N4008522R2535 Amend 03.pdf

PDF 147 KB Posted

Attached to
Civil and Paving Multiple Award Construction Contract Federal contract opportunity
Solicitation number
N4008522R2535
Issued by
Department of the Navy Naval Facilities Engineering Command

About this file

This document provides an amendment to a solicitation for multiple award construction contracts. The solicitation is for up to four indefinite-delivery, indefinite-quantity construction contracts to perform work at Marine Corps Base Camp Lejeune, Marine Corps Air Station Cherry Point, and other military installations within the Marine Corps Installation East area of responsibility. Work will include construction and paving projects predominantly valued between $150,000 and $10 million. This solicitation is set aside for HUBZone small businesses. The amendment answers nine questions from potential offerors to clarify aspects of the solicitation such as the description of the seed project, size of relevant experience projects, inclusion of joint venture and mentor-protege agreements, submission requirements, and page limits. No changes are made to the response date by this amendment.

View the file

Other files for this federal contract opportunity

Other files attached to Civil and Paving Multiple Award Construction Contract, newest first.
File Type Posted
22R2535 Pricing Sheet.pdf PDF
N4008522R2535 Amend 02.pdf PDF
22R2535 DWG Amend02.pdf PDF
Site Visit Roster.pdf PDF
Construction Experience Project Data Sheet.pdf PDF
N4008522R2535 Amend 01.pdf PDF
RFP N4008522R2535.pdf PDF
22R2535 DWG_Part2.pdf PDF
22R2535 DWG_Part3of3.pdf PDF
22R2535 Specs.pdf PDF
22R2535 DWG_Part1.pdf PDF
Construction Experience Project Data Sheet.pdf PDF
PPQ.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFIC T ON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO.

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLIC TION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 11)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPIRATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

1 3

AMENDMENT NO. 0003 7/20/22

5. PROJECT NO. (If applicble) 200081

N40085

NAVFAC Mid-Atlantic Resident Officer in Charge of Construction 1005 Michael Road Camp Lejeune, NC 28547-2521

See Item 6

✘ N40085-22-R-2535

6/28/22

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

20-0081, Paving Parking Lot G480 Amendment 0003

The time and date for receipt of proposals is unchanged.

This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of a proposal.

See Continuation Page(s) Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

N4008522R2535 Amendment 03

Continuation Sheet

1. Question: The seed project for this MACC is paving parking lot G480 – should this be the description shown on page 3 of the solicitation? With the quantity of 95,000,000 Each listed, it is unclear what should be written on the line for net amount.

Answer: The line item description on the solicitation represents the basic award for the contract, which has a Not To Exceed value of $95,000,000. No pricing shall be included on this line item. Provide pricing for the seed project on the “Pricing Sheet” provided in the attachments in SAM.gov.

2. Question: On Page 9 of 51, the Corporate Experience factor criteria indicates offerors are to submit projects with a final construction cost between $50K - $1M, however on Page 5 of 51, Paragraph 1.3 indicates task orders will predominantly range between $150K - $10M. If we included projects for Corporate Experience that exceed $1M as indicated under Factor 1 – Corporate Experience will the projects be considered relevant?

Answer: A construction project in excess of $1 million dollars will be considered relevant, as long as it meets all other criteria stated by the RFP.

3. Question: Under Factor 1 – Corporate Experience, the size of relevant past construction projects is listed as a size of $50,000 to $1,000,000. Should this be changed to $50,000 to $10,000,000? The solicitation notes that the maximum for anticipated projects is $10,000,000, not $1,000,000.

Answer: No, the majority of projects awarded under this MACC will fall within the $50,000 to $1,000,000 range. Projects in excess of $1 million that demonstrate Corporate Experience will be considered relevant, as long as it meets all other criteria stated by the RFP.

4. Question: Please clarify if the Government would like both Joint Venture Agreements and SBA approved Mentor-Protégé Agreements or one or the other to be included in the offerors submission.

Answer: Provide any agreements that apply to the company or companies that will be submitting the proposal.

5. Question: Please clarify if the Government would like offerors to include Joint Venture/MPA information under (b) Non-cost/price Factors, Factor 1-Corporate Experience, f). If not there, please specify where in the submission offerors are to include the requested information.

Answer: Yes. Information is also required for each contractor who is part of the partnership/joint venture under Factor 2- Safety.

6. Question: Would the Government consider allowing offerors to submit proposals through the PIEE Solicitation Module in an effort to reduce environmental impacts of hard copy submissions?

N4008522R2535 Amendment 03

Answer: No, only hard copy proposals will be accepted.

7. Question: The Government states that relevant projects, in regard to size, will have a value of $50,000-$1,000,000. Does this mean the majority of task orders anticipated under this contract will fall within that range?

Answer: Yes.

8. Question: Are subcontractor letters of commitment included in the page count under (b) Non-cost/price Factors, Factor 3-Management Approach, (i)?

Answer: Trades and services that will be subcontracted should be identified within this narrative but the letters of commitment from the subcontractors will not count towards the page limit.

9. Question: Block 13-A of the SF 1442 states to submit one original and four copies. Section 00 21

00, Instructions, requires one original plus one copy for the price factor, and one original plus two copies for the non-price factors. Are we to assume that the section 00 21 00 requirements take precedence over the SF 1442’s requirements?

Answer: Follow the guidelines under Section 00 21 00 Instructions.