Amendment 2.pdf
PDF 144 KB Posted
- Attached to
- IDIQ AE Multi-Discipline Design & Engineering Services (Large Projects) for Hampton Roads, AOR Federal contract opportunity
- Solicitation number
- N4008522R2616
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 3.pdf | ||
| Amendment 1.pdf | ||
| AE Multi-Disc LG Projects HR Synopsis FINAL.pdf | ||
| Attachment C- PIEE Vendor Access Instructions.pdf | ||
| Attachment A - Past Performance Questionnaire (PPQ).pdf | ||
| Attachment B - Small Business Subcontracting Plan.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N40085-22-R-2616 INDEFINITE DELIVERY/INDEFINITE QUANTITY CONTRACT FOR
MULTIDISCIPLINE ARCHITECT-ENGINEER (AE) SERVICES FOR LARGE PROJECTS IN THE
NAVFAC MID-ATLANTIC (MIDLANT) AREA OF RESPONSIBILITY (AOR), LOCATED
PRIMARILY IN HAMPTON ROADS AOR.
Amendment 2 – 16 February 2022
This Amendment hereby:
1. Revises Synopsis Section 5.0 Special Requirements; 5.1 System of Award Management (SAM) Database
2. Revises Synopsis Section 6.0 SF-330 SUBMISSION REQUIREMENTS:.
3. Revises Synopsis Section 7.1 Criterion 1-Specialized Experience (SF330, Part I, Section F), Submission Requirements
4. Revises Synopsis Section 7.2 Criterion 2- Professional Qualifications (SF330, Part I, Sections E & G):
5. Provides PPI responses
6. Provides a conformed synopsis document with revisions herein
5.1 System of Award Management (SAM) Database.
From:
All contractors are advised that registration in the System for Award Management (SAM) Database is required prior to submission of SF330 package. If the firm is operating as a Joint Venture Entity, the Joint Venture shall be registered in the System for Award Management (SAM) Database prior to submission of SF330 package. Failure to register in the SAM Database may render your firm ineligible for award. For more information, check the SAM Web site: https://www.sam.gov.
To:
All contractors are advised that registration in System for Award Management (SAM) Database be required prior to award of a contract. Failure to register in the SAM Database may render your firm ineligible for award. For more information, check the SAM Web site: https://www.sam.gov.
6.0 SF-330 SUBMISSION REQUIREMENTS:
From:
The SF 330 shall be typed, one sided, at least 11 point Times New Roman or larger. Part I shall not exceed 100 single-sided 8.5 by 11 inch pages (the page limit does not include ISRs, certificates, PPQs, Joint Venture Agreements, licenses, or the draft subcontracting plan, as required by the Small Business Subcontracting criterion, nor does the page limit include cover sheets or dividers, provided that these do not contain any substantive information submitted in response to the synopsis or intended to demonstrate the qualifications of the firm). ) showing the names and roles of all key personnel listed in Section E with the associated firm as listed in Section C, may be one page single sided 11 by 17 foldout, using 11 point font or larger (font limitations do not apply to graphics, captions or tables).
Introductions shall be included in Sections E and F. Please include your DUNS, CAGE, and TIN numbers in Block 30 of the SF 330.
The SF 330 shall be typed, one sided, at least 11 point Times New Roman or larger. Part I shall not exceed 150 single-sided 8.5 by 11 inch pages (the page limit does not include ISRs, certificates, PPQs, Joint Venture Agreements, licenses, or the draft subcontracting plan, as required by the Small Business Subcontracting criterion, nor does the page limit include cover sheets or dividers, provided that these do not contain any substantive information submitted in response to the synopsis or intended to demonstrate the qualifications of the firm). The organizational chart of the proposed team (Section D of the SF-330) showing the names and roles of all key personnel listed in Section E with the associated firm as listed in Section C, may be one page single sided 11 by 17 foldout, using 11 point font or larger (font limitations do not apply to graphics, captions or tables). Introductions shall be included in Sections E and F. Please include your DUNS, CAGE, and TIN numbers in Block 30 of the SF 330. If submitting as a Joint Venture, and you do not yet have DUNS, CAGE, and TIN for the Joint Venture, then DUNS, CAGE and TIN should be submitted for each firm. DUNS, CAGE and TIN for the Joint Venture, if selected, would be required prior to the award of any contract.
The Government point of contact is Amanda Bricker, Contract Specialist, amanda.l.bricker.civ@navy.us.mil amanda.l.bricker.civ@us.navy.mil
Inquiries concerning this procurement should include solicitation number and title and be forwarded via email to the point of contact.
To:
Inquiries concerning this procurement should include solicitation number and title and be forwarded via email to the point of contact. Inquiries concerning the Synopsis shall be received no later than 14 calendar days prior to the SF-330 due date. Late submissions may not be answered.
7.1 Criterion 1-Specialized Experience (SF330, Part I, Section F), Submission Requirements
From
Submission requirements: Provide five (5) projects completed within the past seven (7) years immediately preceding the date of issuance of this notice that best demonstrate specialized experience of the proposed team in the areas outlined above. Sufficient information to determine the date of completion the project must be included in the project description or the project will not be considered. Provide at least one example project demonstrating experience with a final construction cost $30M or more. If more than the maximum number of projects are submitted, the Government will only evaluate the first five (5) projects in the order submitted. Offerors must clearly define the professional service role performed by offeror in relationship to the project owner. For Design-Build projects, state whether offeror performed as sub-contractor for Prime construction contractor in role of Designer of Record (DOR) or if not, the specific role. Only experience where firms prepare the design-build RFP package will be considered services similar to those anticipated under this contract.
