AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Building 240, Replace Waste Water Treatment Plant (WWTP) Headw orks, Naval Support Activity (NSA) Hampton Roads, Northw est Annex (NWA), Chesapeake, Virginia

The bid due date of Thursday, 3 January 2018 is hereby extended to Thursday, 10 January 2018 @ 1400 EST.

This modification is issued to provide site visit log, full size draw ings, and PPI responses.

See SF30 Block 14 Continuation Page.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 28-Dec-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008519B6606

X 9B. DATED (SEE ITEM 11)

03-Dec-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

28-Dec-2018

CODE

COMMANDING OFFICER

NAVFAC MID-ATLANTIC

9742 MARYLAND AVENUE

NORFOLK VA 23511-3095

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008519B6606

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0001

(1) Provide site visit log:

Provided as Attachment F Site Visit Log.

(2) Provide full size drawings:

NAVFAC Drawing Nos. 12774064 – 12774085 (22 sheets) were previously provided scaled to 8.5”x11” sheets.

Full size (34”x 22” scale) drawings have been provided as ATTACHMENT G 1582924 DWGS_FULL SIZE.

(3) Provide responses to PPIs 6 – 8, and 10:

PPI

No.

Date Received QUESTION GOVERNMENT RESPONSE

Posted on Amend No.

6 12/20/2018

During the site visit it was discussed that access to the site for materials and equipment would be via a narrow gravel road with access off of Mile Post Rd. and ending at the Fabric Tension Bldg. on the northeast side of the site. During periods of wet weather it is likely that this road could be damaged by construction traffic. Will it be the KTRs responsibility to maintain and repair the road.

Yes. It will be the responsibility of the KTR to maintain/repair the road during construction and that the road shall be brought back to its original state if damage does occur upon completion of the work.

7 12/20/2018

Will KTR personnel also be required to access the site via the gravel road accessed from Mile Post Rd? Can KTR personnel park on the gravel lot on the southside of the site?

KTR personnel may enter the site via the WWTP's primary entrance/exit to minimize disturbance on the gravel road.

KTR personnel may park on the gravel lot on the southside of B-392, but may be asked to relocate vehicles when the bldg.'s dumpster is serviced, typically 1-2 times annually. 0001

8 12/20/2018

Is there a location for the KTR's field office that is in an accessible location and within 100 linear feet of available electricity (100 amps minimum)?

Yes. Locations are available for a field office and within close proximity to a power source. 0001

N4008519B6606

10 12/20/2018

Concerning the bid date of January 3, 2019, we are having difficulties with subcontractors being able to provide a price by this date due to the holiday's. Is there any chance of a bid extension forthcoming to give all bidders more time to provide an accurate proposal?

Bid due date is extended to Thursday, 10 January 2018 @

1400 EST.

(End of Summary of Changes)