Amend 0001_Atch(1)_Govt Response.pdf

PDF 67 KB Posted

Attached to
Integrated Solid Waste Management Services at U. S. Marine Corps Air Station Iwakuni, Japan
Solicitation number
N4008425B0003
Issued by

About this file

This document is a Government Pre-Award Inquiry Form for Solicitation No. N4008425B0003, addressing Integrated Solid Waste Management Services at U.S. Marine Corps Air Station Iwakuni, Japan. The form contains seven pre-solicitation questions and corresponding government responses, covering topics such as non-recurring work, mercury and fluorescent lamp disposal, building availability, electrical access, and joint venture agreement modifications. Amendment No. 0001 was issued to clarify several points, including confirmation that mercury lamp disposal is included in the contract, Building 714 will be unavailable during the contract period, and washing machines and dryers will be collected and disposed of outside the installation site. The responses provide detailed guidance on contractor responsibilities and operational expectations for the waste management services contract.

View the file

Other files

File Type Posted
N4008425B00030001_Amend0001.pdf PDF
Amend 0001_Atch(2)_Amendment_lis.pdf PDF
Atch 4_Escort Request Form_ Entry-Exit.pdf PDF
Atch 3_ RepresentationsR.pdf PDF
SF 1449 - N4008425B0003.pdf PDF
Atch 2_0200000_09_ELINS_ISWM_250328.xlsx XLSX spreadsheet
Atch 5_Pre-Award Inguirty Form.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION NO. N4008425B0003

Integrated Solid Waste Management Services at U.S. Marine Corps Air Station Iwakuni, Japan

GOVERNMENT PRE-AWARD INQUIRY FORM Attachment (1)

Page Section Para.

1 13-Jun-25 21 SF+1449+-

+N4008425B0003 (1)

6-a-ⅰ It says, “As the need exists for the performance of Non-Recurring work...”, but please explain the specific conditions for the occurrence of non-recurring work.

Non-Recurring work orders are used to address needs that can't be met through Recurring work. These are issued as formal task orders when the government requires a specific, one-time service.

2 13-Jun-25 PWS The PWS only mentions fluorescent lamps. Is it correct to understand that mercury lamps are not covered by this contract? If there is a misunderstanding, please let us know the planned quantity to be disposed of under this contract.

Collection, transportation, and disposal of mercury lamps are included in this contract. The language in J-1503030-11, Historical Quantities has been updated accordingly to clarify this per A0001 (Attachment 3)

3 13-Jun-25 PWS /J-0200000-

Will #714 be unavailable at the start of this contract? If so, when will the dismantling of#714 begin? Will you provide an alternative area other than #714 during the dismantling period?

That is correct, Building 714 will be unavailable. The Government-furnished Facility (GFF) area, delineated by a pink line and marked as "B.# 714 Segregation Facility" on the drawing J-0200000-04, will continue to be available for the contractor's use. There are no plans to provide an alternative area and there is currently no date established for when the project at Bldg. 714 will begin.

The Government has noticed that page 1 of 2 of drawing J-0200000-04 includes size information for Building 714. As this may have caused confusion, the drawing has been updated accordingly.

4 13-Jun-25 PWS /J-0200000-

Currently, we are using the electrical outlets inside of B#714, but if #714 becomes unavailable, where should we get electricity from?

Please refer to Spec Item 2.4.4, Government-Furnished Utilities in Annex 0200000. The Contractor may submit a request to use Government-provided electricity. Upon approval of the request, the Contractor will be permitted to tap into the electricity and/or domestic water. If the request is not approved, the contractor may install a generator to supply the necessary power.

5 18-Jun-25 298 CUI//FEDCONATTA

CHMENTJ-1503030-

11HISTORICALQUA

NTITIES

It states, “Washing machines and dryers will be collected by contractors and disposed of/recycled outside the installation site.” This is not included in the QRP, and I understand that these items are not to be delivered to the recycling center. Is that correct?

That is correct. 0001

6 18-Jun-25 What measures should be taken if the disposal contractor (disposal site) or transportation contractor specified in the initial joint venture agreement is changed or added?

The contractor is responsible for notifying the Contracting Office in writing of any changes to the Joint Venture Agreement and for submitting all required, updated permissions and licensees as detailed in the SOW.

7 18-Jun-25 We understand that the fluorescent lamps and mercury lamps currently stored in Building #714 are not covered by this contract. Is this understanding correct?

Collection, transportation, and disposal of mercury lamps are included in this contract. The language in J-1503030-11, Historical Quantities has been updated accordingly to clarify this per A0001 (Attachment 3).