NOTE 1: If the firm is a joint venture, projects performed by both members of the joint venture should be submitted; however, if there are no projects performed by the joint venture, projects may be submitted for either member of the joint venture, not to exceed a total of five (5) projects, but greater consideration may be given where projects are demonstrated for the joint venture and/or both members of the joint venture.
To
Submission requirements: Provide seven (7) projects completed within the past seven (7) years immediately preceding the date of issuance of this notice that best demonstrate specialized experience of the proposed team in the areas outlined above. Sufficient information to determine the date of completion the project must be included in the project description or the project will not be considered. Provide at least one example project demonstrating experience with a final construction cost $30M or more. If more than the maximum number of projects are submitted, the Government will only evaluate the first seven (7) projects in the order submitted. Offerors must clearly define the professional service role performed by offeror in relationship to the project owner. For Design-Build projects, where the firm’s role is Designer of Record and firm performed professional services of full design plans and specifications for Prime Contractor will be evaluated as design-bid-build experience. For item b) only experience where firms prepared the design-build RFP package will be considered services similar to those anticipated under this contract.
NOTE 1: If the firm is a joint venture, projects performed by both members of the joint venture should be submitted; however, if there are no projects performed by the joint venture, projects may be submitted for either member of the joint venture, not to exceed a total of seven (7) projects, but greater consideration may be given where projects are demonstrated for the joint venture and/or both members of the joint venture.
7.2 Criterion 2- Professional Qualifications (SF330, Part I, Sections E & G):
Firms will be evaluated on professional qualifications, competence, and experience of the proposed key personnel in providing services to accomplish the tasks required under this contract, including participation in example projects as outlined in the SF330, Part 1, Section G. Key personnel are individuals who will have major contract or project management responsibilities and/or will provide unusual or unique expertise. Specific disciplines that must be included in key personnel are Project Managers, Quality Control Manager, Architects, Landscape Architects, Civil Engineers, Structural Engineers, Mechanical Engineers, Electrical Engineers, Geotechnical Engineers, Cost Engineers, Certified Interior Designers and licensed Fire Protection Engineers.
Firms will be evaluated on professional qualifications, competence, and experience of the proposed key personnel in providing services to accomplish the tasks required under this contract, including participation in example projects as outlined in the SF330, Part 1, Section G. Key personnel are individuals who will have major contract or project management responsibilities and/or will provide unusual or unique expertise. Specific disciplines that must be included in key personnel are Project Managers, Quality Control Manager, Architects, Landscape Architects, Civil Engineers, Structural Engineers, Mechanical Engineers, Electrical Engineers, Geotechnical Engineers, Cost Engineers, Certified Interior Designers and licensed Fire Protection Engineers. Registered Communication Distribution Designer (RCDD), Certified Technology Specialist-Designer (CTS-D), and Certified Value Specialist (CVS).
RFI
Page Section Para. Question Response
3 Amendment 1, issued on February 2,2022, specific to 5.1 System of Award Management (SAM) Database:
Stated, “All contractors are advised that registration in the System for Award Management (SAM) Database is required prior to submission of SF330 package. If the firm is operating as a Joint Venture Entity, the Joint Venture shall be registered in the System for Award Management (SAM) Database prior to submission of SF330 package. Failure to register in the SAM Database may render your firm ineligible for award.”
Prior to the Original Published Date: Jan 28, 2022, we began creating a Joint Venture, specific to this NAVFAC requirement, with the assumption ”All contractors are advised that registration in System for Award Management (SAM) Database be required prior to award of a contract.” This process, submitting and receiving approval from State and Federal Agencies, for TIN, DUNS, CAGE, and SAM are nonconcurrent and normally take 45 calendar days. Time between amendment and Offer Date is 33 Calendar Days. This places a disadvantage for you to receive a competitive unrestricted proposal.
Question: Given the fact the normal process to obtain a SAM registration is 45 days, compounded with known government delays due to COVID, would you extend the Offer Due Date 60 days from February 02, 2022 to allow sufficient time for teams to obtain SAM registration in order to foster greater competition and
See Amendment 2.
options for the Government to choose?
4 5 of
6.0 SF-330
SUBMISSION
REQUIREMENTS
Top of page 5 States: “… substantive information submitted in response to the synopsis or intended to demonstrate the qualifications of the firm). ) showing the names and roles of all key personnel listed in Section E with the associated firm as …” Question: Are there some words missing on line 6?
See Amendment 2.
5 7 of
7.1 Criterion 1-
Specialized Experience
Lines 5 and 6 States: Designing and providing full construction drawings and specifications for various facility projects; including applying sustainability concepts through an integrated, cost effective design approach; Question:
Please clarify if “full design” experience where the firm was the Designer of Record as a sub-contractor for Prime Construction Contractor for a Design/Build project will be considered as equivalent to where the firm was the Designer of Record for a Design/Bid/Build project.
Bid per Synopsis.
6 7 of
7.1 Criterion 1-
Specialized Experience
a) States: Prepare Design-Build RFP packages; including environmental surveys, geotechnical reports and schematic design concepts;
And Provide five (5) projects completed within the past seven
(7) years … Question: Does a prepared Design-Build RFP package qualify as one of the “Provide five (5) projects completed within the past seven
(7) years …”?
