Attachment 1- HR Painting and Wall Covering IDIQ Specifications.pdf
PDF 1 MB Posted
- Solicitation number
- N4008524B2502
About this file
This is a solicitation for a regional indefinite delivery indefinite quantity (IDIQ) contract to provide interior and exterior painting, vinyl wall covering installation and removal, sandblasting, water blasting, lead abatement, and other maintenance services at various government sites in the Hampton Roads area of Virginia. The contract will have a one-year base period and four one-year options and will be awarded to a single contractor. Work will be ordered through task orders administered by six different military bases and will include services such as removal and installation of signs, gutters, and storm windows; wall preparation and repair prior to wall covering installation; blast cleaning; painting; and abatement of lead-based paint. Pricing is established through contract line items for pre-priced work and non-pre-priced line items for additional tasks. Invoices and progress payments are to be submitted monthly.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| OF 1419 Abstract PAGE 1 AND 2_Regional Painting.pdf | ||
| Updated Attachment 2- HR Paint and Wall Covering IDIQ ELINs.xlsx | XLSX spreadsheet | |
| Amendment 0001.pdf | ||
| Attachment 3 - PIEE Vendor Access Instructions.pdf | ||
| IFB N4008524B2502.pdf | ||
| Attachment 4 - Pre-Proposal Inquiry (PPI) Form.xlsx | XLSX spreadsheet | |
| Attachment 2- HR Paint and Wall Covering IDIQ ELINs.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Regional IDIQ Contract for Paintings and Coatings HRPAINTINGIDIQ
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 11 00 08/15, CHG 2: 08/21 SUMMARY OF WORK
01 14 00 11/22 WORK RESTRICTIONS
01 20 00 11/20, CHG 2: 08/21 PRICE AND PAYMENT PROCEDURES
01 30 00 11/20, CHG 2: 05/22 ADMINISTRATIVE REQUIREMENTS
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 33 29 02/21 SUSTAINABILITY REQUIREMENTS AND
REPORTING
01 35 13 11/20, CHG 1: 02/22 SPECIAL PROJECT PROCEDURES
01 35 26 11/20, CHG 3: 02/22 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 20 11/11, CHG 8: 02/21 QUALITY CONTROL
01 50 00 11/20, CHG 2: 08/22 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 08/22 TEMPORARY ENVIRONMENTAL CONTROLS
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS
01 78 23 08/15, CHG 2: 08/21 OPERATION AND MAINTENANCE DATA
01 78 24.00 20 02/15, CHG 3: 08/21 FACILITY ELECTRONIC OPERATION AND
MAINTENANCE SUPPORT INFORMATION (eOMSI)
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 41 00 08/22 DEMOLITION
02 82 00 11/18, CHG 1: 11/19 ASBESTOS REMEDIATION
02 83 00 11/18 LEAD REMEDIATION
DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON
07 92 00 08/16, CHG 3: 11/18 JOINT SEALANTS
DI VI SI ON 08 - OPENI NGS
08 81 00 05/19 GLAZING
DI VI SI ON 09 - FI NI SHES
09 24 23 08/17, CHG 2: 11/18 CEMENT STUCCO
09 26 00 08/16, CHG 1: 08/18 VENEER PLASTER
09 65 00 08/10, CHG 3: 08/18 RESILIENT FLOORING
09 72 00 08/17, CHG 1: 08/18 WALLCOVERINGS
09 90 00 02/21 PAINTS AND COATINGS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION 01 11 00
SUMMARY OF WORK
08/ 15, CHG 2: 08/ 21
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals Salvage Plan ; G
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
This is a Regional Indefinite Quantity Contract to provide interior and exterior painting, removal and installation of vinyl wallcoverings, sandblasting, waterblasting, lead base paint abatement, various types of maintenance repairs and preparations associated with painting and wallcovering. Other incidental type work associated with painting and wallcovering is included and may be ordered for industrial, commercial, and residential locations indicated within each task order. The Government contemplates one contract award with 6 administration offices resulting from this solicitation. The contract will be for all Federal Activities in the Hampton Roads Area. Each PWD Base location (6 total) will administer the work they order.
The bid schedule contains the Annual aggregate estimated total of quantities for the contract. The Contractor must furnish all labor, materials, equipment, tools, transportation, supervision, safety, surveys, scoping, layout work, engineering and management necessary to fulfill the requirements of this contract and each task order in a timely manner, with safety as a priority and quality work as the final product.
1.2.2 Location
Work may be ordered and administered by any of the six Bases listed below;
each Base has a Facilities Engineering Acquisition Division (FEAD) Director that will order and administer Task Orders and inspect the work within their areas. Each Base will process invoices for their orders.
