SF30 Amend1 23F2548 5-24.pdf
PDF 232 KB Posted
- Attached to
- Bldg. 3870 Interior Renovations Federal contract opportunity
- Solicitation number
- N4008523R2548
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| ATTACHMENT I- ACKNOWLEDGE OF AMENDMENTS.pdf | ||
| ATTACHMENT C- WAGE DETERMINATION.pdf | ||
| ATTACHMENT F- PPI TEMPLATE.pdf | ||
| 23R2548 General Requirements.pdf | ||
| ATTACHMENT H-SOLICITATION PROVISIONS.pdf | ||
| ATTACHMENT G - Price Proposal Form.pdf | ||
| ATTACHMENT A- SPECIFICATIONS.pdf | ||
| ATTACHMENT B- DRAWINGS.pdf | ||
| ATTACHMENT D- SECNAV 5512.pdf | ||
| ATTACHMENT E- ONE DAY PASS FORM.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| ������������� | |
| � | ��������� |
| �� |
| ����� | ���������� |
| ���� | ������ |
| ����������� | � |
| ��� | ������ |
| ��� | �� | ��������� |
| �� |
������ ��!"#$%&'��!�(�%&�")*+�,$'-./'+0�0���'�
&')'#1'-�"0�02'�3$")'�-'4#.+"0'-�!�&�02'�&')'#30��!��!!'&4�3&#�&�0��02'�2�%&�"+-�-"0'�43')#!#'-�/"(�&'4%$0�#+�&'5')0#�+��!�(�%&��!!'& ��#��
���6�� ������ ����
�����6������
| ��� | �� | ��������� |
| �� |
����������6��������� �� ������
78��9:;<=>?@>A��)�
| � | ||
| � | ��� ���� | |
| � | ���� �����B������ | ����� |
| � | ���������� | |
| � |
| ���� | �� | |
| � �������� | �� | �������� |
?:7@C:7@>�<D�E<F9G9>?>9<@H:<C9D9G?>9<@�<D�G<@>=?G> � ��)�+0&")0�#-�)�-'
I ��"/'+-/'+0J/�-#!#)"0#�+�+%/�'& K ��'!!')0#1'�-"0' L ��&'M%#4#0#�+J3%&)2"4'�&'M%#4#0#�+�+%/�'& � ��3&�5')0�+%/�'&�NOP�QRRSTUQVSWX
Y ��"-/#+#40'&'-��(�NOP�Z[\W]�[\Q̂�O[W_�̀X )�-'
E>?@C?=C�D<=:�ab�c=7d8�eeHfbegh�
3�������������.4"�!"&��L��)!&���K ILK
!")#$#0(�)�-'
�i" ��"/'+-/'+0��!�4�$#)#0"0#�+�+%/�'& i� ��-"0'-�Njkk�Olkm�nnX
�o" ��/�-#!#)"0#�+��!�)�+0&")0J�&-'&�+%/�'&
�o� ��-"0'-�Njkk�Olkm�npX ee8��>q9E�9>7:�<@Fr�?;;F97E�><�?:7@C:7@>E�<D�E<F9G9>?>9<@E
���������0��� ��6��
| ���� | ���� | ��� |
| �# | ����L ��0�������� |
���������������������� ���������� ����s � � ��s �
�I ��"))�%+0#+.�"+-�"33&�3&#"0#�+�-"0"�NOP�]WtuT]WvX w�������� ����������� �������������� ��w ea8��>q9E�9>7:�?;;F97E�<@Fr�><�:<C9D9G?>9<@E�<D�G<@>=?G>EH<=C7=E8�
9>�:<C9D97E�>q7�G<@>=?G>H<=C7=�@x:y7=�?E�C7EG=9y7C�9@�9>7:�ez8
)2')*��+' " ��02#4�)2"+.'��&-'&�#4�#44%'-�3%&4%"+0�0����NjRWUTP{�Qu[\Z]T[{X�02'�)2"+.'4�4'0�!�&02�#+�#0'/��L�"&'�/"-'�#+�02'�)�+0&")0��&-'&���
������+%/�'&�#+�#0'/��o"
� ��02'�"��1'�+%/�'&'-�)�+0&")0J�&-'&�#4�/�-#!#'-�0��&'!$')0�02'�"-/#+#40&"0#1'�)2"+.'4�N|uU\�Q|�U\Q̂}W|�T̂�RQ{T̂}�ZPPTUW~�
������QRR]ZR]TQ[TẐ�vQ[Q~�W[U���4'0�!�&02�#+�#0'/��L��3%&4%"+0�0��02'�"%02��(��!�!"&�LK �oK���
) ��02#4�4%33$'/'+0"$�".&''/'+0�#4�'+0'&'-�#+0��3%&4%"+0�0��"%02��(��!�
- ���02'&�NjRWUTP{�[{RW�ZP�_ZvTPTUQ[TẐ�Q̂v�Qu[\Z]T[{X
's��� � �����6����������
| �� | �� |
| ����� | ��������� |
| ������� |
| �# | ���i"�����o"�� |
| ������ | �������� |
��) ��-"0'�4#.+'-
��" ��+"/'�"+-�0#0$'��!�4#.+'&�Nl{RW�Z]�R]T̂[X
��) ��-"0'�4#.+'-
��" ��+"/'�"+-�0#0$'��!�)�+0&")0#+.��!!#)'&�Nl{RW�Z]�R]T̂[X
�L ��-'4)#�+��!�"/'+-/'+0J/�-#!#)"0#�+���]}Q̂T�Wv�V{�����|WU[TẐ�\WQvT̂}|~�T̂USuvT̂}�|ZSTUT[Q[TẐ�UẐ[]QU[�|uV�WU[�_Q[[W]��\W]W�PWQ|TVSW�X
3".'�������!����3".'4
� ��#44%'-��( )�-'
� ��+"/'�"+-�"--&'44��!�)�+0&")0�&�N�u_VW]~�|[]WW[~�UZû[{~�j[Q[W�Q̂v��O���ZvWX ���
��� ��)�+0&")0�&J�!!'&�&
NjT}̂Q[u]W�ZP�RW]|Ẑ�Qu[\Z]T�Wv�[Z�|T}̂X
��� ��%+#0'-�40"0'4��!�"/'&#)"
NjT}̂Q[u]W�ZP��Ẑ[]QU[T̂}��PPTUW]X
�]W�TZu|�WvT[TẐ�ûu|QVSW
�����¦���¤�© ����ª��£����
BLDG. 3870, INTERIOR RENOVATIONS (LITTLE CREEK SITE), JOINT EXPEDITIONARY BASE LITTLE CREEK-FORT STORY
VIRGINIA BEACH, VIRGINIA
Proposal due date of Wednesday, 24 May 2023 at 1400 EST has been extended to 5 June 2023 at 1400 EST.