Yes.
7 7 of
7.1 Criterion 1-
Specialized Experience
b) States: Provide five (5) projects completed within the past seven
(7) years … Question: Will you allow submission of up to 10 projects completed within the past 7-years while still maintaining overall 100-page limit for Part I?
See amendment 2.
8 7 of
7.1 Criterion 1-
Specialized Experience
Firms may be considered more favorably by demonstrating the following:
It is common for larger MILCON projects to be executed in phases under separate task orders. (ex:
T.O.#1- Planning/Programming/DD1391;
T.O.#2-Detailed Design; T.O.#3- Construction Phase Services).
Question: Can projects that were performed under multiple separate task orders be combined into a single project write-up?
No. Bid per Synopsis, "For submittal purposes, a task order on an IDIQ contract is considered a project, as is a stand-alone contract award"
9 8 of
7.1 Criterion 1-
Specialized Experience
NOTE 2: States:
Date of project completion is defined as date of final design acceptance by client. For full design projects, date of project completion is the date of final signed sealed plans & specifications delivered to client.
For DB RFP preparation, date of project completion is the date of final RFP document submission to client.
For DB RFP representing Contractor as Designer-of- Record (DOR), date of project completion is the date of final design acceptance by client.
final design acceptance by client.
Question: Is the intent to say DB Full Design [by AE#2]? Please clarify and confirm that the phase “For DB RFP representing the Contractor as Designer of Record” refers to completion of the “full design” drawings and specifications.
Bid per Synopsis.
10 8 of
7.2 Criterion 2-
Professional Qualifications
1st paragraph Does not list Food Service Consultant, Elevator Consultant, Roofing Consultant, or Forensic Consultant. Question: Do we need to provide any of the above as Key Personnel?
Bid per Synopsis.
11 Are there page limitations in regards to the introductions required for SF330 Section E and Section F?
No, but in accordance with changes issued in Amendment 2, Part I shall not exceed 150 single-sided 8.5 by 11 inch pages (the page limit does not include ISRs, certificates, PPQs, Joint Venture Agreements, licenses, or the draft subcontracting plan, as required by the Small Business Subcontracting criterion, nor does the page limit include cover sheets or dividers, provided that these do not contain any substantive information submitted in response to the synopsis or intended to demonstrate the qualifications of the firm)
12 Will the introduction to Section F be taken into consideration as part of the grading for Criterion 1- Specialized Experience, or is it solely based on the Section F projects?
Bid per Synopsis.
"All information for Criterion 1 should be submitted in the SF330, Part I, Section F of the SF330. The Government WILL NOT consider information submitted in addition to Part 1, Section F in evaluation of Criterion 1."
13 Will the introduction to Section E be taken into consideration as part of the grading for Criterion 2 – Professional Qualifications, or is it based only on Section E resumes and Section G?
Bid per Synopsis.
14 Criterion 2 - Professional Qualifications (SF330, Part I, Sections E & G): The SF330 instruction for BLK 19 states, “Provide information on up to five projects in which the person had a significant role that demonstrates the person's capability relevant to her/his proposed role in this contract.” Please confirm the number of projects allowed in BLK 19 of the two page resumes required in the synopsis (N40085-22-R-2616).
There is no limit to the number of projects. Bid per Synopsis of Resumes are limited to two (2) pages
15 Does a cover letter count towards the page limit (currently 100 pages)?
Bid per Synopsis, "the page limit does not include ISRs, certificates, PPQs, Joint Venture Agreements, licenses, or the draft subcontracting plan, as required by the Small Business Subcontracting criterion, nor does the page limit include cover sheets or dividers"
16 SF330 Submission requirements states that, “font limitations do not apply to graphics, captions or tables.” Please confirm this statement applies to the entire SF-330 submission and not just the Organizational Chart.
Confirmed.
17 SF330 Submission Requirements states “In accordance with the FAR 36.601-4(b) the AE firm must be a registered/licensed Architectural and/or Engineering firm to be eligible for award.
Provide proof that the firm is permitted by law to practice the professions of Architecture or Engineering, (e.g., state registration number, or a brief explanation of the firm’s licensing in jurisdictions that do not register firms, etc.).” FAR 36.601-4(b) states “Contracting officers may award contracts for architect-engineer services to any firm permitted by law to practice the professions of architecture or engineering.”
Please confirm that a list of state registration numbers for each participating AE firm's office/branch location (Part II) demonstrating their licensure to perform Architectural and/or Engineering Services is sufficient proof and that this information may be provided in tabular format as an appendix and not counted among the 100 page limit of Part I. Additionally, please confirm that only AE firms submitting as prime consultants must demonstrate this proof.
A list of state registration numbers for each participating AE firm's office/branch location demonstrating their licensure to perform Architectural and/or Engineering Services is sufficient proof and this information may be provided in tabular format as an appendix and not counted among the 150 page limit of Part I.
18 Criterion 1- Please provide clarification of the following statement, “Only experience where firms prepare the design-build RFP package will be considered services similar to those anticipated under this contract.” This could be interpreted as the only kind of specialized experience valid for this contract. We do not believe that is the intent of the statement.
