Attachment_C_-_Price_Proposal_Form.docx
DOCX document 23 KB Posted
- Attached to
- REPAIR NORTH AND SOUTH HELIX HOUSE ICE SHIELDS
- Solicitation number
- N4008517R5068
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_0005.pdf | ||
| Amendment_4.pdf | ||
| Amendment_3.pdf | ||
| HelixHouse.pdf | ||
| ICE_SHIELD_ATTENDEES.pdf | ||
| Amendment_1.pdf | ||
| Attachment_B_-_Past_Perf_Questionnaire.docx | DOCX document | |
| Attachment_A_-_Construc_Exp_Proj_Data_Sheet.docx | DOCX document | |
| N4008517R5068_Solicitation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRICE PROPOSAL FORM
1.1 CONTRACT LINE ITEMS
Provide the Contract Line Item Number (CLIN) lump sum price for the items below:
CLIN 0001 – BASE PRICE: The price for CLIN 0001 shall be the total price for SubCLINs 000101 through 000110, complete in accordance with the drawings and specifications, but not including the work indicated or specified to be provided under CLINs 0002, 0003, 0004, and 0005.
SubCLINs
| 0101 General Requirements (Divisions 00 and 01) | $_______________ | |||
| 0102 Site staging, preparation, and restoration | $_______________ | |||
| 0103 Temporary supports and protection components and associated engineering | $_______________ | |||
| 0104 Equipment: Cranes and lifts | $_______________ | |||
| 0105 Testing and inspections | $_______________ | |||
| 0106 Demolition of ice shields | $_______________ | |||
| 0107 Provision of ice shields | $_______________ | |||
| 0108 Hot-dip galvanizing of ice shields components | $_______________ |
0109 Roofing system and associated components removal and repair and
| re-installation of associated components | $_______________ | |
| 0110 Roof deck removal and repair | $_______________ |
TOTAL PRICE FOR CLIN 0001: $_________________
CLIN 0002 – OPTION 1, NORTH HELIX HOUSE ICE SHIELDS REPLACEMENT (CONTRACT PERIOD 2): Total price, complete in accordance with drawings and specifications.
TOTAL PRICE FOR CLIN 0002: $________________
CLIN 0003 – OPTION 2, HOT-DIP GALVANIZED COATING AND LIQUID TOP COAT SYSTEM OF SOUTH HELIX HOUSE ICE SHIELDS AND COMPONENTS: Total price, complete in accordance with drawings and specifications.
TOTAL PRICE FOR CLIN 0003: $________________
CLIN 0004 – OPTION 3, SOUTH HELIX HOUSE STEEL PRESERVATION: Total price, complete in accordance with drawings and specifications.
TOTAL PRICE FOR CLIN 0004: $________________
CLIN 0005 – OPTION 4, HOT-DIP GALVANIZED COATING AND LIQUID TOP COAT SYSTEM OF NORTH HELIX HOUSE ICE SHIELDS AND COMPONENTS: Total price, complete in accordance with drawings and specifications.
TOTAL PRICE FOR CLIN 0005: $________________
TOTAL PRICE FOR ALL CLINs 0001 THROUGH 0005: $_________________
1.2 CONTRACT LINE ITEM NOTES
a. Submit offers using this Price Proposal Form and these Contract Line Item Notes.
b. A firm-fixed proposed price is required for all CLINs. No provision is made for economic price adjustment.
c. Except when it is determined in accordance with FAR 17.206 (b) not to be in the Government’s best interest, the Government will evaluate offers for award purposes by adding the total price for the options and planned modifications (CLINs 0002 through 0005) to the total price for CLIN 0001. In accordance with FAR 52.217-5, evaluation of options will not obligate the Government to exercise the option(s).
d. The Government reserves the unilateral right to award CLINs 0002 through 0010 to the Contractor at the proposed price within 365 calendar days after the contract award. If CLIN 0002 and/or CLIN 0005 are/is exercised, the period of performance will be extended by 365 days. If CLIN 0003 are/is 0004 are exercised, the contract completion date remains unchanged, as the work can be performed concurrently with the work in the base price.
e. The Government may reject an offer as nonresponsive if it is materially unbalanced as to prices for the basic requirement and the option quantities. An offer is unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.
f. If any CLIN 0002 through 0005 is exercised, additional bonding and consent of surety is required. Consequently, the Performance Bond must reflect 100 percent of the aggregate amount of all items.
1.3 UNIT PRICES
Complete the following unit prices, to be used in the event an adjustment needs to be made to the contract price after contract award. The quantities listed are estimates only. Should the actual quantity of any of these items required to complete the work vary from that listed, the unit price will be used to adjust the total contract price in accordance with the contract clause entitled FAR 52.211-18,Variation in Estimated Quantity.
