  • The system must transmit alarms to the local/regional dispatch center and integrate with the basewide mass notification system
  • Specific requirements are provided for wiring, device types, control panel location, and other system components
  • The Navy's Fire Protection Engineer must review and approve submittals and witness the final inspection/acceptance test

View the file

Other files

File Type Posted
AMENDMENT 0002 N4008524R2620.pdf PDF
1735431 Reference Drawings-OC B-536_Unaccompanied Enlisted Personnel Housing_1984.pdf PDF
ATTACHMENT K SITE VISIT.pdf PDF
E BLANK SPONSOR VERIFICATION SPREADSHEET.xls XLS spreadsheet
B WDva2024167.pdf PDF
A 1735431 DB-RFP PACKAGE.pdf PDF
C BASE ACCESS INSTRUCTION.pdf PDF
I Oceana IDIQ Front End SPECS - 20220602.pdf PDF
F PPI Spreasheet.xlsx XLSX spreadsheet
D SECNAV 5512.pdf PDF
J Basemap_N60191.pdf PDF
H PROVISION 52.204-24.pdf PDF
GENERAL REQUIREMENTS B536 NASO.docx DOCX document
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

J

PAGE OF PAGES

2. AMENDMENT/MODIFICATION NO.

3. EFFECTIVE DATE

25 MAR-2024

4. REQUISITION/PURCHASE REQ. NO.

ACQR6033955

5. P ROJECT NO.(If applicable)

CODE N40085 7. ADMINISTERED BY (If other than item 6) CODE 6. ISSUED BY

NAVFACSYSCOM MID-ATLANTIC

OCEANA

FACILITIES ENGINEERING & ACQ DIV

953 HORNET DR SUITE 213

VIRGINIA BEACH VA 23460-2190

See Item 6

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X 9A. AMENDMENT OF SOLICITATION

NO. N40085-24-R-2620

X 9B. DATED (SEE ITEM 11)

13-March-2024

10A. MOD. OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X is not extended. The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue ofthis amendment you desire to change an offer already submitted, such change may be made by telegramor letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES T HE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. T HIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO T HE AUT HORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORT ANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

SOLICITATION N40085-24-R-2620, Replace Fire Alarm System, BLDG 536, NAS OCEANA, VIRGINIA BEACH, VA

The purpose of this amendment is to answer Pre-Proposal Inquiries (PPI's), Add SITE VISIT Attachment and Add TECHNICAL CHANGES.

SEE CONTINUATION PAGE(s)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

TEL: EMAIL:

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

BY

(Signature of Contracting Officer)

16C. DATE SIGNED

25 March-2024

EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

30-105-04 ST ANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

of 5

N40085-24-R-2620 0001 Page 2 of 5

SECTION SF 30

BLOCK 14 CONTINUATION PAGE SUMMARY OF CHANGES

The following have been added by full text:

Amendment 0001

PRE-PROPOSAL INQUIRIES

1) PPI #1:

QUESTION: Is the government able to provide CAD drawings for the building to assist with design?

RESPONSE: No CAD drawings for Building 536 are available.

ATTACHMENT

2) Add Attachment K: SITE VISIT Sign–In Sheet.

TECHNICAL CHANGES

3) In the SCOPE OF WORK, Part 3, C1030 SPECIALTIES, Firestopping Systems, after the last paragraph:

ADD the following paragraph:

“Firestopping system installation and testing must fall within the same construction phasing and sequencing requirements as the fire alarm system.”

4) In the SCOPE OF WORK, Part 3, replace D40 FIRE PROTECTION SYSTEMS in its entirety with:

D40 FIRE PROTECTION SYSTEMS

Refer to Part 4 Section D40 for performance requirements of the building elements included in the fire protection systems.

SYSTEM DESCRIPTION

The facility is a 3-story BEQ with a core and two residence wings, totaling approximately 123,199 sq.ft. There is a direct hydraulic elevator in the core that travels from first through third floors. The elevator machine room is on the first floor. The facility does not have a dedicated fire pump or

0001 Page 3 of 5 generator.

GENERAL SYSTEM REQUIREMENTS

The Contractor must coordinate all work related to the Fire Protection System with the Contracting Officer, Base Fire Department and local/regional dispatch center. During disconnection and demolition work, as stated elsewhere within the RFP, there must be no loss of alarm transmitting or receiving capability. If temporary interruption of individual alarm connections will have to occur in order to perform the work, it must be minimized and must be approved by the Contracting Officer and Base Fire Department prior to work being performed.

Interruption of alarm or communications functions at the local/regional dispatch center is prohibited.

The Contractor must be responsible to engage and coordinate ALL required Fire Protection related outages with the “existing NASO fire protection maintenance contractor”. The successful bid must include all associated costs and fees incurred by the “existing NASO fire protection maintenance contractor” to perform all required Fire Protection related outages for the project.

Provide working space around all equipment. Provide all required fittings, connections and accessories required for a complete and usable system. Install equipment in accordance with the criteria of PTS section D40 and the manufacturer’s recommendations. Where the word "should" is used in the manufacturer's recommendations, substitute the word "must".