Statement “Only experience where firms prepare the design-build RFP package will be considered service similar to those anticipated under this contract” applies to Criterion 7.1, item b). For design-build projects where the firm’s role is Designer of Record and the firm performed professional services of full design plans and specification will be evaluated as Design-Bid-Build experience.
19 - Criterion 1-Specialized Experience (SF330, Part I, Section F): We recommend with the extended period of relevant project completion (7 years rather than 5) that NAVFAC considers Navy projects with FC 300-09N experience more favorably than other DoD agency projects. Consider adding a “may be considered more favorably” feature to Criterion 1 such as: “Demonstrated experience on Navy installations within the primary geographic area of this contract.” This feature has been included in many other recent Midlant AE IDIQ multi-discipline procurements.
See Amendment 2, 20 Criterion 2 — Professional Qualifications (SF330, Part I, Sections E & G): Is there a minimum number of resumes required for each Key Personnel?
Bid per Synopsis, "Provide resumes for all proposed key personnel that illustrate experience in the work proposed under this contract. Resumes are limited to two
(2) pages"
21 Criterion 2 — Professional Qualifications (SF330, Part I, Sections E & G): Would the addition of resumed Disciplines or Specialties over and above those considered Key Personnel per the synopsis have the potential to favorably impact the evaluation of Section E?
No, Bid per Synopsis.
22 Criterion 2 — Professional Qualifications (SF330, Part I, Sections E & G): Cost Engineer is identified as Key Personnel.
Do you require a registered professional engineer or is a certification such as the Nationwide Certified Cost Professional (CCP) meet the requirements? Industry standard does not require cost estimators to be registered professional engineers.
Professional registration is not require for the Cost Engineer, but certification such as Nationwide Certified Cost Profession (CCP) is required.
23 What is the cutoff date and time to submit questions?
See Amendment 2.
24 Within Criterion 2, Professional Qualifications, please clarify the maximum number of individual resumes that will be evaluated for each key personnel role.
Bid per Synopsis.
There is no maximum number of key personnel for Criterion 2.
25 Within Criterion 2, Professional Qualifications, please clarify if the resumes are limited to two pages per person resumed or two pages total if multiple personnel are resumed for the same position.
Resumes are limited to 2 pages per person.
26 The RFP references the need for a Registered Communication Distribution Designer (RCDD) within paragraph B.4 of Appendix “B”. Because of the specialized nature of this role, should this be considered a key personnel role within Criterion 2, Professional Qualifications?
Registered Communication Distribution Designer (RCDD) is required per FC 1- 300-09N
27 In view of most personnel teleworking during COVID, will you consider removing the mailed/hardcopy proposal requirement?
Bid per Synopsis.
28 May we use subconsultant projects in Section F or do all five need to come from the Prime?
No, Bid per Synopsis
29 The current and previous contracts for the NAVFAC MidLant Hampton Roads Large Projects IDIQ have been held by the same firm since 2015. By requiring Specialized Experience projects be completed within the last 7 years, this limits the ability of other teams to show relevant project experience for NAVFAC MidLant within the Hampton Roads AOR. We request the project completion date be extended to 10 years. If changed, the project completion dates would mirror the current time requirements listed for key personnel resume project experience resulting in a more comprehensive offering to the Government.
CONFORMED SYNOPSIS -SEE ALL CHANGES IN RED
N40085-22-R-2616 INDEFINITE DELIVERY/INDEFINITE QUANTITY CONTRACT FOR MULTI-
DISCIPLINE ARCHITECT-ENGINEER (AE) SERVICES FOR LARGE PROJECTS IN THE
NAVFAC MID-ATLANTIC (MIDLANT) AREA OF RESPONSIBILITY (AOR), LOCATED
PRIMARILY IN HAMPTON ROADS AOR.
ALL INFORMATION NEEDED FOR INTERESTED PARTIES TO SUBMIT A STANDARD FORM
(SF) 330, ARCHITECT ENGINEER QUALIFICATIONS IS CONTAINED HEREIN. THERE IS NO
SEPARATE REQUEST FOR PROPOSALS (RFP) PACKAGE TO DOWNLOAD.
1.0 DESCRIPTION:
This procurement will result in one Indefinite Delivery/Indefinite Quantity (IDIQ) contract for multi-discipline Architect-Engineer (AE) Services support. Engineering and Design Services as required for construction, repair, replacement, demolition, alteration, and improvements for Special Projects and Military Construction (MILCON) facilities, also including base utility systems. These services will be procured in accordance with 40 United States Code (USC) Chapter 11, Selection of Architects, and Engineers, as implemented by Federal Acquisition Regulation (FAR) Subpart 36.6. Work under the contract is anticipated to occur primarily in the Hampton Roads area of Virginia for NAVFAC MID- ATLANTIC, but may be ordered throughout the NAVFAC MIDLANT AOR.
2.0 CONTRACT INFORMATION
The IDIQ contract shall be for a five-year ordering period, not to exceed 60 months. The total fee for the contract term shall not exceed $95,000,000. The guaranteed minimum for the contract term is $5,000 and will be satisfied by simultaneous award of the initial task order with the basic contract.
Firm-fixed price task orders will be negotiated for this contract. Contract capacity shall be limited to $95,000,000. Otherwise, there is no dollar limit per task order or per year. The estimated start date is September 2022.