Work may also be ordered electronically by authorized agents through e-mail.
a. Joint Expeditionary Base Little Creek-Fort Story (JEBLCFS), Norfolk, Virginia; Fort Barfoot, Blackstone, Virginia; Fort Walker, Virginia;
Surface Combat Systems Center, Wallops Island, Virginia; and satellite locations within a 50 mile radius of any of the above locations shall be considered part of the service area.
b. Naval Base Norfolk, Norfolk, Virginia; Chambers Field, Norfolk, Virginia; Craney Island, Chesapeake, Virginia; and satellite locations within a 50 mile radius of any of the above locations shall be
SECTION 01 11 00 Page 1 considered part of the service area.
c. Naval Air Station Oceana, Virginia Beach, Virginia; Fleet Training Center Dam Neck, Virginia Beach, Virginia; Fentress Airfield, Virginia Beach, Virginia; and satellite locations within a 50 mile radius of any of the above locations shall be considered part of the service area.
d. Norfolk Naval Shipyard, Portsmouth, Virginia; Portsmouth Naval Hospital, Portsmouth, Virginia; St. Juliens Creek, Portsmouth, Virginia; and satellite locations within a 50 mile radius of any of the above locations shall be considered part of the service area.
e. Naval Weapons Station Yorktown, Yorktown, Virginia; Cheatham Annex, Williamsburg, Virginia; and satellite locations within a 50 mile radius of any of the above locations shall be considered part of the service area.
f. Naval Support Activity Norfolk (NAVSUPPACT) Atlantic Fleet Compound, Norfolk, Virginia; Naval Security Activity Northwest, Chesapeake, Virginia; and satellite locations within a 50 mile radius of any of the above locations shall be considered part of the service area.
1.3 OCCUPANCY OF PREMISES
Building(s) will be occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location in the work area.
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.4 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.5 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
Government -furnished, if any, will be provided per Task Order.
Government-furnished materials and equipment for installation by the Contractor are pursuant to Contract Clause " FAR 52.245-1 , Government Property ." Contractor to provide any additional quantities that are required.
1.5.1 Delivery Schedule
Contractor must notify the Contracting Officer in writing at least 21 calendar days in advance of the date on which the materials and equipment
SECTION 01 11 00 Page 2 are required. Contractor must pick up materials and equipment no later than 30 calendar days after such date.
1.6 TASK ORDERS
A Task Order is a document (DD Form 1155) prepared by the Contracting Officer that is issued to the Contractor and unilaterally orders work to be performed. Task Orders will be issued as necessary and may be amended. The Contractor must be responsible for receiving, processing, and accomplishing work ordered on written Task Orders. Task Orders may be faxed or e-mailed to the contractor by the Contract Administrator of the issuing Base. During electronic outages or other special conditions, the contractor will be required to pick up Task Orders daily from the Contract Administrator of the issuing Base. Building locations of where to pick up task orders will be given to the contractor at the pre-construction meeting that will be held within 15 days after award of the contract.
1.6.1 Task Order Numbering System
Each Base will issue, administer, and approve payment for work that they order. Each Base will issue their work on a separate numbering system (e.g. Base 1 will issue work on Task Orders 100 through 999, Base 2 will issue work on Task Orders 1000 through 1999.) The numbering system that will be used for this contract will be established at the pre-construction meeting or by such other means as shall be determined by the Contracting Officer.
1.6.2 Pre-Priced Contract Line Items
The Government will use the prices awarded for contract line items in the base year and for each option year as they apply in the award, and only if the option is extended. The Government will order work for Task Orders by multiplying the unit of measurement for each line item times the contract price for that line item. Each line item used on a Task Order is totaled separately and then combined with other line items to establish an estimated cost for a Task Order. Final payment will be determined by calculating the total work measured in place times the unit price of each line item. The total of all line items completed per Task Order, measured in place, and accepted by the Government must be sent by the Contractor to the administrating office that issued the Task Order for payment.
All work must be measured in place (task completed).
1.7 STANDARDS OF MEASUREMENT
The following standards of measurement shall be used by the Government and must be used by the Contractor when estimating the amount of work for each task order issued for this contract. These standards are contained in the Painting Contractors Association (PDCA) estimating book "PDCA, Estimating Guide" Volume 2: Rates and Tables, Twenty-First Edition; Copyright 2003, General, "Standards of Measurement," from Section 4, page 11.t
a. Rule #1 No object is considered less than one linear foot long and shall be measured as one square foot per linear foot.
b. Rule #2 Pipes, rods, structural steel, lumber, and other items to be finished whose circumference or perimeter is less than one foot is measured as
SECTION 01 11 00 Page 3 one foot, otherwise the actual measurement is used.
c. Rule #3 Items having similar surfaces, finishes, application methods, and accessibility may be grouped together and an appropriate production rate may be applied to the entire group.