Unit Prices Form
| Item |
| Description |
| Quantity |
| Unit |
| Unit Price |
| 0001a |
| Provide anchor bolts connection at downlead A-frame base plate. |
| 1 |
| EA |
| $________ |
| 0001b |
| Removal of existing concrete roof deck and provision of concrete roof deck repair at ice shield connections. |
| 1 |
| CF |
| $________ |
| 0001c |
| Removal and reinstallation of rubber roof pavers. |
| 1 |
| SF |
| $________ |
| 0001d |
| Removal of existing paver mat and provision of paver mat. |
| 1 |
| SF |
| $________ |
| 0001e |
| Removal of existing roofing system and provision of roofing system repairs. |
| 1 |
| SF |
| $________ |
| 0001f |
| Removal of existing roofing penetration pocket and provision of penetration pocket and associated accessories and components at ice shield connections. |
| 1 |
| EA |
| $________ |
| 0001g |
| Removal of existing roofing penetration pocket and provision of penetration pocket and associated accessories and components at downlead A-frame connections. |
| 1 |
| EA |
| $________ |
| 0001h |
| Removal of existing aluminum sheeting at bushing area and provision of 0.050-inch thick aluminum sheeting including welding. |
| 1 |
| SF |
| $________ |
| 0001i |
| Removal and reinstallation of existing aluminum paver clamp and associated components. |
| 1 |
| EA |
| $________ |
| 0001j |
| Removal and reinstallation of existing aluminum guard rail system including aluminum 4 x 4 x 1/4 angles and kick plates and associated components. |
| 1 |
| LF |
| $________ |
| 0001k |
| Removal and reinstallation of existing fiberglass guard rail system including fiberglass 4 x 4 x 1/4 angles and kick plates and associated components. |
| 1 |
| LF |
| $________ |
| 0001l |
| Provide roof pavers. |
| 1 |
| SF |
| $________ |
| 0001m |
| Removal of asbestos containing material discovered during construction. |
| 1 |
| SF |
| $________ |
1.4 DESCRIPTION OF CLINS AND SUBCLINS
The total amount for CLIN 0001 shall provide the full project scope, excluding options, complete and in place in accordance with the drawings and specifications even if not specifically listed below.
CLIN 0001 is subdivided as follows:
000101: General Requirements (Divisions 00 and 01) includes the price for all work associated with the specified requirements of Divisions 00 and 01.
000102: Site staging, preparation, and restoration includes the price for all work associated with mobilization and demobilization and associated miscellaneous work required.
000103: Temporary supports and protection components and associated engineering includes the price for all work associated with delegated design for temporary protection of the existing bushings, and for temporary shoring and supports required to accomplish the work, and associated miscellaneous work required.
000104: Equipment includes the price for all work associated with cranes and lifts required to accomplish the work of the project including mobilization, setup, and demobilization, and associated miscellaneous work required.
000105: Testing and inspections includes the price for all work associated with all testing and inspections, and associated miscellaneous work required.
000106: Demolition of ice shields includes the price for all work associated with demolition of ice shields and associated miscellaneous work required.
000107: Provision of ice shields includes the price for all work associated with provision of ice shields and associated miscellaneous work required.
000108: Hot-dip galvanizing of ice shields components includes the price for all work associated with hot-dip galvanizing of ice shields components, and associated miscellaneous work required.
000109: Roofing system and associated components removal and repair and reinstallation of associated components includes the price for all work associated with the removal of portions of the roofing system (paver mat, 3-ply SBS roofing, tapered roofing insulation, aluminum sheeting, penetration pockets, etc.) and associated components (rubber roof pavers, aluminum paver clamps, aluminum guard rail system, fiberglass guard rail system, etc.) and the provision of roofing system repairs (paver mat, 3-ply SBS roofing, tapered roofing insulation, aluminum sheeting, penetration pockets, etc.) and reinstallation of associated components (rubber roof pavers, aluminum paver clamps, aluminum guard rail system, fiberglass guard rail system, etc.), and associated miscellaneous work required.
000110: Roof deck removal and repairs includes the price for all work associated with the removal of portions of the concrete roof deck and repair of the roof deck, and associated miscellaneous work required.
Option CLINs are described as follows:
0002 Option 1: North Helix House Ice Shields Replacement (Contract Period 2) as indicated in CLIN 0001.
0003 Option 2: Hot-Dip Galvanized Coating and Liquid Top Coat System of South Helix House Ice Shields and Components.
0004 Option 3: South Helix House Steel Preservation includes all work associated with previously unexecuted work on NAVFAC Contract N40085-16-B-9322, specifically Option 2.
0005 Option 4: Hot-Dip Galvanized Coating and Liquid Top Coat System of North Helix House Ice Shields and Components.