AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The reason for this amendment is to add a revised Exhibit Line Item schedule. This w ill replace w hat w as initially issued. No other revisions are required at this time. There w ill not be an extension of time to submit offers.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 19-Sep-2013
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N40083-13-R-2636
X 9B. DATED (SEE ITEM 11)
13-Sep-2013
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
19-Sep-2013
CODE
NAVFAC MIDWEST PWD CRANE
NAVAL SUPPORT ACTIVITY B#2516
300 HIGHWAY 361
CRANE IN 47522-5001
N40083 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N40083-13-R-2636
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Revised the Exhibit Line Items. See attached.
(End of Summary of Changes)
LINE ITEM DESCRIPTION QTY UOM UNIT PRICE AMOUNT
A001 HARVESTING 1-3 TREES 3 EA
This line item will involve all materials and equipment to cut, skid, load and transport selected trees to the storage site. Unloading will be performed by NAVFAC employees using Navy certified Weight Handling Equipment. It is assumed that this line item will be used when the specific location contains 3 or less trees to be harvested. For this line item, estimate the total cost of transporting all trees at the specified location to the storage facility. (Per Location Price) YEAR 2
A002 HARVESTING 4-6 TREES 3 EA
This line item will involve all materials and equipment to cut, skid, load and transport selected trees to the storage site. Unloading will be performed by NAVFAC employees using Navy certified Weight Handling Equipment. It is assumed that this line item will be used when the specific location contains no less than 4 and no more than 6 trees to be harvested. For this line item, estimate the total cost of transporting all trees at the specified location to the storage facility. (Per Location Price) YEAR 2
A003 HARVESTING 7-9 TREES 3 EA
This line item will involve all materials and equipment to cut, skid, load and transport selected trees to the storage site. Unloading will be performed by NAVFAC employees using Navy certified Weight Handling Equipment. It is assumed that this line item will be used when the specific location contains no less than 7 and no more than 9 trees to be harvested. For this line item, estimate the total cost of transporting all trees at the specified location to the storage facility. (Per Location Price) YEAR 2
A004 MOBILIZATION/DEMOBILIZATION
This line item will involve the costs associtated with mobilizing contractor and equipment to the location of trees marked for harvest. This line item is to mobilize/demobilize from off-station to on-station. YEAR 2 3 EA
A005 MOBILIZATION/DEMOBILIZATION
This line item will involve the costs associtated with mobilizing contractor and equipment to the location of trees marked for harvest. This line item is to mobilize/demobilize from one location on-station to another location on-station.
YEAR 2 3 EA
A006 HARVESTING 1-3 TREES 3 EA
This line item will involve all materials and equipment to cut, skid, load and transport selected trees to the storage site. Unloading will be performed by NAVFAC employees using Navy certified Weight Handling Equipment. It is assumed that this line item will be used when the specific location contains 3 or less trees to be harvested. For this line item, estimate the total cost of transporting all trees at the specified location to the storage facility. (Per Location Price) YEAR 3
A007 HARVESTING 4-6 TREES 3 EA
EXHIBIT LINE ITEMS
This line item will involve all materials and equipment to cut, skid, load and transport selected trees to the storage site. Unloading will be performed by NAVFAC employees using Navy certified Weight Handling Equipment. It is assumed that this line item will be used when the specific location contains no less than 4 and no more than 6 trees to be harvested. For this line item, estimate the total cost of transporting all trees at the specified location to the storage facility. (Per Location Price) YEAR 3
A008 HARVESTING 7-9 TREES 3 EA
This line item will involve all materials and equipment to cut, skid, load and transport selected trees to the storage site. Unloading will be performed by NAVFAC employees using Navy certified Weight Handling Equipment. It is assumed that this line item will be used when the specific location contains no less than 7 and no more than 9 trees to be harvested. For this line item, estimate the total cost of transporting all trees at the specified location to the storage facility. (Per Location Price) YEAR 3
A009 MOBILIZATION/DEMOBILIZATION
This line item will involve the costs associtated with mobilizing contractor and equipment to the location of trees marked for harvest. This line item is to mobilize/demobilize from off-station to on-station. YEAR 3 3 EA
A010 MOBILIZATION/DEMOBILIZATION
This line item will involve the costs associtated with mobilizing contractor and equipment to the location of trees marked for harvest. This line item is to mobilize/demobilize from one location on-station to another location on-station.
YEAR 3 3 EA
A011 TRANSPORTATION
This line item will involve the transporting of a load of trees to the Charlestown Navy Yard in Boston Massachusetts. Loading of the logs will be performed by NAVFAC heavy equipment employees using Navy Certified Weight Handling Equipment. The trip to the Shipyard is approximately 1,035 miles one way and directions will be provided. For this line item, estimate the total cost of transporting a full load (as determined by DOT weight regulations) for the transport of a load of logs to the Charlestown Navy Shipyard in Boston, MA. This ELIN is for the period 10/2014 through 10/2015. YEAR 2 15 EA
A012 TRANSPORTATION
This line item will involve the transporting of a load of trees to the Charlestown Navy Yard in Boston Massachusetts. Loading of the logs will be performed by NAVFAC heavy equipment employees using Navy Certified Weight Handling Equipment. The trip to the Shipyard is approximately 1,035 miles one way and directions will be provided. For this line item, estimate the total cost of transporting a full load (as determined by DOT weight regulations) for the transport of a load of logs to the Charlestown Navy Shipyard in Boston, MA. This ELIN is for the period 10/2015 through 10/2016. YEAR 3 10 EA