d. Rule #4 When items that do not have all grouping factors in common are adjacent, they should be listed separately on the quantity take-off and measured at no less than one square foot per linear foot.
e. Rule #5 When items having equivalent surface, finishes, application method, and accessibility change direction at sharp angles and continue for a significant distance in the new direction, then measurement of the object increases by the length of the new direction, but usually not less than 1/2 of a square foot per linear foot.
f. Rule #6 When measuring non-uniformly shaped and curved items, the added length of the surface due to its curvature, change of direction or nonuniformity must be measured.
g. Rule #7 Closely fabricated items, such as chain-link fence, open web joists and grating, should be measured as being solid. If both sides of a closely fabricated item are finished, double the surface area. When a closely fabricated item is attached to framework, measure the framework separately as described in Rule #2.
h. Rule #8 When a small opening interrupts a continuous surface, the opening is disregarded and considered part of the continuous surface. Any openings extending from floor to ceiling and exceeding five feet in width shall be deducted. All openings 100 square feet or larger are deducted.
i. Rule #9 Cabinets, tubs, showers, and other items that restrict movement or access shall not be deducted from the measurement of total surface area.
1.7.1 Surface Area Tables
The tables in Section 8 of the Painting and Decorating Contractors of America, estimating book "PDCSA Estimating Guide", Volume 2: Rates and Tables; Twenty-First Edition Copyright 2003, titled "Surface Area Tables" may also be used in estimating the square foot area to be painted. In all cases, when one or more of the tables are used to estimate the area of an item to be painted the tables letter (A, B, C,) and table name must be noted in the estimate so all parties will know which method of estimating is used. Table B "Common Estimating Multipliers" may also be used in estimating the square foot area to be painted. The use of the multipliers must be noted on the estimate and the basic measurement and the product of the multiplier must both be shown for clarity.
SECTION 01 11 00 Page 4
1.8 SYNOPSIS OF LINE ITEMS
NOTE: For all lines items, except line items specified for heights over 25 feet to 50 feet, must include everything required to complete the work up to a height of 25 feet above Ground Level, floor level, or other permanent solid surface from which personnel can safely work. This includes, but is not limited to, material, labor, supervision, field office overhead, transportation, tools, ladders, scaffolds, man lifts, and man lifts required to complete the assigned work. For all surfaces higher than 25 feet, the contractor is entitled to additional reasonable costs for scaffolding rental, man lift rental, crane rental, and the mobilization and demobilization of that equipment. That additional cost must be included in the cost of the line items that specify heights over 25 feet to 50 feet. If the height exceeds 50 feet or there is not a line item addressing heights over 25 feet to 50 feet, that additional cost must be handled through the use of the non-prepriced line items.
a. Removal and Reinstallation of Accessories:
X001AA. Remove and Reinstall Large Signs and Lights:
Includes Contractor removal, protection, and reinstallation of large signs and lights. Lost, damaged, or missing fasteners must be replaced by the Contractor. Large signs and lights are considered to be those that require two or more people to remove and reinstall. In most cases, ladders will be used. Removal and reinstallation of signs and lights over 25'-0" high will be worked in conjunction with the line item for non-prepriced work.
X001AB. Remove and Reinstall Gutters, Downspouts, and Hangers:
Includes Contractor removal, protection, and reinstallation of gutters, downspouts, and hangers. Lost or damaged components must be replaced by the Contractor. New caulking is included as part of this line item. In most cases, ladders will be used. Removal and reinstallation of gutters, downspouts, and hangers over 25'-0" high will be worked in conjunction with the line item for non-prepriced work.
X001AC. Remove and Reinstall Storm Windows (Frames and Panels):
Includes Contractor removal, protection, and reinstallation of clean and good condition frames and panels. Broken or lost components will be replaced by the Contractor. Panels must be clean when reinstalled. New caulking must be included as part of this line item.
X001AD. Removal and Replacement of Storm Windows (Panels Only):
Includes Contractor removal, protection, and reinstallation of panels and insulation. Broken or lost components must be replaced and installed by the Contractor. Panels must be clean when reinstalled.
New caulking is included as part of this line item.
X001AE. Removal and Replacement of Window Air Conditioners:
Includes Contractor removal, protection, and reinstallation of window air conditioners including extruding panels and insulation. Broken or lost components must be replaced and installed by the Contractor. New caulking is included as part of this line item. Air conditioner
SECTION 01 11 00 Page 5 removal is considered to be a line item that requires two people to remove and reinstall.
b. Removal and Disposal of Accessories:
X002AA. Removal and Disposal of Large Signs and Lights:
Includes Contractor removal and proper disposal of large signs and lights. Large signs and lights are considered those that require two or more people to remove and dispose. In most cases, ladders will be used. Disposal of debris must occur daily in accordance with the terms of the contract, off of Government property. Removal and disposal of signs and lights over 25'-0" high will be worked in conjunction with the line item for non-prepriced work.