This proposed contract is being solicited on an UNRESTRICTED basis. The Small Business size standard classification is North American Industry Classification System (NAICS) Code 541330, Engineering Services, and the Small Business size standard is $16,500,000. Most task orders issued for this contract are for military construction or major maintenance projects with construction costs ranging from $10M to $100M, some projects maybe larger or smaller than this range. Facility types may include, but are not limited to, personnel housing facilities (Bachelor Enlisted Quarters (BEQ) and Bachelor Officers Quarters (BOQ)); office facilities; training facilities (operational, maintenance and classroom); and industrial maintenance facilities (Vehicle Maintenance Shops. Shore Intermediate Maintenance Activities, Aircraft Maintenance Hangars, Public Works Shops, Warehouses). The Government seeks the most highly qualified firm to perform the required services, based on the demonstrated competence and qualifications, in accordance with the selection criteria.
3.0 PROJECT INFORMATION
The general type of services expected include, but not limited to; developing Design-Bid-Build packages, developing Design-Build Request for Proposal (RFP) packages, conducting Life Safety Code Studies, Interior space planning/design studies, Engineering site investigations, Preliminary Design, Facility planning including preparing Form DD1391 in Navy’s Electronic Procurement Generator (EPG), development of requirements and project scope, preparation of engineering evaluations, preparation of unit guidance costs or parametric cost estimating, development of alternatives and economic analysis, analysis of proposed sites for foundations, utilities, access, constraints and identification of environmental, sustainable design and anti-terrorism/force protection issues, government collateral equipment lists, Sustainable Checklists, develop commissioning requirements, project preliminary hazard analysis, obtaining permits and regulatory approvals, reviewing contractor submittals, field consultation and inspection during construction, Title II Inspections, Electronic Operation and Maintenance Support Information (eOMSI), and Record document preparation.
While Design-Bid-Build methodologies (with the preparation of 100% Plans and Specifications) will continue to be utilized, a significant number will likely require preparation of Requests for Proposal packages for Design-Build solicitations using abbreviated (0% - 35%) design documentation. Packages would include elements of site/engineering investigation, architectural programming, and functional/ performance specifications. Phases and/or pre-priced contract options may be included and will be exercised at the discretion of government for 0% to 35% design, 35% to 100% design, and post construction contract award services. Options are normally exercised within several months of completing prior work; however, delays of up to one year are possible (ie. Solicitation/procurement source selection construction contract period prior to exercising AE post award construction services).
Comprehensive AE services are required for planning, design, and construction services in support of new construction, renovations, repairs, replacements, demolition, alteration, and/or improvement of military and other governmental facilities to include base utility systems. AE services may include multiple disciplines or single disciplines, including but not limited to project manager, architectural, landscape architecture, structural, mechanical, electrical, civil, geotechnical, fire protection, cost engineering and interior designer. Specialized services for telecommunications, physical security, audio-visual and collateral equipment may be required.
Most projects will be new, repair, replacement, upgrade, maintenance, energy savings, and sustainability projects covering the full range of the field of engineering for a wide variety of new and existing facilities and systems, utilities and infrastructure. Projects may include multiple disciplines or single disciplines, including general building renovation work; development of Design-Bid-Build (DBB) packages;
development of Design-Build (DB) request for proposal packages; conducting Life Safety Code Studies;
interior space planning/design studies; engineering and design of site work; paving; landscaping;
communications; fire protection; energy conservation systems; utilities; and faculty planning.
Architect-Engineering and Engineering Services that may be required under this contract include facility and/or infrastructure field surveys and investigations resulting in the development of engineering analyses, studies, cost estimates, plans, specifications, Requests for proposal (RFPs) for design/build projects and Post-Construction Award design completion, shop drawing review, and other associated engineering services.
Projects shall include, but not limited to the following:
1) Fire protection water supply and distribution systems
2) Base-wide fire-reporting systems
3) Administrative facilities
4) Personnel support facilities – (lodging, berthing, recreational)
5) Child development centers
6) Medical facilities – (hospitals, medical/dental clinics)
7) Training facilities
8) Simulators
9) Industrial facilities
10) Maintenance facilities
11) Operational facilities
12) Warehouse facilities
13) Aircraft hangars
14) Bulk fuel facilities
15) Utility Systems – including steam; low pressure compressed air; fresh water; salt water;
sanitary sewer; oily waste water collection
16) Electrical Systems – including high voltage to low voltage electrical
17) Control systems
18) Ordnance storage and handling facilities including electrical hazard classifications required to be designed to Naval Sea Systems Command Ordnance Pamphlet 5 (NAVSEA OP 5) Explosives Safety Management Policy requirements
19) Waterfront facilities and infrastructure – (piers; wharves; quay (key) walls; dry docks, bulkheads, coastal and shoreline protection, fender systems; berthing and mooring;
dredging; coastal and shoreline protection; and waterfront related utilities)
20) Communications facilities – (telephone, television, fiber optics, cyber security, Supervisory Control and Data Acquisition (SCADA) control system, and Local Area Network (LAN))
21) Laboratory spaces and facilities and Research, Development, Test, and Evaluation (RDT&E) spaces and facilities
22) Ranges
23) Roads and Pavements and associated infrastructure including parking areas
24) Railroads
25) Landscaping
26) Storm Water Systems
4.0 ENGINEERING, DESIGN & CONSTRUCTION SERVICES
See Appendix A for Specific Types of AE Services
The selected firm will provide a full range of services for engineering, design and construction phases of anticipated projects, which may include, but are not limited to any or all of the following:
1. Project management
2. Data management
3. Project programming and master planning
4. Feasibility and concept studies
5. Space utilization
6. Design concepts/standards
7. Research
8. Analysis
9. Engineering
10. Design
11. Design/build request for proposal preparation
12. Engineering During Construction (EDC)
13. Construction phase support for Facility Repair projects involving historic facilities or facilities located in a Historic Districts, including repair, replacement, demolition, and new construction
5.0 SPECIAL REQUIREMENTS
See Appendix B for Additional Types of Special Requirements
5.1 → System for Award Management (SAM) Database
All contractors are advised that registration in System for Award Management (SAM) Database be required prior to award of a contract. Failure to register in the SAM Database may render your firm ineligible for award. For more information, check the SAM Web site: https://www.sam.gov.