The purpose of this amendment is to as follows:
(1) Provide responses to PPIs (1-9)
1. PPI RESPONSES:
RFI
No.
Date Submitted
REFERENCE
QUESTION GOVERNMENT
RESPONSE Page Section Para.
1 2-May
There does not appear to be an overall New Work drawing, Can we use the Mechanical overall for measurements as long as they are both the same?
The documents consist of 5 architectural drawings, 3 mechanical drawings, and 4 electrical drawings. This complete package illustrates the complete scope of the project. Graphic scales are provided to assist the contractor in measuring the proposed work.
2 8-May
DRAWINGS SHOW
THIS WALL IN
MEN’S BATHROOM
AS A PARTITION
WALL. DOES IT
STAY OR GET
DEMO’D? (SEE
ATTACHED)
The partial CMU wall illustrated shall be demolished and replaced with a new toilet partition. The tile floor finish shall be continuous
3 8-May
THERE WAS
CONFUSION
BETWEEN
DESIGNER AND
CUSTOMER
WHETHER OR NOT
THESE DOORS
WERE TO STAY OR
BE REPLACED DUE
GLASS DOORS NOT
BEING ALLOWED
DUE TO SECURITY
REASONS (SEE
ATTACHED )
Replacement of the entry doors is not in the scope of work; as there are no specifications or accompanying design for this work, it cannot be competitively bid. Should the customer elect to add this work to the contract, it will need to be negotiated post award.
4 8-May
DRW
AD101-
Note 11
DRAWING AD101 –
NOTE 11 – PREPARE
EXISTING WALLS TO
RECEIVE NEW
CERAMIC TILE
FINISH. WALLS ARE
2 DIFERENT TYPES –
WILL THE CERAMIC
TILE BE ABLE TO
RECEIVE NEW TILE
OR WILL THE TILE
SIDE NEED TO BE
DEMO’D?
IF NOT DEMO’D
WHAT WILL NEED
TO BE DONE TO
THE WALL ONCE
THE FCU &
RELATED PIPING IS
Existing ceramic tile shall be removed and the substrate prepared to receive new ceramic tile as scheduled. FCU and associated piping scheduled to remain shall be temporarily removed, salvaged, and reinstalled on new tile wall finish. Patch and repair wall as required to receive new tile finish.
DEMO’D? (SEE
ATTACHED)
5 8-May
WILL CRANE
SIMULATOR BE
STAYING IN PLACE
WHILE NEW
CEILING TILE IS
BEING INSTALLED?
(SEE ATTACHED)
The large simulator will remain.
6 8-May
SAME CONFUSION
REGARDING THE
GLASS DOORS AND
WHETHER OR NOT
THEY WERE TO
STAY OR BE
REPLACED DUE
SECURITY
REASONS.(SEE
ATTACHED)
Replacement of the entry doors is not in the scope of work; as there are no specifications or accompanying design for this work, it cannot be competitively bid. Should the customer elect to add this work to the contract, it will need to be negotiated post award.
7 8-May
ROOM C15 –
OLD/NOT IN USE
UNIT TO STAY OR
BE DEMO’D? IF
DEMO’D – WALL
REPAIR WILL LIKELY
BE NEEDED BEHIND
THE UNIT.
Remove existing fan coil unit and patch wall as required.
Verify FCU is inoperable prior to removal.
8 8-May
ROOM C16 -
OLD/NOT IN USE
UNIT TO STAY OR
BE DEMO’D? IF
DEMO’D – WALL
REPAIR WILL LIKELY
BE NEEDED BEHIND
THE UNIT. (SEE
ATTACHED)
Remove existing fan coil unit and patch wall as required.
Verify FCU is inoperable prior to removal.
9 8-May Room C16
BOARDED UP
WINDOWS TO
REMAIN OR
OPENED BACK UP?
THEY WERE
BOARDED UP FOR
SIMULATOR DARK
ROOM BUT ROOM
WILL NO LONGER
BE USED AS FOR A
Remove wood window covering and paint window frames as required to match.
SIMULATOR. (SEE
ATTACHED)
| SF30 Amend1 23F2548 |
| 23F2548 Amend V1 |