X002AB. Removal and Disposal of Gutters, Downspouts, and Hangers:
Includes Contractor removal and disposal of gutters, downspouts, and hangers. Disposal of debris must occur daily in accordance with the terms of the contract, off of Government property. Removal and disposal of gutter, downspouts, and hanger over 25'-0" high will be worked in conjunction with the line item for equipment.
X002AC. Removal and Disposal of Vinyl Wall Covering:
Includes Contractor removal and disposal of vinyl wall covering without causing damage to the existing underlying/adjacent surfaces.
This includes removal of excessive, loose adhesive after paper has been removed. Disposal of debris must occur daily in accordance with the terms of the contract, off of Government property.
X002AD. Removal and Disposal of Wood or Vinyl Base:
Includes Contractor removal and disposal of wood or vinyl base up to six inches high. Disposal of debris must occur daily in accordance with the terms of the contract, off of Government property.
c. Total Lead Based Paint Abatement:
X003AA. Remove Lead Based Paint to Bare Surfaces (Interior):
Includes Contractor removal to bare surface of all lead based paint and requires placement in approved containers. The Contractor must furnish containers to be used and the Government must dispose of waste.
Lead based paint abatement/removal must be paid per square foot for normal flat surfaces. When surfaces are irregular in form (i.e.
specialty trims, corrugated surfaces, etc.) the price must be negotiated on the non-prepriced line item prior to work being performed.
X003AB. Remove Lead Based Paint to Bare Surfaces (Exterior):
Includes Contractor removal to bare surface or all lead based paint and placement in approved Contractor-furnished containers. The Government must dispose of waste.
Lead based paint abatement/removal must be paid per square foot for normal flat surfaces. When surfaces are irregular in form (i.e.
SECTION 01 11 00 Page 6 specialty trims, corrugated surfaces, etc.) the price must be negotiated on the non-preprice line item prior to work being performed.
d. Remove Loose/Scaling Lead Based Paint and Spot Prime:
X004AA. Remove Loose/Scaling Lead Based Paint (Interior):
The Contractor is responsible for lead based paint removal and placement of waste in approved containers. The Contractor must furnish containers to be used, and the Government shall dispose of waste. Contractor must remove and dispose of loose, scaling lead based paint using the same rules and regulations as X003AA. Removal must be down to where scaling particles do not come off when hand rubbing pressure is applied horizontally or vertically, and to where the new paint mil thickness encapsulates all surfaces evenly. Surfaces that have been tested and found to have lead content, but are in otherwise good condition, may be ordered to be painted over without any removal of lead upon approval by Contracting Officer.
Lead based paint abatement/removal must be paid per square foot for normal flat surfaces. When surfaces are irregular in form (i.e.
specialty trims, corrugated surfaces, etc.,) the price must be negotiated on the non-prepriced line item prior to work being performed.
X004AB. Remove Loose/Scaling Lead Based Paint (Exterior):
The Contractor is responsible for lead based paint removal and placing waste in approved containers. The Contractor must furnish containers to be used and the Government shall dispose of waste. Contractor must remove and place loose, scaling lead based paint using the same rules and regulations as X003AB. Removal must be down to where scaling particles do not come off when hand rubbing pressure is applied horizontally or vertically, and to where the new paint mill thickness encapsulates all surfaces evenly. Surfaces that have been tested and found to have lead content, but are in otherwise good condition, may be ordered to be painted over without any removal of lead upon approval by Contracting Officer.
Lead based paint abatement/removal must be paid per square foot for normal flat surfaces. When surfaces are irregular in form (i.e.
specialty trims, corrugated surfaces, etc.) the price must be negotiated on the non-prepriced line item prior to work being performed.
e. Replacement of Deteriorated Wood and Damaged Glass:
X005AA. Replacement of Existing Trim:
Contractor must remove existing trim lumber and replace with new.
Includes primer coat on all sides, fasteners, and caulking.
X005AB. Replacement of Existing Plywood:
Contractor must remove existing plywood and replace with new.
Includes primer coat on all sides, fasteners, and caulking.
X005AC. Remove and Replace Existing Sheet Glass:
SECTION 01 11 00 Page 7
Contractor must remove existing sheet glass and glazing and replace with new. Includes new sheet glass, glazing, pins/stars, cleaning of new sheet glass, and caulking, if applicable.
f. Blast Cleaning:
X006AA. Blast Clean - Near White:
Includes blast cleaning, protection, and cleanup performed by the Contractor. A near white blast cleaned surface finish is defined as one from which all oil, grease, oxides, paint, rust, or other foreign matter have been completely removed from the surface except for very light shadows, very light streaks, or light discoloration. Sample panel approval by Contracting Official is required; final surface condition of remaining work must be similar to approved sample panel.