5.2 → Conflicts of Interest
The awarded contract will be subject to specific provisions addressing the avoidance of organizational conflicts of interest such as those described below. The offeror will be required to perform throughout the contract term. The offeror will be required to self-perform material portions of the work on all awarded task orders. Subcontracting an entire design effort on any given task order will be prohibited
A-E firms are advised that the selected firm, its subsidiaries or affiliates, and its sub-consultants that design, prepare, or provide engineering services in support of construction contract documents cannot provide, or be part of a team providing, construction services for the contract resulting from the design effort. Services that will create such a conflict of interest may include, but are not limited to, efforts such as concept design, preparation of project programming documents (DD Form 1391), facility siting studies, environmental assessments, geotechnical services, engineering studies and services, design-build Request for proposal (RFPs), or other activities that result in identification of project scope and cost.
The Contractor shall not incorporate its products or services in such statement of work or specifications unless so directed in writing by the Contracting Officer, in which case the restrictions shall not apply. This contractor will be required to include Organizational Conflict of Interest restrictions in its subcontractor’s or consultants’ agreements concerning the performance of this contract.
5.3 → Registered/Licensed Firm
In accordance with the FAR 36.601-4(b) the AE firm must be a registered/licensed architectural and/or engineering firm to be eligible for award. Provide proof that firm is permitted by law to practice the professions of architecture or engineering, (e.g.., state registration number, or a brief explanation of the firm’s licensing in jurisdictions that do not register firms, etc.). Failure to submit the required proof could result in a firm’s elimination from consideration.
FIRMS WHO ARE OFFERING AS A JOINT VENTURE SHOULD INCLUDE WITH THEIR
SUBMISSION A COPY OF THE JOINT VENTURE AGREEMENT. FAILURE TO INCLUDE THE
JOINT VENTURE AGREEMENT WILL RESULT IN THE FIRM’S ELIMINATION FROM
FURTHER EVALUATION
6.0 SF-330 SUBMISSION REQUIREMENTS:
Architect-engineer firms that meet the requirements described in this announcement are invited to submit:
1. One electronic SF330 package (.pdf format) marked “Original” via PIEE. Please see below and
Attachment C – PIEE Vendor Access Instructions.
2. One hard copy marked “copy” including one (1) CD with all documents as Portable Document
Format (PDF)’s and properly bookmarked with searchable bookmarks for ease in navigation.
See below for mailing instructions
The SF 330 shall be typed, one sided, at least 11 point Times New Roman or larger. Part I shall not exceed 150 single-sided 8.5 by 11 inch pages (the page limit does not include ISRs, certificates, PPQs, Joint Venture Agreements, licenses, or the draft subcontracting plan, as required by the Small Business Subcontracting criterion, nor does the page limit include cover sheets or dividers, provided that these do not contain any substantive information submitted in response to the synopsis or intended to demonstrate the qualifications of the firm). The organizational chart of the proposed team (Section D of the SF-330) showing the names and roles of all key personnel listed in Section E with the associated firm as listed in Section C, may be one page single sided 11 by 17 foldout, using 11 point font or larger (font limitations do not apply to graphics, captions or tables). Introductions shall be included in Sections E and F. Please include your DUNS, CAGE, and TIN numbers in Block 30 of the SF 330. If submitting as a Joint Venture, and you do not yet have DUNS, CAGE, and TIN for the Joint Venture, then DUNS, CAGE and TIN should be submitted for each firm. DUNS, CAGE and TIN for the Joint Venture, if selected, would be required prior to the award of any contract.
**The Government will not consider information submitted beyond the page limits set forth below.**
Electronic and Hard Copy submission of proposals will be required.
Electronic submission of proposals will be required in accordance with the following:
Offerors shall submit electronic proposals (.pdf format) in response to this solicitation. Only the PIEE Solicitation Module is authorized for the submission of electronic proposals in response to this solicitation. Electronic proposal submissions should be no larger than 1.9 GB per file. Electronic proposals shall match the hard copy version of the proposal. In the event of a discrepancy, the electronic will govern. Offerors shall ensure that the Government has received the electronic proposal prior to the date and time specified. PIEE Solicitation Vendor Access Instructions are provided via Attachment-C.
Emailed submissions will not be accepted.
Offerors shall allow adequate time to upload files which may be slower for non-DoD users and to avoid other technical difficulties that may be encountered. Offerors are also responsible for submitting files in the format specified and consistent with requirements stated elsewhere in this solicitation. Files that cannot be opened, or are otherwise missing the required content are the responsibility of the Offeror.
