About this file

AMENDMENT_0003.pdf

View the file

Other files

File Type Posted
AMENDMENT_0004.pdf PDF
AMENDMENT_0002.pdf PDF
B2_Amendment_001_08-01-19.pdf PDF
Attachment_F_-_Price_Proposal_Form.pdf PDF
AMENDMENT_0001.pdf PDF
20190724_B2_SITE_VIST_LIST.pdf PDF
Attachment_B__SECNAV_5512_(KITTERY).pdf PDF
Attachment_A_PPII_log.doc DOC document
N4008519R9123.pdf PDF
Attachment_C_-_Construction_Experience_Data_Sheet.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

SOLICITATION NO. N40085-19-R-9123 DESIGN-BID-BUILD (DBB), REACTOR SERVICING SHIP SUPPORT, BUILDING 2, PORTSMOUTH NAVAL

SHIPYARD, KITTERY, MAINE

The purpose of this amendment is to provide additional PPI responses.

The proposal due date has been extended to 29 August 2019, not later than 2:00 PM EDT.

See Continuation Page(s).

1. CONTRACT ID CODE PAGE OF PAGES

J 1 6

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 20-Aug-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008519R9123

X 9B. DATED (SEE ITEM 11)

25-Jun-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

20-Aug-2019

CODE

NAVFAC MID ATLANTIC

ACQUISITION CORE

9324 VIRGINIA AVENUE

NORFOLK VA 23511-3095

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008519R9123

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0003

GC

PPI#

Section/ page no.

Paragraph Reference

Drawing Number Question Response

26 14 21 23 In reviewing the project documents, it appears the specifications are calling for one type of elevator and the drawings show a different type. Please clarification what type of elevator you want.

The specifications call out the correct desired elevator type; a geared traction elevator.

27 ED101 On Drawing ED101 Note 7 states to demo a temporary disconnect feeding an adjacent building. What size disconnect need to be removed and is there cabling/wiring that will also need to be removed?

Removals Keynote 7 indicates that the temporary power disconnect is to be removed "by others". The associated conduit and cables will also be removed "by others".

28 ED101 On Drawing ED101 in reference to note 10 and the removal of the cable and conduit associated with the (2) phone boxes. What shall we consider for cable and lengths in each conduit?

Refer also to sheet ED202, Removals Keynote 5. These cabinets are understood to be no longer in use. The removal of cables is to permit removal of conduits down to just below slab level. For bidding purposes, assume 20 conduits per box.

Most conduits are empty.

For bidding purposes per box, assume (4) # 16 copper cables in each of 4 conduits.

29 ED101 On Drawing ED101 note 16, how long is the conduit to be removed or where does it terminate?

For bidding purposes, assume this conduit is 70 feet long and it terminates on the exterior of the building.

30 ED102 On Drawing ED102, Are there any batteries to be removed in the DC room?

The electrical equipment identified as "DC" is shown on Sheet ED102 in Storage Room 108, Removals Keynotes 6, 7, 8 and 9 refer to equipment which was once powered by a shipyard DC system. There is no "DC Room." There are no batteries to be removed.

31 ED102 Can an existing DC one-line drawing be provided?

Refer to response to #20.

There is no DC one line available.

32 ED102 On Drawing ED102, The AC unit, break room condensing unit and CU/? shown to be demoed. Where are these three units fed from and what size conduit is feeding them?

For bidding purposes, assume power wiring to be removed from each of the three items of equipment as

(4) # 6, 1 1/4-inch conduit.

For bidding purposes, assume these three items of equipment are fed from Panel PP1, Refer to Sheet ED101 for location of panel

PP1.

33 ED104 On drawing ED104, Note 2 & 3.” Remove items on wall above 8’’x8’’x72’’ wireway” What are the items above the wireway to be removed?

The starters and combination starters, along with associated conduit and wire, which are identified by Removals keynotes 1 and 2 are the items to be removed.

34 ED501 ED501, can dimension for the pad mounted switchgear and transformer be provided?

The information provided on ED501 includes transformer size and voltage, manufacturer and a model number, along with the approximate weight based upon name plate information attached to the unit. Refer to project Civil Sheet CX101, existing Keynote 30 and removals keynote 7, for approximate foot print of this equipment and its concrete base.

35 Spec Section 01 45 00

1.5.2 The quality assurance

specification 014500 indicates commissioning is being procured through the Architect / Engineer per specification

014500.0020 section

1.5.2. However, the

commissioning specification 019100.15-

1.1 indicates that the prime contractor is to procure services through with commissioning as a first-tier sub. Please clarify who is to carry the cost of commissioning.

A-E will provide commissioning.

36 Please confirm that all of the equipment in specification 11 31 13 Electric Kitchen Equipment will be paid for through CLIN 0004 – Planned Modification Item 1, Furniture, Fixtures and Equipment.

Yes, that is correct.

37 When does the Navy expect to award this project and at what point does the 459 days of the contract duration start?

If the contract duration starts months before the building is unoccupied in March 2020, will the contractor be allowed more time for the work?

THE GOVERNMENT

INTENDS TO AWARD

THE PROJECT FIRST

QUARTER OF PHYSCAL

YEAR 2020. THE

BUILDING WILL

REMAIN OCCUPIED

UNTIL MARCH 5 2020.

THE BUILDING

COMPLETION DATE

WILL BE APRIL 01 2021.

CONTACT DAYS WERE

BASED OFF DECEMBER

30 2019 AWARD.35

38 Because of the comprehensiveness of the shoring for the exterior masonry and the widespread hazardous

CONTRACT

COMPLETION DATE

WILL REMAIN THE

SAME

material removals required, the general contractor would not be able to start any new construction in the building for 5 months after the March 2020 occupancy cut-off date.

This would leave only 10 months for construction if the contract duration started in March 2020. Can the contract duration be extended?

39 Due to the complexity of the project and multiple subcontractor clarifications needed, can the bid date be extended by another week?

Bid date will be extended from August 23rd to August 29th.

40 EP601 Panelboard PP1 calls out for a 400amp GFI breaker for the outside receptacle at stair tower

2. The one lines and panel schedule calls for a 3 wire panelboard. It is not possible to have a GFI breaker in a 3 wire panelboard as a neutral is required for a GFI

In lieu of providing a 400amp GFCI breaker as presently scheduled for PP-1

– 37,39,41, provide that breaker as a 400-amp shunt trip breaker with 120-volt shunt trip coil. Adjacent to Panel PP-1, provide a 400 amp, 3 phase, 3 wire in-line ground fault detection system. The ground fault detection system to consist of a 400 amp, 480 volts, 3 phase, 3 wire ground fault sensor and relay, a set of current transformers, NEMA 3R enclosures for both components, and wiring a 120-volt circuit through the ground fault sensor system to provide power to the coil on the 400-amp shunt trip breaker to disconnect power when a ground fault condition is detected.

Provide manufacturers wiring diagrams as a Shop Drawing for this system.

Field adjust settings per manufacturer recommendations. Provide 120-volt shunt trip circuit from panel LP-1 –

20, presently scheduled as a spare, 20/1 breaker. Basis of Design for 400 amp ground fault sensor: Bender Inc:

Linetraxx RCMA 423 for 3 phase, 3 wire systems. Basis of design for 400 amp CT products : Bender Inc, W.AB series with both DC and AC sensing, 400 amp rated.

(End of Summary of Changes)