X006AB: Blast Cleaning - Commercial:
Includes blast cleaning, protection, and cleanup performed by the Contractor. A commercial blast cleaned surface finish is defined as one from which all oil, grease, dirt, rust, scale, and foreign matter have been removed from the surface except for a shadow, streaks, or discolorations caused by rust stain, mill scale oxides or slight tight residues of paint or coatings that may remain; if the surface is pitted, slight residues of rust or paint may be found in the bottom of pits; at least two-thirds of each square inch of surface area must be free of all visible residues and the remainder must be limited to light discoloration, slight staining, or tight residue. Sample panel approval by Contracting Officer is required, and final surface condition of remaining work must be similar to approved sample panel.
X006AC. Blast Cleaning - Brush Off:
Includes blast cleaning, protection, and cleanup performed by the Contractor. Brush off blast cleaning is defined as one from which all oil, grease, dirt, rust, scale, loose rust, and loose paint or coatings are removed completely, but tight mill and tightly adhered rust, paint, and coatings are permitted to remain, provided that all mill scale and rust have been exposed to the abrasive blast pattern sufficiently to expose numerous flecks of the underlying metal fairly uniformly distributed over the entire surface. Sample panel approval by the Contracting Officer is required, and final surface condition of remaining work must be similar to approved sample panel.
X006AD through X006AF. Water Blasting of Various Surfaces:
Includes blast cleaning, protection, and cleanup performed by the Contractor. Water blasting must consist of washing surfaces to receive paint with a high pressure water spray to remove loose paint, dirt, and other foreign or deleterious materials. The working pressure must be a minimum 850 pounds per square inch at a nozzle with a minimum operating rate of 20 gallons per minute. Do not flood vents or damage windows and floors. If the pressure specified will cause damage to existing wood, prior to damaging, advise the Contracting Officer and obtain permission to vary the pressure. Direct the wash nozzle at the surface at an angle of approximately 75 degrees with the surface, and at a distance not greater than 5 feet in order to apply enough water pressure that is required to remove loose paint, dirt, chalking, and other foreign matter. Note: Prior to the initial
SECTION 01 11 00 Page 8 surface cleaning, Contractor must water blast a representative surface designated by the Contracting Officer. Sample panel approval by the Contracting Officer is required, and final surface condition of remaining work must be similar to approved sample panel.
g. Extraordinary Work / Surface Preparation:
X007AA. Putty and Glazing:
Includes cleaning surfaces, application of putty or glazing, and final cleaning of work area and surrounding surfaces by the Contractor.
X007AB. Sealant:
Includes cleaning surfaces, application of backup material and sealant, and final cleaning of work area and surrounding surfaces by the Contractor.
X007AC. Concrete Crack and Small Holes Repairs:
Includes removing loose concrete, cleaning surfaces, priming, and repairing cracks, and/or small holes to match adjacent surfaces by the Contractor.
X007AD. Concrete Hole and Depression Repair (Greater than 3"):
Includes removing loose concrete, cleaning surfaces, priming, and repairing holes and depressions to match adjacent surfaces by the Contractor.
X007AE. Stucco Repairs:
Includes removal of loose stucco, cleaning surfaces, priming, installation of compatible lath, and repairing stucco surfaces to match adjacent surfaces by the Contractor.
X007AF. Wallboard/Plaster Repairs (Cracks up to 1" wide):
Includes removal of loose gypsum/plaster, cleaning surfaces, priming, and repairing defective surfaces with compatible materials to match adjacent surfaces by the Contractor.
X007AG. Wallboard/Plaster Holes and Depressions Repair (Greater than 3" Dia.):
Includes removal of loose gypsum/plaster, cleaning surfaces, priming, and repairing defective surfaces with compatible materials to match adjacent surfaces by the Contractor
X007AH. Additional Surface Preparation:
Additional surface preparation is used when preparation exceeds the Contractor's responsibility of 25% of the total surface area. This line item is for additional preparation that may be required of the Contractor above 25% of the surface area being worked.
X007AJ. Skimming Voids:
Skimming voids includes cleaning, sanding, and priming of voids, if
SECTION 01 11 00 Page 9 applicable, to manufacturer's specifications; skimming (interior and exterior) of voids with approved materials by the Contractor.
h. Extraordinary Work / Surface Preparation in Conjunction with Vinyl Coated Wallcovering:
X008AA and X008AB. Crack and Hole Repairs (1/4" through 3")
Work on wallboard / plaster includes Contractor removal of loose gypsum / plaster, cleaning surfaces, priming, and repairing defective surfaces with compatible materials to match adjacent surfaces.