All Design Documents, (i.e. plans, specifications, phasing plan, and calculations) developed for Section D40 must be prepared by, or under the supervision of the design/build contractor's Qualified Fire Protection Engineer, the Fire Protection Designer of Record (FPDOR).

Construction documents must include the services of a Fire Protection Quality Control Specialist as detailed in Specification Section 01 45 00.00 20.

Installation drawings, shop drawings or working plans, phasing plan, calculations, other required pre-construction documentation and as-built drawings must be prepared by, or under the direct supervision of a National Institute for Certification in Engineering Technologies (NICET) engineering technician as specified below. NICET engineering technicians must hold a current certification as an engineering technician in the field of Fire Protection Engineering Technology with Level IV certification in the appropriate subfield.

A phasing plan must be prepared by or under the supervision of either the FPDOR or the FPQC and must minimize the duration of time residents are displaced. The phasing plan must be submitted at the same time as the design drawings and must be approved by the Contracting Officer and NAVFAC Midlant Fire Protection Engineer (FPE) before construction drawings are submitted.

Provide training for the systems consisting of one (1) four (4)-hour session to accommodate the maintenance staff and base fire department

D4010 FIRE ALARM AND MASS NOTIFICATION SYSTEMS

In according with Phasing requirements, demolish the existing fire alarm system in its entirety, including the connection to the telegraphic fire alarm reporting system (underground Gamewell loop). A fire alarm system and transmission to the local/regional

0001 Page 4 of 5 dispatch center must remain operable for occupied portions of the building as detailed in Phasing requirements.

Provide a new analog/addressable, voice evacuation combination fire alarm mass notification system capable of notifying building occupants inside and near the facility.

Other disciplines such as architectural, mechanical, electrical, etc. may have incidental work to support the fire alarm system replacement. Design in accordance with UFC 3- 600-01, UFC 4-021-01, and FC 1-300-09N.

Provide a radio transmitter compatible with the basewide fire alarm reporting system.

Oceana’s receiving station utilizes Monaco equipment. Collaborate to ensure continuity of alarm transmission from the local receiving station to the regional dispatch center.

Provide a radio transceiver compatible with the basewide mass notification system.

Oceana’s emergency management system utilizes Federal Signal equipment. Ensure continuity of messages from the emergency management system to the building and rebroadcast over the building speakers.

Provide Class A Notification Appliance Circuits and Class A Signaling Line Circuits. Any Class B Initiation Device Circuits must be less than 10 feet in length.

All wiring must be installed in conduit (EMT minimum). Minimum conduit size is ¾” except drops to individual devices may be ½”. Conduit may be reused if it complies with UFC 3- 600-01, but all wiring must be replaced.

Provide smoke detectors with sounder bases with 520 Hz low frequency in sleeping rooms. Provide detectors that do not require individual programming when they will be replaced (by government technicians) in the future.

Provide carbon monoxide (CO) detection in the mechanical room that contains fuel fired equipment. Prohibit multi-criteria CO detectors (disabling heat and smoke modes of multi-criteria is not permitted).

Provide duct smoke detectors for HVAC systems required by NFPA 90A and remove existing. Duct smoke detector activation must shut down respective HVAC units and also send a supervisory signal to the FMCP.

Test the water flow switches (or pressure switches) and tamper switches on the existing sprinkler risers. If switches do not function properly, provide new switches. The water motor gong and its piping must remain.

Provide manual pull stations at locations required by UFC 3-600-01. Manual pull stations installed outside in or near open stairwells must be weatherproof.

Provide notification appliances throughout the building as required by UFC 3-600-01 and

UFC 4-021-01. Prohibit addressable notification appliances.

Locate the fire alarm/mass notification control panel (FMCP) and all notification appliance circuit (NAC) booster panels in conditioned spaces. The front entrance has sufficient room in the South-East corner. NAC panels may also be located in the TV Lounge or the Recreation Room in the core’s second and third floors. NAC panels may not be located in

0001 Page 5 of 5 the mechanical rooms.

Locate the remote annunciator and local operating console (LOC) as directed by the Contracting Officer and the NAVFAC FPE.

All fire alarms, supervisory alarms and trouble conditions must transmit to the fire alarm receiving station. Transmitter zones must be coordinated with base fire department.

Transmitter zones include:

a. Sprinkler Water Flow

b. Smoke Detector

c. Manual Pull Station

d. Supervisory (i.e., valve tamper switch)

e. Duct Smoke Detector

f. Carbon Monoxide Detector

g. Sleeping Room Smoke Detector

NAVFAC FPE must review and approve all submittals for the fire alarm system.

NAVFAC FPE must witness and approve final inspection/acceptance test.

D4020 FIRE SUPPRESSION WATER SUPPLY AND

EQUIPMENT

Not used.

D4040 SPRINKLERS

Not used.

D4090 OTHER FIRE PROTECTION SYSTEMS

The facility’s fire rated walls must be identified in order to assist the firestop contractor.

The drawing showing the facility’s fire rated walls must be prepared by or under the supervision of either the FPDOR or the FPQC.

**End of Amendment 0001**

Amendment 0001 N4008524R2620
AMENDMENT_0001_N4008524R2620_FireAlarm B536
Amendment 0001
Amendment 0001

ATTACHMENT K SITE VISIT

File details come from the government source that posted it. Updated .