PIEE system will record the date and time of package submittal. The date and time of package submittal recorded in PIEE shall govern the timeliness of any proposal submission. LATE PROPOSALS WILL
NOT BE CONSIDERED.
Hard Copy submission of proposals will be required in accordance with the following:
The HARD COPY SF330 submissions shall be delivered by MAIL ONLY within 5 business days of the due date for electronic submission. Firms should check with their intended courier to ensure they have the proper identification credentials to access Naval Station Norfolk. NOTE: Hard copy SF330s shall mirror the electronic versions submitted. In the event of discrepancy between the electronic and hard copies, the electronic copy received by the due date and time will be the governing document.
Hand delivered proposals will not be accepted.
Interested firms shall submit one (1) hard copy of the SF330 and 2 PDF CDs with searchable bookmarks for ease in navigation.
SF330 submissions shall be labeled
“SF330 SUBMISSION FOR N4008521R0275, ATTN: AMANDA BRICKER; DO NOT OPEN IN
MAIL ROOM”.
Express Mail to:
Naval Facilities Engineering Command, Mid-Atlantic 9324 Virginia Avenue Building Z-140, Room 225 Norfolk, Virginia 23511 Attn: Amanda Bricker, CON22
PROPOSALS THAT ARE HAND CARRIED WILL NOT BE ACCEPTED.
It is the sole responsibility of the Offeror to obtain the solicitation files, along with any amendments, from Opportunities (www.sam.gov).
If an SF 254/SF 255 is submitted for this solicitation, it will not be reviewed or considered. As required above, provide verifiable evidence that your firm is permitted by law to practice the professions of Architecture or engineering (e.g., state registration number).
Responses are due no later than 01 March 2022 at 2:00 pm (Local Time). Late responses will be handled in accordance with FAR 52.215-1.
amanda.l.bricker.civ@us.navy.mil
Inquiries concerning this procurement should include solicitation number and title and be forwarded via email to the point of contact. Inquiries concerning the Synopsis shall be received no later than 14 calendar days prior to the SF-330 due date. Late submissions may not be answered.
7.0 SELECTION CRITERIA
Firms responding to this synopsis will be evaluated to determine the most highly qualified firms to perform the required services in accordance with the published selection criteria. Failure to comply with instructions, or provide complete information may affect the firm’s evaluation or disqualify the firm from further consideration. Evaluation criteria (1) through (4) are considered most important and are equal among themselves; criteria (5) through (7) are of slightly less importance and are equal among themselves; criteria (8) is of the least importance and will be used as a tie-breaker among technically equal firms. Specific selection criteria include:
1. Specialized Experience
2. Professional Qualifications and Technical Competence
3. Past Performance
4. Quality Control
5. Program Management and Capacity
6. Firm Location
7. Commitment to Small Business
8. Volume of Work
7.1 Criterion 1-Specialized Experience (SF330, Part I, Section F):
Firms will be evaluated on specialized experience in performance of services similar to those anticipated under this contract through evaluation of experience in:
a) Designing and providing full construction drawings and specifications for various facility projects; including applying sustainability concepts through an integrated, cost effective design approach;
b) Prepare Design-Build RFP packages; including environmental surveys, geotechnical reports and schematic design concepts;
c) Experience preparing preliminary design deliverables such as concept plans, facility planning studies, including; developing facility requirements, preparing engineering evaluations, project scope, and unit guidance or parametric cost estimating;
d) Designing projects that demonstrate experience with Virginia codes, laws and permitting procedures;
e) Building Code Analysis and Life Safety Code Analysis; and
f) Providing construction phase services (shop drawing review, record drawings preparation, construction inspection services, and owner’s manuals)
Firms may be considered more favorably by demonstrating the following:
1. Experience designing projects to Navy or other DoD agencies criteria (such as: UFC, ECB, Mil Stds., NAVFAC DB Master RFP templates, UFGS, etc.)
2. Demonstrated experience to Navy facility projects, demonstrating capability of AE firm and individual team members (AE staff, key personnel, sub-consultants) to develop/prepare Regional DD1391 using MII cost estimating software.
3. Demonstrated experience providing Value Engineer Study or Cost and Schedule Risk Analysis (CSRA) per FC 1-300-09N.
NOTE: Project examples that include only inspection and condition assessment effort and associated reports do NOT demonstrate specialized experience and will NOT be considered services similar to those anticipated under this contract.
Submission requirements: Provide seven (7) projects completed within the past seven (7) years immediately preceding the date of issuance of this notice that best demonstrate specialized experience of the proposed team in the areas outlined above. Sufficient information to determine the date of completion the project must be included in the project description or the project will not be considered.
Provide at least one example project demonstrating experience with a final construction cost $30M or more. If more than the maximum number of projects are submitted, the Government will only evaluate the first seven (7) projects in the order submitted. Offerors must clearly define the professional service role performed by offeror in relationship to the project owner. For Design-Build projects, where the firm’s role is Designer of Record and firm performed professional services of full design plans and specifications for Prime Contractor will be evaluated as design-bid-build experience. For item b) only experience where firms prepared the design-build RFP package will be considered services similar to those anticipated under this contract.