X008AC. Crack and Hole Repairs (Greater than 3"):
Work on wallboard / plaster includes Contractor removal of loose gypsum / plaster, cleaning surfaces, priming, and repairing defective surfaces with compatible materials to match adjacent surfaces.
X008AD. Skim Coating:
Skim coating includes cleaning surface, prime if required by manufacturer, and application(s) of skim coat (with approved materials) up to 1/2" to smooth out imperfections in wall or ceiling surfaces by the Contractor.
i. Painting - Exterior Surfaces:
NOTE: Painting and priming must be paid per square foot for normal flat surfaces. When surfaces are irregular in form (i.e. trims, corrugated surfaces, doors, windows, etc.,) the price must be negotiated on the non-preprice line item prior to work being performed.
X009AA. Painting of Exterior Wood / Plywood:
Painting of exterior wood / plywood includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
X009AB. Painting of Exterior Concrete Surfaces:
Painting of exterior concrete surfaces includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
X009AC. Painting of Exterior Asbestos Surfaces:
Painting of exterior asbestos surfaces includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
X009AD. Painting of Exterior Metal Surfaces:
Painting of exterior metal surfaces includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
SECTION 01 11 00 Page 10
X009AE. Painting of Exterior Metal Surfaces (Heights Over 25 Feet to 50 Feet):
Painting of exterior metal surfaces includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment over 25'-0" to 50'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
X009AF. Painting of Exterior Metal Surfaces (Corrugated Siding):
Painting of exterior metal surfaces (corrugated siding) includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
X009AG. Painting of Exterior Metal Surfaces (Corrugate Siding at Heights Over 25 Feet to 50 Feet):
Painting of exterior metal surfaces (corrugate siding) includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment over 25'-0" to 50'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
X009AH. Painting of Exterior Metal Roof Surfaces:
Painting of exterior metal roof surfaces includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
X009AJ. Painting of Exterior Concrete or Masonry Textured Surfaces:
Painting of exterior concrete or masonry textured surfaces includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
X009AK. Painting of Exterior Concrete or Masonry (Water Repellent Vapor Permeable):
Painting of exterior concrete or masonry with a water repellent vapor permeable coating includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas. The specified paint shall be highly vapor permeable; not subject to ultra violet deterioration;
mold, fungi, and algae resistant; and it shall not flake, peel, or crack.
X009AL. Priming of Exterior Surfaces:
Priming includes 100% wipe down of surfaces and is used to prime areas that exceed the Contractor's responsibility of 25% of the surface area to be painted. NOTE: Some repair line items include 100% prime and will not require the use of this line item.
SECTION 01 11 00 Page 11
X009AM. Painting of all Insulated Surfaces:
Painting of insulated surfaces includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
X009AN. Painting of Exterior Concrete or Masonry Textured Surfaces (Elastomeric Coating):
Painting of exterior concrete or masonry textured surfaces includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
X009AP. Painting of Irregular Surfaces (Corrugated Siding):
Painting of irregular surfaces includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
X009AQ. Painting of Irregular Surfaces (Corrugated Siding at Heights Over 25 Feet to 50 Feet):
Painting of irregular surfaces includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment over 25'-0" to 50'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
j. Painting - Interior Surfaces:
NOTE: Painting and priming must be paid per square foot for normal flat surfaces. When surfaces are irregular in form (i.e. trims, corrugated surfaces, doors, windows, etc.) the price must be negotiated on the non-preprice line item prior to work being performed.
X010AA. Painting of Interior Wood or Plywood:
Painting of interior wood or plywood includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25' height, signs, MSDS reports posted, barricades, and cleanup of the areas.
X010AB. Interior Natural Finish of Wood or Plywood:
Painting of interior wood or plywood with natural finish includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25' height, signs, MSDS reports posted, barricades, and cleanup of the areas.
X010AC. Painting Interior Metal Surfaces:
Painting of interior metal surfaces includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25' height, signs, MSDS reports posted, barricades, and cleanup of the areas.
SECTION 01 11 00 Page 12
X010AD. Painting of Interior Concrete or Masonry Surfaces:
Painting of interior concrete or masonry surfaces includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
X010AE. Painting of Interior Concrete or Masonry with Textured Surfaces:
Painting of interior concrete or masonry with textured surfaces includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
X010AF. Painting of Exterior Concrete or Masonry (Water Repellent Vapor Permeable):
Painting of interior concrete or masonry with a water repellent vapor-permeable coating includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas. The specified paint shall be highly vapor permeable; not subject to ultra violet deterioration; mold, fungi, and algae resistant; and it shall not flake, peel, or crack.
