Amendment_0003.pdf
PDF 143 KB Posted
- Solicitation number
- N4008519B6606
About this file
Amendment_0003.pdf
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Building 240, Replace Waste Water Treatment Plant (WWTP) Headw orks, Naval Support Activity (NSA) Hampton Roads, Northw est Annex (NWA), Chesapeake, Virginia
The bid due date of Thursday, 17 January 2019 @ 1400 EST remains unchanged.
Modification issued to provide PPI responses.
See SF30 Block 14 Continuation Page.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 11-Jan-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008519B6606
X 9B. DATED (SEE ITEM 11)
03-Dec-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
11-Jan-2019
CODE
COMMANDING OFFICER
NAVFAC MID-ATLANTIC
9742 MARYLAND AVENUE
NORFOLK VA 23511-3095
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008519B6606
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0003
(1) Provide responses to PPIs 1, 2, and 3:
PPI
No.
Date Received QUESTION GOVERNMENT RESPONSE
Posted on Amend No.
1 12/20/2018
01 20 00.00 20 - PRICE AND PAYMENT
PROCEDURES - P-1.3 - Will a cost loaded NAS be a requirement for this project? Will progress payments be made based upon an Earned Value Report or a schedule of prices based invoice with an estimate for voucher?
A cost loaded NAS will not be required. A schedule of value will suffice for progress payments.
2 12/20/2018
01 32 16.00 20 - SMALL PROJECT
CONSTRUCTION PROGRESS
SCHEDULES - P1.3.1 - Is Microsoft Project 2010 Settings and Parameters the software requirement for this project? Is Primavera P6 or Suretrak acceptable?
Remove Spec Section 01 32
16.00 20 and replace with Section 01 32 17.00 20, as provided as Attachment H
3 12/20/2018
01 32 16.00 20 - SMALL PROJECT
CONSTRUCTION PROGRESS
SCHEDULES - Typically Cost Loading is not a requirement for this Small Project NAS Specification. Please confirm that a cost loaded NAS will be required.
A cost loaded NAS will not be required. A schedule of value will suffice for progress payments.
(End of Summary of Changes)