All projects provided in the SF330 must be completed by offeror’s office/branch/regional office proposed to manage and perform work under this contract. Projects not meeting this requirement will be excluded from consideration in the evaluation. To enable verification, firms should include the DUNS number along with each firm name in the SF330 Part 1, Section F, block 25, “Firm Name” Include a contract number or project identification number in block 21. Include an e-mail address and phone number for the point of contact in block 23(c). In block 24, include in the project description the contract period of performance, date of project completion (MM/DD/YEAR), award contract value, current contract value, define professional service role and a summary of the work performed that demonstrates relevance to specialized experience as outlined above. For projects performed as a subcontractor or a joint venture involving different partners, specifically indicate the value of the work performed by the offeror and identify the specific roles and responsibilities performed by the offeror or team member on the project. If the project description does not clearly delineate the work performed by the entity/entities offering/teaming on this contract, the project may be eliminated from consideration.
NOTE 1: If the firm is a joint venture, projects performed by both members of the joint venture should be submitted; however, if there are no projects performed by the joint venture, projects may be submitted for either member of the joint venture, not to exceed a total of seven (7) projects, but greater consideration may be given where projects are demonstrated for the joint venture and/or both members of the joint venture.
Projects shall be submitted on the SF-330 at Part I, Section F and shall be completed projects. Projects not completed will be excluded from evaluation consideration. For submittal purposes, a task order on an IDIQ contract is considered a project, as is a stand-alone contract award. Do not submit an IDIQ contract as an example project. The Government will not evaluate information provided for an IDIQ contract. Submitted projects that do not conform to this requirement will not be evaluated.
NOTE 2: Date of project completion is defined as date of final design acceptance by client. For full design projects, date of project completion is the date of final signed sealed plans & specifications delivered to client. For DB RFP preparation, date of project completion is the date of final RFP document submission to client. For DB RFP representing Contractor as Designer-of-Record (DOR), date of project completion is the date of final design acceptance by client. For Design Development/DD1391 and Studies/Investigations, date of project completion is the date of final submission of design development/DD1391 and/or report to customer. A project may not be considered if insufficient information is provided to clearly show the date of completion.
All information for Criterion 1 should be submitted in the SF330, Part I, Section F of the. The Government WILL NOT consider information submitted in addition to Part 1, Section F in evaluation of Criterion 1.
7.2 Criterion 2-Professional Qualifications (SF330, Part I, Sections E & G):
Firms will be evaluated on professional qualifications, competence, and experience of the proposed key personnel in providing services to accomplish the tasks required under this contract, including participation in example projects as outlined in the SF330, Part 1, Section G. Key personnel are individuals who will have major contract or project management responsibilities and/or will provide unusual or unique expertise. Specific disciplines that must be included in key personnel are Project Managers, Quality Control Manager, Architects, Landscape Architects, Civil Engineers, Structural Engineers, Mechanical Engineers, Electrical Engineers, Geotechnical Engineers, Cost
Engineers, Certified Interior Designers and licensed Fire Protection Engineers. Registered Communication Distribution Designer (RCDD), Certified Technology Specialist-Designer (CTS-D), and Certified Value Specialist (CVS).
Submission Requirements:
SF330, Part I, Section E. Provide resumes for all proposed key personnel that illustrate experience in the work proposed under this contract. Resumes are limited to two (2) pages and should indicate:
professional registration, certification, licensure and/or accreditation in appropriate disciplines; cite recent (within the past ten (10) years) project-specific experience in work relevant to the services required under this contract and indicate proposed role in this contract. At a minimum, resumes should indicate academic qualifications, professional licensure, supplemental training or certificates, and total years’ professional experience. State whether team members are U.S. Citizens. The AE shall indicate whether the key personnel hold a security clearance, and if so, at what level. Indicate participation of key personnel in example projects in the SF330, Part 1, Section G.
7.3 Criterion 3-Past Performance (SF330, Part I, Section H):
Firms will be evaluated on past performance with Government agencies and private industry in terms of work quality, compliance with schedules, cost control, and stakeholder/customer satisfaction. Evaluating past performance and experience will include information provided in Past Performance Questionnaires (PPQs) or CPARS for Criterion 1 projects and may include customer inquiries, Government databases, and other information available to the Government including contacts with points of contact in other criteria. NOTE: Past performance information for projects listed under Criterion 1 may be given greater weight.
Submission Requirements:
SUBMIT A COMPLETED CPARS EVALUATION FOR EACH PROJECT UNDER CRITERION 1.
IF A COMPLETED CPARS EVALUATION IS NOT AVAILABLE, the Past Performance Questionnaire (PPQ) (Attachment (A)) included in this notice is provided for the firm or its team members to submit to the client for each project included under Criterion 1, Specialized Experience. DO
NOT SUBMIT A PPQ WHEN A COMPLETED CPARS IS AVAILABLE.
IF A CPARS EVALUATION IS NOT AVAILABLE, ensure correct phone numbers and email addresses are provided for the client point of contact. For Design-Build contracts, if the Offeror was not both the Prime Contractor (JV partner or single entity) and Designer of Record on a project, the design-build contractor may complete and provide a PPQ for the AE design partner/Designer of Record.
Completed PPQs should be submitted with your SF330. If the firm is unable to obtain a completed PPQ from a client for a project(s) before the response date set forth in this notice, firms should complete and submit with their responses the first page of the PPQ (Attachment (A)), which will provide contract and client information for the…
This is the start of the file's text. The full file is on GovTribe.