X010AG. Painting of Interior Plaster or Wallboard:
Painting of interior plaster or wallboard surfaces includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
X010AH. Painting of Open Truss or Bar Joist (Heights Over 25 Feet to 50 Feet):
Painting of open truss or bar joist includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment over 25'-0" to 50'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
X010AJ. Priming of Interior Surfaces:
Priming includes 100% wipe down of surfaces and is used to prime areas that exceed the Contractor's responsibility of 25% of the surface area to be painted. (NOTE: Some repair line items include 100% prime and will not require use of this line item.)
k. Interior Painting - Little or No Surface Preparation:
NOTE: Painting and priming must be paid per square foot for normal flat surfaces. When surfaces are irregular in form (i.e. trims, corrugated surfaces, doors, windows, etc.,) the price must be negotiated on the non-preprice line item prior to work being performed.
X011AA. Interior Painting with Little or No Surface Preparation (One Coat):
SECTION 01 11 00 Page 13
Apply one coat of specified paint, with 100% wipe down as the only preparation. Also includes property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
X011AB. Interior Painting with Little or No Surface Preparation (Two Coats):
Apply two coats of specified paint, with 100% wipe down as the only preparation. Also includes property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
l. Interior Painting -Restrooms:
NOTE: Painting and priming must be paid per square foot for normal flat surfaces. When surfaces are irregular in form (i.e. trims, corrugated surfaces, doors, windows, etc.) the price must be negotiated on the non-preprice line item prior to work being performed.
X012AA. Interior Painting of Wood in Restrooms:
Interior painting of wood in restrooms includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
X012AB. Interior Painting of Metal in Restrooms:
Interior painting of metal in restrooms includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
X012AC. Interior Painting of Concrete / Masonry in Restrooms:
Interior painting of concrete / masonry in restrooms includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
X012AD. Interior Painting of Plaster or Wallboard in Restrooms:
Interior painting of plaster or wallboard in restrooms includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
m. Interior Painting - Insulation:
X013AA. Painting of Cloth or Paper Covered Insulation:
Painting of cloth or paper covered insulation includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
n. Painting - Mechanical, Electrical, and Miscellaneous Metal Items:
SECTION 01 11 00 Page 14
X014AA. Painting of Mechanical or Electrical Metal Surfaces:
Painting of mechanical or electrical metal other than piping (not adjacent to painted surfaces) includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
X014AB through X014AD. Painting of Mechanical or Electrical Piping:
Painting of mechanical or electrical piping (all sizes) includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
X014AE. Painting of Mechanical and Electrical Piping Identification (Letters and Miscellaneous Markings):
Painting of mechanical or electrical piping identification (all sizes) includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
o. Painting - Hot Metal Surfaces:
NOTE: Painting and priming must be paid per square foot for normal flat surfaces. When surfaces are irregular in form, the price must be negotiated on the non-preprice line item prior to work being performed.
X015AA and X015AB. Painting of Hot Metal:
Painting of hot metal includes 100% wipe down, 25% surface preparation, 25% prime, two coats of specified paint, property and personnel protection, equipment to 25'-0" height, signs, MSDS reports posted, barricades, and cleanup of the areas.
p. Vinyl Coated Wallcoverings:
NOTE: Refer to Section 09 72 00 Wallcoverings for specifications.
X016AA and X016AB. Wall Covering (Types I or II):
Includes providing selected wallcovering, 100% wipe down, 25% scraping, and 25% skimming of surface area to remove raised surfaces and smooth out defects that may protrude through the new wallcovering. Also includes manufacturer's suggested adhesive, caulking, and cleanup of areas.
X016AC. Install Government Furnished Wallcovering:
Includes 100% wipe down, 25% scraping, and 25% skimming of surface area to remove raised surfaces and smooth out defects that may protrude through the new wallcovering. Also includes manufacturers suggested adhesive, caulking, and cleanup of areas.
q. Wall Base:
SECTION 01 11 00 Page 15
NOTE: Refer to Section 09 65 00 Resilient Flooring (Wall Base) for specifications.
X016AD. Cove Base Installation Up to Six Inches:
This line item must be a composite rate for 4" and 6" cove base in various colors and must include cove base, wall preparation, adhesives, installation, and cleanup.
