Amd02_198033.pdf
PDF 366 KB Posted
- Solicitation number
- N4008519B8033
About this file
Amd02_198033.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amd04_198033.pdf | ||
| 60021279.pdf | ||
| Amd03_198033.pdf | ||
| 60021281.pdf | ||
| 60021280.pdf | ||
| Amd01_198033.pdf | ||
| Solicitation_198033.pdf | ||
| N4008517B0094_Dwgs_Part2.pdf | ||
| N4008517B0094_Dwgs_Part1.pdf | ||
| N4008517B0094_Specs.pdf | ||
| N4008519B8033_PreSolic_170094.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ACQR5602134 170094
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
See SF30 Block 14 Continuation pages
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 09-Apr-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008519B8033
X 9B. DATED (SEE ITEM 11)
12-Mar-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
09-Apr-2019
CODE
NAVFAC MID ATLANTIC
ROICC CAMP LEJEUNE
1005 MICHAEL ROAD
CAMP LEJEUNE NC 28547-2521
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008519B8033
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0002
Question 1. Form 30 for Amendment 1 does not indicate if amendments must be signed and turned in with the bid. Is acknowledgement on Form 1442 sufficient?
Answer 1. Yes, acknowledgement on the Standard Form 1442 is acceptable.
Question 2. This project will generate the following materials with potential for recycling and future use:
Topsoil from shoulder widening Common borrow soil material from culvert excavations ABC from shoulder widening along Sneads Ferry road at the Ammo Dump Concrete from pipe and headwall removal Steel and Aluminum from pipe and headwall removal
Can these materials be deposited at the base landfill or recycling center rather than disposed of off base?
Answer 2. Topsoil, common fill and ABC gravel can be taken to Pogeyman’s Mound (intersection of Sneads Ferry Rd. and Marines Rd.) and placed onsite for future use by the Base.
Segregated by material type, DO NOT MIX. Concrete material (pipes/headwalls) shall be disposed of off base at the contractor’s expense. Steel and Aluminum pipes can be taken to the Base Landfill metal pile on the Recycling Lot on Piney Green Rd.
Question 3. The 3 culvert replacements on Sneads Ferry Road are going to be time consuming tasks due to the depth of excavation, the number of utilities to protect and work around, and the amount of water that must be pumped around. The time required for these replacements while maintaining traffic in a one way pattern will be more than twice that required if the road could be closed. There are no intermediate contract time requirements for the one way traffic operation.
Would the ROICC entertain a temporary detour of Sneads Ferry traffic for each site? This will result in less total time impact to Sneads Ferry Traffic and increase the quality of the new crossings while reducing the cost.
Answer 3. Contractor can close down Sneads Ferry Road to replace these culverts provided advanced notice (1 month minimum advance and anticipated outage duration) so detours can be planned and outages advertised to the public through PMO. Access MUST be maintained to the
N4008519B8033
Ammo Supply Point (ASP) at all times during construction from one side or the other so Marines can continue training operations. Contractor cannot have both culvert crossing on either side of the ASP closed at the same time.
Question 4. Will the engineer consider 5” of Asphalt Base Course in lieu of 10” of ABC for the widening?
Answer 4. Yes, this is acceptable.
Question 5. Is it the intention of the Engineer to place sod following the pavement backup for the entire length of the widening on both roads? If so, can a width be specified?
Answer 5. Yes, provide sod to the limits of the Contractor's actual disturbance.
Question 6. Is there an approved permit covering the storm drainage improvements?
Answer 6. No permits required for this work.
Question 7. Can you provide as-built documents for the existing utilities located at the culvert replacements?
Answer 7. The utilities shown on the plans represent the as-built conditions. A utility locate was completed at each site as a part of the design effort. This is the best data available.
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 11-Apr-2019 02:00 PM to 18-Apr-2019 02:00 PM.
(End of Summary of Changes)