Revised_Spec_01_11_00_8-31-18.doc

DOC document 37 KB Posted

Attached to
Award Notice N4008018C3036 Carpet Replacement B449, 1490, 516 and 2272
Solicitation number
N4008018B3036
Issued by

About this file

Revised_Spec_01_11_00_8-31-18.doc

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Carpet Replacement Bldg. 449, 1490, 516, 2272 2018

SECTION 01 11 00

SUMMARY OF WORK

08/15

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for Contractor Quality Control approval. for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work shall include, but will not be limited to lifting existing modular furniture and removing existing carpet and vinyl base at various buildings. All work will be conducted after hours (4:00 p.m.)

and government escort will be provided by clients.

The new work shall include, but will not be limited to: installing twenty-four inch by twenty-four inch (24” x 24”) carpet tiles and vinyl base in various building throughout the base as follows:

B449-Contractor shall provide all labor and equipment necessary to lift office cubicles and remove approximately 18,500 SF of direct glue down sheet carpet, with the exception of room 203 and approximately 2,500 linear feet (LF) of wall base, with the exception of room 203.

transitions, and clean and scrape floors Install new

24oz – 24” X 24”, direct glue down carpet tiles with neoprene backing, 4” vinyl wall base, and transitions. Colors to be chosen by client.

B516-Contractor shall provide all labor and equipment necessary to lift office cubicles, move office furniture, and demo approximately

14,200 SF of carpet tiles, approximately 2,340 linear feet(LF)of wall base, 1” wide transitions approximately 60’, and clean and scrape floors. Install new 24oz – 24” X 24”, direct glue down carpet tiles with neoprene backing,4” vinyl wall base, and transitions. Colors to be chosen by client.

B1490-Contractor shall provide all labor and equipment necessary to lift office cubicles, move office furniture, and to remove approximately 7,900 square feet of existing direct glue down sheet carpet, and approximately 550 linear feet (LF) of wall base, and adhesive to install new 24 x 24 carpet tile in building 1490 rooms 40,102, and 74. Install 4” cove base to match carpet selection. Colors to be chosen by client.

B2272- Contractor shall provide all labor and equipment necessary to lift office cubicles, move office furniture, and demo remove approximately 27,000 square feet of existing direct glue down sheet carpet and approximately 180 linear feet (LF) of wall base, and install new 24 x24 carpet tile at building 2272.

Replace Carpet in Atriums Floors 2-5 and Rooms 150.5, 162, 167, 234.1, 354, 360, 443.1, 443.2 and Elevators B1, B2 and B3 and

C1 and C2. Carpet will match texture. Colors to be chosen by client.

B2272 Admiral’s Suite fifth floor–Contractor shall provide all labor and equipment necessary to remove approximately 6,055 square feet of existing sheet carpet and approximately 77 square feet of vinyl floor tile in kitchenette area and install new sheet carpet and vinyl tile flooring. Existing wood base board shall not be removed. If damage Contractor shall replace wooden base board in kind at the

Contractor’s expense. New Sheet carpet shall match existing color and texture. Color for vinyl floor tile to be chosen by client

1.2.2 Location

The work is located at Naval Air Station/Warfare Center, Patuxent River Maryland. The exact location will be shown by the Contracting Officer.

1.3 OCCUPANCY OF PREMISES

Buildings will be occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location in the work area.

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.4 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section -- Section 01 11 00 Page 2

File details come from the government source that posted it.