r. Non-Prepriced Work:
X017AA through X017AC. Non-Prepriced Work:
This line item covers, but is not limited to, the cost for labor, materials, and various types of equipment required to provide repair work, modifications, or new work in conjunction with other work ordered under the bid schedule for Interior / Exterior Painting and Wallcovering. The Government must provide the Contractor with a scope of work requested to be performed. After review, the Contractor must submit to the Contracting Officer either a Type I or Type II proposal (in some cases both) within five working days of the date of receiving the scope of work. Under a Type I proposal, the Contractor must develop man-hours, material, equipment, overhead and profit costs for task requested from current issues of any of the R.S. Means Facilities Estimating Guides. Under a Type II proposal, if requested task is not found in the R. S. Means Facilities Guide, then the Contractor must submit a minimum of two (2) written quotes (for direct cost only) from subcontractors / suppliers, and a breakdown of Contractors overhead and profit. The Contractor must submit the following to the Contracting Officer who may, using discretion, initiate negotiations for time and cost:
1. Task description.
2. Direct labor hours from R.S. Means Estimating Guide per task, including all identifying Means numbers.
3. Davis-Bacon Wage Rate for trades performing tasks, including fringes.
4. Description of proposal materials, number of units and direct bare costs per R. S. Means Estimating Guide.
5. Description of proposed heavy equipment, rental rates per R.S.
Means for the estimated time the equipment will be utilized.
Material: All material required to complete the project must be at bare cost only. The only mark up allowed to be added to material is delivery or shipping costs required for the contractor to receive the material.
Labor: This Line Item must cover the total cost of labor per hour including (but not limited to): All overhead, contractor profit, supervision, and on the job material handling and ordering, preparation of cost estimate, job preparation, travel, pre-expended bin materials and supplies, and incidental tools, field and home office overhead, clerical support, inspection, fees, taxes, licenses, bonds, permits, insurance, and in-scope and emergency repairs not covered under the existing line items. For this line item (LABOR,)
SECTION 01 11 00 Page 16 the person performing the work will be a journeyman mechanic that has the same qualifications and expertise as the mechanic working normal line item tasks. In many cases it will most likely be the same person. A single inclusive hourly rate is to be entered by the bidder for the hourly bid rate and multiplied by the Government estimate for the number of labor hours. The number of hours ordered per task must be negotiated and must become the firm fixed price, unless the scope of work changes.
s. Command Interest Work:
In some cases of Command Interest where the request for work is of an urgent nature the contractor must be paid an additional one time cost to respond within 48 hours from receiving a written or verbal request for work. The Contractor must respond within 48 hours and must work diligently until all work is completed. The Contractor must be aware of the intent of this line item. Payment is based solely on the timeliness and the diligent progress of the Contractor's performance.
The Contractor must complete the project within the time negotiated or risk losing entire additional pay. When the delay is determined not to be caused by the contractor, the Government may consider payment.
Liquidated damages assessment starts the day after the required completion date. When the Command Interest Line Item is used, the startup time is up to 48 hours. Additional time that is given on other non-negotiated line items do not apply with Command Interest Work.
1.9 NAVY AND MARINE CORPS INTRANET( NMCI) COORDINATION REQUIREMENTS
1.9.1 NMCI Contractor Access
Allow the NMCI Contractor access to the facility towards the end of construction (finishes 90 percent complete, rough-in 100 percent complete, Inside Plant (ISP)/Outside Plant (OSP) infrastructure in place) to provide equipment in the telecommunications rooms and make final connections.
Coordinate efforts with the NMCI Contractor to facilitate joint use of building spaces during the final phases of construction. After the Contracting Officer has facilitated coordination meetings between the two contractors, within one week, incorporate the effort of additional coordination with the NMCI Contractor into the construction schedule to demonstrate a plan for maintaining the contract duration.
1.10 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area located within five miles of the construction site.
Provide a salvage plan , listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Provide a system for property control in the salvage plan. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.
SECTION 01 11 00 Page 17
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 18
SECTION 01 14 00
WORK RESTRICTIONS
11/22
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel
1.2 SPECIAL SCHEDULING REQUIREMENTS
a. All affected facilities will remain in operation during the entire construction period. The Contractor must conduct operations so as to cause the least possible interference with normal operations of the activity.
b. Permission to interrupt any Activity roads, railroads, or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
c. The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the construction schedule each factor which constitutes a potential interruption to operations.
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, include delivery vehicles, are clearly identified with their company name.
1.3.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.3.1.2 Additional Personnel Requirements
1.3.1.2.1 General Construction and Finish Work
General construction and finish work of the secure area or controlled area
SECTION 01 14 00 Page 1 must be performed by U.S. firms using U.S. citizens. General construction includes construction activities such as building sitework, utilities, foundations, structure, and enclosure or shell, including doors, windows and façade work. Finish Work includes construction activities such as insulation, floor, partition, and ceiling systems; cabinet work; conveyor systems; specialties; building furnishings, fixtures, and equipment; and mechanical and electrical services and equipment including those specialized for fire protection, security, communication, control, energy conservation, safety, comfort, convenience, and similar purposes.
1.3.1.2.2 General Construction
General construction of the secure area or controlled area must be performed by U.S. firms using U.S. citizens. General construction includes construction activities such as building sitework, utilities, foundations, structure, and enclosure or shell, including doors, windows and façade work.
This is the start of the file's text. The full file is on GovTribe.