- Repair Exterior Leaks-Griffin Terrace
- Solicitation number
- N40080-19-R-0117
About this file
N40080-19-R-0117-A0004 Amendment
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NSN 754-01-152-8070 STANDARD FORM 30 (REV. 10-83
PREVIOUS EDITIONS UNUSABLE Prescribed by GSA Page 1 of 2 FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
PAGE OF PAGES
1 2
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
16 August 2019
4. REQUISITION /PURCHASE REQ. NO.
5. PROJECT NO. (if applicable)
MAXIMO # B6FXNG
6. ISSUED BY CODE N40080 7. ADMINISTERED BY (If other than Item 6) CODE
Public Works Department/FEAD 181 Wainwright Road USNA, Halligan Hall, Stop 21A Annapolis, MD 21402-5013
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
X 9A. AMENDMENT OF SOLICITATION NO.
N40080-19-R-0117
9B. DATED (see item 11)
10A. MODIFICATION OF CONTRACT NO.
DUNS NO. TIN# 10B. DATED (see item 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of
Offers is extended, X is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning one copy of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or © By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATION OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGE SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor X is not, is required to sign this document and return Copy to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section heading, including solicitation/contract subject matter where feasible).
SB MACC MECHANICAL (FY19) – RFP for “DESIGN/BID-BUILD: REPAIR EXTERIOR LEAKS-GRIFFIN
TERRACE” , USNA ANNAPOLIS, MD”
Request for proposal is amended as follows:
See Page 2 for details.
All other terms and conditions remain the same.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A as heretofore changed, remains unchanged and in full force and effect.
15A NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
Bridgette M. Garcia, Contracting Officer
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
BY__________________
(Signature of Contracting Officer)
16C. DATE SIGNED
16 August 2019
NSN 754-01-152-8070 STANDARD FORM 30 (REV. 10-83
PREVIOUS EDITIONS UNUSABLE Prescribed by GSA Page 2 of 2 FAR (48 CFR) 53.243
The purpose of this Amendment No. 0004 to N40080-19-R-0117 is to:
1. Clarify the RFI response #2 with the additional questions submitted
RFI# 2a. Are these allowances to be included as part of one of the two line items on the bid form? Please clarify.
RFI# 2b. Do we need to list these allowances and their individual prices? If so, should we create an attachment for the bid form?
NAVFAC Response: Include the allowances in one of the two line items on the bid form.